Resolved
That the Capital Monitoring Report Quarter 2 2015/2016 be noted.
Performance Management Scrutiny Committee noted this item on Wednesday 21 October 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Capital Monitoring Report Quarter 2 2015/2016 be noted.
1.1The purpose of this report is to inform Members of the current position for the Council’s 2015/16 to 2018/19 capital programme taking into account the latest monitoring information on the progress of the schemes, any necessary budget increases and decreases and the re-profiling of budgets between 2015/16 and future years. The report reflects:
The re-profiled 2015/16 budget of £62m and the future years capital programme budget; Expenditure to date of 23.2% of the revised budget; A projected outturn in line with the re-profiled budget of £62m; and The current funding of the programme and its future affordability.
Members are asked to:
A. Approve net budget variations of £3m to the 2015/16 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2015/16 capital budget of £62m. Including new allocations of capital receipt funding as follows: £86k for the Mere warden’s bungalow refurbishment.
B. Approve the re-profiled capital budgets of £40.9m for 2016/17 and £28.1m for 2017/18 and £70k for 2018/19 as detailed in Appendix 1/Table 4.
C. Accept the expenditure to date of £14.4m, representing 23.2% of the revised capital budget for 2015/16, with 42% of the year having elapsed.
1 Performance Management Scrutiny Committee 21st October 2015: Capital Monitoring Report – Quarter 2 2015/16
REPORT
3. Risk Assessment and Opportunities Appraisal
3.1Risk assessments are undertaken as part of the evaluation of all capital bids.
3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.
3.3Environmental appraisals are carried out for individual schemes as appropriate.
3.4Community consultations are carried out for individual schemes as appropriate.
4.1This report considers the capital spend within the capital programme for 2015/16 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.
5.1The capital programme for 2015/16 and future years, was updated as part of the Business Plan and Financial Strategy 2015/16 to 2016/17, approved by Council on 26 February 2015. This included updated allocations of capital grants and a review of and delivery schedule for schemes.
6. Original and latest proposed capital programme for 2015/16
6.1The capital budget for 2015/16 is subject to change, the largest element being slippage from 2014/15 and re-profiling into future years. In Quarter 2 there has been a net budget decrease of £3m, compared to the position reported at Quarter 1 2015/16. Table 1 summarises the overall movement, between that already approved, and changes for Quarter 2 that require approval.
Table 1: Revised Capital Programme Quarter 2 2015/16 Service Area Agreed Capital Slippage and Quarter 2 Revised Programme - budget changes budget 2015/16 Capital Council approved to changes to Programme 26/02/15 Quarter 1 15/16 be approved Quarter 2 General Fund
Commissioning 30,587,810 5,260,051 (1,492,077) 34,355,784 Adult Services 3,740,632 209,288 - 3,949,920 Children’s Services 7,777,002 4,648,707 (1,165,923) 11,259,786 Resources & Support 2,856,717 1,969,005 - 4,825,722
Total General Fund 44,962,161 12,087,051 (2,658,000) 54,391,212
Housing Revenue Account 6,581,090 1,331,937 (319,913) 7,593,114
Total Approved Budget 51,543,251 13,418,988 (2,977,913) 61,984,326 2 Performance Management Scrutiny Committee 21st October 2015: Capital Monitoring Report – Quarter 2 2015/16
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8 Appendix 1: Capital Monitoring Quarter 2Appendix | 1.1 MB | Download |
PDF |
Capital Monitoring Report Quarter 2 2015/2016Report | 204 KB | DownloadRead as text |
Follow Performance Management Scrutiny Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2020 | Financial StrategyThat the Medium Term – July 2020 – 2020/21 to 2025/26, be noted. | Noted | Open |
| 8 Jul 2020 | Financial Monitoring Report, Quarter 4 2019/20That the report be noted. | Noted | Open |
| 8 Jul 2020 | Future Work Programmei) That Climate Change and SEND be considered by the Committee at its meeting in July; and ii) That the Financial Str... | Decided | Open |
| 10 Jun 2020 | Minutes of the meeting held on 20th May 2020that the minutes of the Performance Management Scrutiny Committee meeting held on 20 th May 2020 be approved as a cor... | Approved | Open |
| 10 Jun 2020 | Quarter 4, 2019/20 Corporate Performance ReportThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.