(a) That approval be given to the budget variations of £3.4 m to the 2013/14 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2013/14 capital budget of £47.4m and the increase in the operating leasing by £0.26m to £1.84m. (b) That approval be given to the re-profiled capital budgets of £62.2m for 2014/15, £13.5m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4. (c) That the expenditure to date of £33.3m, representing 70.3% of the revised capital budget for 2013/14, with 92% of the year having elapsed, be accepted.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1The purpose of this report is to inform Members of the current position for the Council’s 2013/14 to 2016/17 capital programme taking into account the latest monitoring information on the progress of the schemes, any necessary budget increases and decreases and the re-profiling of budgets between 2013/14 and future years. The report reflects:
The re-profiled 2013/14 budget of £47.4m and the future years capital programme budget; Expenditure to date of 61.2% of the revised budget; A projected outturn in line with the re-profiled budget of £47.4m; and The current funding of the programme and its future affordability.
Recommendations
Members are asked to:
A. Approve budget variations of £3.4m to the 2013/14 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2013/14 capital budget of £47.4m and the increase in the operating leasing by £0.26m to £1.84m.
B. Approve the re-profiled capital budgets of £62.2m for 2014/15, £13.5m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4.
C. Accept the expenditure to date of £33.3m, representing 70.3% of the revised capital budget for 2013/14, with 92% of the year having elapsed.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1Risk assessments are undertaken as part of the evaluation of all capital bids.
3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions. 1 Cabinet 09 April 2014: Capital Monitoring – Period 11 2013/14
3.3Environmental appraisals are carried out for individual schemes as appropriate.
3.4Community consultations are carried out for individual schemes as appropriate.
Financial implications
4.1This report considers the capital spend within the capital programme for 2013/14 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.
Background
5.1The capital programme for 2013/14 and future years, was updated as part of the Capital Strategy 2013/14 to 2016/17 report, approved by Council 28 February 2013. This included updated allocations of capital grants and followed a review of internally financed schemes to re-prioritise schemes based on current priorities and to ensure the programme is affordable based on the projected level of capital resources available to the Council. The Council’s capital programme is subject to regular review and an updated Capital Strategy 2014/15 to 2016/17 was approved by Council on 27 February 2014.
6. Original and latest proposed capital programme for 2013/14
6.1The capital budget for 2013/14 is subject to change, the largest element being slippage from 2012/13 and re-profiling into future years. In Period 11 there has been a net budget decrease of £3.3m, compared to the position reported at Period 10 2013/14. Table 1 summarises the overall movement, between that already approved, and changes for Period 11 that require approval.
Table 1: Revised Capital Programme Period 11 2013/14 Service Area Agreed Capital Slippage and Period 11 Revised Programme - budget changes budget 2013/14 Capital Council approved to changes to Programme 28/02/13 Period 10 13/14 be approved Period 11 General Fund
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.