Cabinet, Thursday 5 August 2010

Proposed Replacement Netherton Activity - Tenders

Approved Executive 1 paper

Cabinet approved this item on Thursday 5 August 2010. Below is the council's own wording, with the papers it was decided on.

Item80

Resolved

That (1) the basis for the funding of the project set out in Section 3 of the report be approved; (2) the agreed Target Cost, which together with contingency allowance totals £4,507,789 be accepted; and (3) the Head of Corporate Legal Services be requested to enter into a formal contract with the successful contractor.
Word for word from the decision Sefton published for this meeting. Source: modgov.sefton.gov.uk

Follow this further

Built from Sefton's papers

What the report saysPro

Report to Cabinet, 5 pages

REPORT TO: Cabinet th DATE: 5 August 2010

SUBJECT: Proposed Replacement Netherton Activity Centre Report on Tenders Received

WARDS AFFECTED: Ford, St.Oswald, Netherton & Orrell

REPORT OF: Peter Moore Environmental and Technical Services Director

CONTACT OFFICER: David Kay 0151 934 4527

EXEMPT/ No CONFIDENTIAL:

PURPOSE/SUMMARY:

This report is to advise Members of the final outcome of the tendering process and to seek approval for the acceptance of the agreed Target Cost.

REASON WHY DECISION REQUIRED:

To enable appointment of the successful contractor and to proceed with construction.

RECOMMENDATION(S):

It is recommended that:

(i) Cabinet notes and approves the basis for project funding as set out in paragraphs 3.1 to 3.4.

(ii) Cabinet approves acceptance of the agreed Target Cost, which together with Contingency allowance, totals £4,507,789.

(iii) Subject to (i) and (ii) above, the Head of Corporate Legal Services be requested to enter into a formal contract with the successful contractor.

KEY DECISION: No

FORWARD PLAN: Not Appropriate

IMPLEMENTATION DATE: Immediately following expiry of the call in period. ALTERNATIVE OPTIONS:

All alternative options have been considered and have been discounted.

IMPLICATIONS:

Budget/Policy Framework: Included within the Leisure Services Capital Programme is provision for this scheme totalling £5,600,000. This funding is provided through prudential borrowing (£5,200,000) and through an ‘Aiming Higher for Disabled Children’ Grant (£400,000).

There is potentially a maximum £1,500,000 Section 106 contribution to the scheme in connection with the Bellway Homes’ redevelopment of their Orrell Lane playing field site. This will be utilised to meet the cost of an all weather sports pitch and associated works with the balance addressing the cost of the Council’s funding underwrite of works already provided for within the current proposals.

Financial Details of the total financial implications are set out in paragraph 3.4 of the main report.

The overall scheme cost does not exceed the total funding available and Members are requested to authorise acceptance of the agreed Target Cost.

2010/ 2011/ 2012/ 2013/ 2011 2012 2013 2014 CAPITAL EXPENDITURE £ £ £ £ Gross Increase in Capital Expenditure

Funded by:

Sefton Capital Resources Specific Capital Resources

REVENUE IMPLICATIONS Gross Increase in Revenue Expenditure Funded by:

Sefton funded Resources

Funded from External Resources

Does the External Funding have an expiry N/A date? Y/N

How will the service be funded post expiry? N/A Legal: Not appropriate

Risk Assessment: Not appropriate

Asset Management: The proposed scheme will replace the existing building, which is currently in poor condition and will improve the leisure facilities within the local area.

The new activity centre will also provide a specialist sensory facility for children with special educational needs, and also provide office accommodation for children’s services SEN staff working within the local community.

CONSULTATION UNDERTAKEN/VIEWS

The Leisure and Tourism Director have been consulted and any comments have been taken into account in preparing this report.

FD472 – The Head of Corporate Finance & Information Services has been consulted and has no comments on this report

CORPORATE OBJECTIVE MONITORING:

Corporate Positive Neutral Negative Objective Impact Impact Impact 1 Creating a Learning Community √ 2 Creating Safe Communities √ 3 Jobs and Prosperity √ 4 Improving Health and Well-Being √ 5 Environmental Sustainability √ 6 Creating Inclusive Communities √ 7 Improving the Quality of Council Services and √ Strengthening local Democracy 8 Children and Young People √

LIST OF BACKGROUND PAPERS RELIED UPON IN THE PREPARATION OF THIS REPORT

Leisure Services Capital Programme 1.0 BACKGROUND

1.1The Netherton Activity Centre was a former 3-form entry Secondary School (Warwick Bolam High School), which due to falling school admissions was declared surplus to requirements as a school and closed in July 1986.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed Replacement Netherton Activity: TendersReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Sefton

Search all
  1. Proposed Replacement Netherton Activity - TendersThis decision
  2. Proposed Replacement Netherton Activity CentreNoted

More from Sefton Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Previous MeetingDecision Made: That the Minutes of the meeting held on 23 July 2026 be confirmed as a correct record. Decided Open
3 Sep 2026 Review of Adult Social Care Charging PolicyThe recommendations in the report had been developed following a review of Adult Social Care charging arrangements, e... Approved Open
3 Sep 2026 Approval of Legal Documentation for Academy Conversions – Voluntary ConversionsThe Archdiocese of Liverpool had determined that all Catholic schools in Sefton would become part of the Pope Francis... Agreed Open
3 Sep 2026 Procurement of Supported Lodgings Accommodation for Young People Aged 16+The proposed procurement would secure a compliant, regulated and more financially sustainable Supported Lodgings arra... Refused Open
3 Sep 2026 Fleet Replacement Street CleansingThe proposal to purchase a new fleet of 13 Small Mechanical Sweepers for the Street Cleansing Service would provide a... Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies