Approval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)

Approved Committee 1 paper

AI summarySalford City Council extends Arboricultural Services contract with Greater Manchester TreeStation for 12 months, valued at £250,000 per year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFirst of two optional 12-month extensions
Money£250,000 per yearTotal £566,000 including extensions
What happens nextExtension starts 1 April 2026Ends 31 March 2027
Who it affectsAll council-owned trees citywideIncludes all Salford wards

What was decided

Councillor Youd, as Lead Member for Finance and Support Services and chair of the Procurement Board, approved a 12-month extension of the Arboricultural Services contract with Greater Manchester (GM) TreeStation. Report P1, P2

The extension runs from 1 April 2026 to 31 March 2027, taking the total contract value to £566,000, of which £316,000 has been awarded to date. Report P3, P4, P5

The extension is needed to maintain the full range of tree management services across council-owned land and to meet statutory duties while a service review is completed. Report P16, P26, P28

Why

DEFRA guidance stresses the role of local government in safeguarding public safety and protecting tree health, and continuing with the current contractor avoids disruption. Report P14, P15

The contractor has delivered social value of £39,538 so far, with a further £64,170 committed, equating to a 13.18% social value add. Report P20

An in-house comparison showed higher cost and reduced resilience: £889,500 initial capital and £592,500 annual running costs for three teams, against no capital outlay and lower risk under the contractor. Report P21, P22, P23, P24, P25

What happens next

The 12-month extension will run from 1 April 2026 to 31 March 2027, subject to ongoing satisfactory performance, insurance, social value, and statutory and ethical compliance. Report P5, P26, P27

A review of service requirements will be undertaken during the extension to inform future procurement, with a further 12-month extension available if appropriate. Report P7, P26

The 2026/27 Environments capital unsupported borrowing, which funds the extension, is subject to council approval in February 2026. Report P44

The money

  • £250,000 Annual value of the contract extension Report P3
  • £566,000 Total contract value including extensions Report P4
  • £316,000 Amount awarded to date under the contract Report P4
  • £889,500 Initial capital investment estimated for three in-house teams Report P22
  • £592,500 Annual operational cost estimated for three in-house teams Report P22
  • £39,538 Social value delivered by the contractor since 1 June 2024 Report P20
  • £64,170 Further social value commitment from the contractor Report P20

Options considered

  • Chosen: Extend the existing contract with Greater Manchester (GM) TreeStation for 12 months. Maintains proven service, avoids disruption, transfers operational and liability risk, requires no capital investment, and allows time for a service review. Report P15, P19, P23, P24, P25, P26
  • Rejected: Do not extend the contract. Risk of disruption, civil liability or criminal penalties from failing to meet legal duties on council-owned trees. Report P36, P37, P45

Implications

  • Legal: The extension is permitted under SCC standing orders and PCRs 2015; original tender documents made provision for two 12-month extensions, so the risk of challenge is extremely low. Report P41, P42, P47
  • Risk: Risk is assessed as Medium: not extending could leave the council exposed to civil liability or criminal penalties for failing to inspect and maintain trees, Tree Preservation Orders, conservation area rules, and wildlife laws. Report P35, P36, P37, P45
  • Financial: Funded from the Approved Capital Programme, specifically 2026/27 Environments capital unsupported borrowing, subject to council approval in February 2026. Report P38, P39, P44
  • Equalities: Equality screening confirms a neutral impact; no new or worsening impacts identified and a full Equality Impact Assessment is not required. Report P32, P33, P34
  • Climate: Arboricultural services support environmental and climate objectives through sustainable tree management and biodiversity benefits, aligned with the Salford Climate Change Strategy. Report P31, P49, P50

Who and where

  • All Salford wards, through management of all council-owned trees citywide Report P16, P55, P56
  • Greater Manchester (GM) TreeStation as the contracted supplier (SME, supplier registration 06495111) Report P3, P6
  • Salford City Council Place Directorate, as lead service group and contract manager Report P6, P53
  • VCSEs and local supply chain recipients of social value activities Report P20

Timeline

  • 8 May 2024: Original contract awarded by Procurement Board Report P9, P10
  • 1 June 2024: Original Arboricultural Services contract commenced Report P5, P7, P16
  • February 2026: Council approval sought for 2026/27 capital borrowing to fund the extension Report P44
  • 23 March 2026: Procurement Board decision date (this report)
  • 31 March 2026: Current contract end date Report P5, P7
  • 1 April 2026: Start of the 12-month extension period Report P5
  • 31 March 2027: End of the first 12-month extension period Report P5

Plain English for the jargon

  • Arboricultural Services: The full range of work needed to manage and maintain trees, including pruning, felling, stump removal, emergency call-out, and disposal of arisings.
  • DEFRA: Department for Environment, Food and Rural Affairs, which issued guidance on the role of local government in protecting trees and woodlands.
  • PSR Competitive Process: Procurement route used for the original award, meaning the call-off was made under a framework or competitive process rather than a fully open tender.
  • SCC: Salford City Council, used in references to standing orders and the Social Value Portal.
  • Social Value: Wider benefits delivered through a contract, such as local employment, spending in the local supply chain, or donations to voluntary, community and social enterprises (VCSEs).
  • Tree Preservation Order: A legal order made by the council to protect specific trees or woodlands from being cut down, topped, lopped, uprooted, damaged or destroyed without consent.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5i

Resolved

Salford City Council – Record of Decision I Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: for an Extension of Contract for Arboricultural Services , as detailed in the table below: Detail required Answers Title/ Description of Contracted Service/Supply/Project Arboricultural Services Procurement Reference numbers (DN and CR number supplied by Procurement) DN710469 / S1254 Name of Successful Contractor Greater Manchester (GM) TreeStation Supplier Registration Number (to be supplied by Procurement 06495111 Proclass Classification No. (to be completed by procurement) Type of organisation (to be supplied by Procurement) Other Status of Organisation (to be supplied by Procurement) SME Contract Value (£) £250,000 per annum Total contract value £ (including extensions) £566,000 ( £ 316,000 awarded to date), Contract Duration 12 month extension Contract Start Date 01/06/2024 Contract End Date 31/03/2026 Optional Extension Period 1 12 months Optional Extension Period 2 12 months Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Ian Worsley Tel: [phone removed] Lead Service Group Place How the contract was procured? (to be supplied by procurement) PSR Competitive Process Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign The Mayor’s Employment Charter N/A EC: Committed to the principles outlined in the Mayor’s Employment charter N/A EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer N/A ? The Reasons are : The original contract awarded to Greater Manchester (GM) Treestation that commenced on 1 st June 2024 and is due to expire on 31 March 2026 included two 12 ? month extensions. This decision allows for the first extension of the contract by a period of 12 months. Extending the contract supports Salford City Council in the citywide management and upkeep of all Council ? owned trees, providing the full range of arboricultural services required to maintain the tree population safely, effectively, and in alignment with statutory obligations and recognised best practice. Options considered and rejected were : Non-extension of the contract. Assessment of Risk : Medium - Salford City Council has several legal obligations and responsibilities regarding the maintenance of trees on council-owned land. The Council must inspect and maintain trees to prevent foreseeable harm, comply with Tree Preservation Orders and conservation area rules, respect wildlife laws, and follow its own tree management policy. A delay or failure to agree an extension to the existing contract for Arboricultural Services may result in disruption and lead to civil liability or criminal penalties. The source of funding is : Capital Budget. Legal Advice obtained : It is an established principle that an existing public contract is capable of being extended (or modified providing any modification does not affect the overall nature of the contract) , and CSO’s also allow for contract extensions to be made, where ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That the Procurement Board recommends (Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board)/ (Paul Dennett, City Mayor):

Approve the extension of the Contract for Arboricultural Services as detailed in the table below:

Detail required Answers Contract Reference DN710469 / S1254 (to be supplied by procurement) Title/Description of Contracted Arboricultural Services Service/Supply/Project Name of Contractor Greater Manchester (GM) TreeStation Type of organisation Other (to be supplied by Procurement) Status of Organisation SME (to be supplied by CoProcurement) Value of Contract Extension (£) £250,000 per annum

Total value of Awarded (including extension period) £ 566,000 ( £ 316,000 awarded to date),

Existing Contract Term 01/06/2024 to 31/03/2026 Extension Period 01/04/2026 to 31/03/2027

Sample D – Extension of Contract Contact Officer (Name & Ian Worsley- [phone removed] number) Lead Service Group Place Funding Source Capital Programme Ethical Contractor (EC): Yes Mayor’s Employment Charter EC: Committed to sign the N/A Mayor’s Employment Charter EC: Committed to the principles outlined in the N/A Mayor’s Employment Charter EC: Accredited Living Wage Yes Employer EC: Committed to becoming Accredited Living wage N/A Employer

Executive summary

This report requests a 12‑month extension to the existing Arboricultural Services contract, which commenced on 1 June 2024 and is due to expire on 31 March 2026. The original contract allows for two additional 12‑month extensions. Extending the contract does not alter its nature or scope..

BACKGROUND DOCUMENTS:

Report of the Strategic Director Place “Approval to Award the Contract for Arboricultural Services” 8th May 2024

Record of Decision Procurement Board 8th May 2024

KEY DECISION:

Yes

DETAILS:

Recent DEFRA guidance issued on behalf of the Parliamentary Under Secretary of State for Nature, emphasises the critical role local government plays in safeguarding public safety and protecting the health of trees and woodlands. The continuity of the

Sample D – Extension of Contract existing contract with Greater Manchester (GM) TreeStation will maintain a proven, cost effective service and avoid disruption.

The contract commenced on 1 June 2024 and runs until 31 March 2026, with two available 12‑month extension periods. The contract supports Salford City Council in the citywide management and upkeep of all Council‑owned trees, providing the full range of arboricultural services required to maintain the tree population safely, effectively, and in alignment with statutory obligations and recognised best practice.

Core Services Delivered • Tree maintenance (pruning, reductions, lifting, pollarding) • Tree felling and stump removal • Emergency call-out and storm-response • Disposal of all arisings • Safety-compliant arboricultural operations across all Council-managed land

Delivery is monitored via agreed metrics and regular reporting with key indicators including service delivery, response times, quality, health and safety, customer satisfaction, environmental performance and Social Value. These are monitored on a monthly and quarterly basis.

Best value is secured through proactive contract management. Daily oversight, regular site visits, and checks on quality, safety, compliance, and productivity ensure works meet required standards. Monthly review meetings with the contractor address performance, costs, workloads, and response times, allowing issues to be resolved quickly. This approach keeps the service efficient, well-managed, and cost-effective throughout the contract

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)Report 149 KB DownloadRead as text

At this meeting

Whole meeting
3To approve, as a correct record, the minutes of the meeting held on Monday 9 March 2026On the agenda 5aApproval to go out to tender for the Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Approved 5bApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 Service (Gillian McLauchlan)On the agenda 5cAllied Health Professional Contract (Debbie Blackburn)Approved 5dApproval to go out to competition for Utility Coring Contract (Lee Lacking)Approved 5eThe purchase of three ex-demonstration Schmidt Swingo Road Sweepers from the NEPO Framework Agreement (Alan Fitzsimons)Approved 5fApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved 5gApproval to go out to tender for the delivery of Bikeability 2026-2029 (Simi Drummond)Approved 5hApproval for an Extension of Contract for Occupational Health Services - Greater Manchester Collaboration OH Services (Optima Health) (Karen Bird)Approved
5iApproval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)This decision
5jApproval to Award the Contract for renewal of non-half hourly (NHH) electricity supply (Majid Maqbool)Approved 5kApproval to Award the Unmetered Public Lighting Electricity contract (Majid Maqbool)Approved 5lApproval to go out to tender/ competition for Chapel Street/ Trinity Way Junction Procurement (Opu Anwar)Approved 5mPrimrose Hill Primary School, Increase in Construction Costs (Sean Leah/ Tracey Squirrell)Approved 8aApproval to Award the Contract for the Salford Healthy Child Programme, 0-19 service (Gillian McLauchlan)Approved 8bApproval to Award the Contract for CCBN Islington Active Neighbourhood Scheme (Anene Chiegboka)Approved

Who was there

5 of 8 attended
JC
Jim CammellInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, present
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Approval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)This decision
  2. Approval for an Extension of Contract for Statutory Homeless Supported Temporary Accommodation Contract at Abbott Lodge (Jane Barlow)Approved
  3. Approval for an Exception to Contractual Standing Orders to award an extension of the Technical and Highways Works Framework Agreement (Steve Hands/ Sharon Walls)Approved
  4. Approval for an Extension of Contract for Interpretation and Translation Services (Stephen Titley)Approved
  5. Approval for an Extension of Contract for the Management Agreement at Salford Innovation Forum (SIF) (Jo Ivison)Agreed
  6. Approval for an Extension of Contract for Occupational Health Services - Greater Manchester Collaboration OH Services (Optima Health) (Karen Bird)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open