To align the end dates with the delayed start dates of the contracts. Alternative Options Considered and Rejected: All three contracts were currently due to end on 31 March 2026, as per the original contract documents, and the Council could decide not to change this date. In accordance with the provisions within the Contract, the Council agreed 2-year contract extensions with the Contractors. However, as the commencement dates were delayed when the original contracts were issued in 2016, recent advice had highlighted that the current end dates would result in the contracts running for a shorter term than tendered for. Therefore, not changing the end dates to align with the actual commencement of the contracts could result in challenge, a need to re-negotiate rates and potential compensation events.