i) That net budget variations of £5.8m to the 2016/17 capital programme be approved, including cuts to capital receipts funded schemes of £4.4m; detailed in Appendix 1/Table 1 and the re-profiled 2016/17 capital budget of £60.2m. ii) That the re-profiled capital budgets of £43.1m for 2017/18 and £18.8m for 2018/19 and £1.8m for 2019/20 be approved as detailed in Appendix 1/Table 4. Including cuts to capital receipt funded schemes of £4.0m in 2017/18. iii) That the expenditure to date of £15.8m be accepted, representing 26% of the revised capital budget for 2016/17, with 50% of the year having elapsed. i) That net budget variations of £5.8m to the 2016/17 capital programme be approved, including cuts to capital receipts funded schemes of £4.4m; detailed in Appendix 1/Table 1 and the re-profiled 2016/17 capital budget of £60.2m. ii) That the re-profiled capital budgets of £43.1m for 2017/18 and £18.8m for 2018/19 and £1.8m for 2019/20 be approved as detailed in Appendix 1/Table 4. Including cuts to capital receipt funded schemes of £4.0m in 2017/18. iii) That the expenditure to date of £15.8m be accepted, representing 26% of the revised capital budget for 2016/17, with 50% of the year having elapsed.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1The purpose of this report is to inform Members of the current position for the Council’s 2016/17 to 2019/20 capital programme taking into account the latest monitoring information on the progress of the schemes, any necessary budget increases and decreases and the re-profiling of budgets between 2016/17 and future years. The report reflects:
The re-profiled 2016/17 budget of £60.2m and the future years capital programme budget; Expenditure to date of 26% of the revised budget; A projected outturn in line with the re-profiled budget of £60.2m; and The current funding of the programme and its future affordability.
Recommendations
Members are asked to:
A. Approve net budget variations of £5.8m to the 2016/17 capital programme, including cuts to capital receipts funded schemes of £4.4m; detailed in Appendix 1/Table 1 and the re-profiled 2016/17 capital budget of £60.2m.
B. Approve the re-profiled capital budgets of £43.1m for 2017/18 and £18.8m for 2018/19 and £1.8m for 2019/20 as detailed in Appendix 1/Table 4. Including cuts to capital receipt funded schemes of £4.0m in 2017/18.
C. Accept the expenditure to date of £15.8m, representing 26% of the revised capital budget for 2016/17, with 50% of the year having elapsed.
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1Risk assessments are undertaken as part of the evaluation of all capital bids.
1 Cabinet 09 November 2016: Capital Monitoring Report – Quarter 2 2016/17 3.2 Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.
3.3Environmental appraisals are carried out for individual schemes as appropriate.
3.4Community consultations are carried out for individual schemes as appropriate.
Financial implications
4.1This report considers the capital spend within the capital programme for 2016/17 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.
Background
5.1The capital programme for 2016/17 and future years, was updated as part of the Financial Strategy 2016/17 to 2018/19, approved by Council on 25 February 2016. This included updated allocations of capital grants and a review of and delivery schedule for schemes.
6. Original and latest proposed capital programme for 2016/17
6.1The capital budget for 2016/17 is subject to change, the largest element being slippage from 2015/16 and re-profiling into future years. In Quarter 2 there has been a net budget decrease of £5.8m, compared to the position reported at Quarter 1. Table 1 summarises the overall movement, between that already approved, and changes for Quarter 2 that require approval.
Table 1: Revised Capital Programme Quarter 2 2016/17 Service Area Agreed Capital Slippage and Quarter 2 Revised Programme - budget changes budget 2016/17 Capital Council approved to changes to Programme 25/02/16 Quarter 2 16/17 be approved Quarter 2 General Fund
Total Approved Budget 55,868,287 10,131,953 (5,834,850) 60,165,390 * Commissioning renamed Place & Enterprise. Brought forward budgets adjusted to reflect change of Council structure: Private Sector Housing transferred from Place & Enterprise (Commissioning) to Public Health and Strategic Asset Services transferred from Resources & Support to Place & Enterprise.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.