Resolved
RESOLVED: That (1) the Strategic Director - Communities be authorised, in conjunction with Capita Symonds Ltd., to provisionally appoint Conlon Construction Limited of Preston as the preferred contractor for the project and for the Environmental and Technical Services Director to establish a target cost for the project; and (2) it be noted that the Chair of the Overview and Scrutiny Committee (Performance and Corporate Services) has given his consent, under Rule 17 of the Scrutiny Procedure Rules, for this decision to be treated as urgent and not subject to “call in” on the basis that any delay in the implementation of the decision will prevent the commencement of the intensive pre-contract cost agreement process which in turn will prevent the commencement and completion of works in accordance with the required Programme.
Word for word from the decision Sefton published for this meeting.
Source: modgov.sefton.gov.uk