Capital Outturn Report 2013/2014

Noted Finance 3 papers

Audit Committee noted this item on Thursday 26 June 2014. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED : That the report of the Head of Finance, Governance and Assurance be noted as follows: (a) That approval be given to budget variations of £17,700 to the 2013/14 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2013/14 capital budget of £47.4m. (b) That approval be given to the re-profiled capital budgets of £71.4m for 2014/15, including slippage of £6.6m from 2013/14, £13.7m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4. (c) That the outturn expenditure set out in Appendix 1 of £40.7m, representing 85.9% of the revised capital budget for 2013/14 be accepted. (d) That approval be given to the Highways and Transport programme of schemes for delivery in 2014/15 and authority be delegated to the Area Commissioner (South) in consultation with the Portfolio Holder to approve any changes to the implementation plan of schemes for delivery in 2014/15 within the parameters of the outline capital programme. (e) That approval be given to the setting aside of capital receipt of £1.35m to replace the self-financed prudential borrowing previously applied to finance the Solar PV schemes. This would generate an ongoing revenue saving from 2014/15. (f) That approval be given to retaining a balance of capita receipts set aside of £13.25m as at 31 st March 2014 to generate a Minimum Revenue Provision saving of £530,000 in 2014/15.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit Committee

Summary

1.1The purpose of this report is to inform Members of the final outturn position for the Council’s 2013/14 capital programme and the current position regarding the 2014/15 to 2016/17 capital programme taking into account the slippage following the closure of the 2013/14 programme, and any budget increases/decreases for 2014/15 and future years. The report reflects:

§ The re-profiled 2013/14 budget of £47.4m and the future years capital programme budget; § The outturn capital expenditure of £40.7m, representing 85.9% of the re-profiled budget for 2013/14; § An underspend of £6.7m, of which £6.56m has been slipped to 2014/15 and £115k of which is no longer required/available to the capital programme; and § The current funding of the programme and its future affordability.

Recommendations

Members are asked to:

A. Approve budget variations of £17,700 to the 2013/14 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2013/14 capital budget of £47.4m.

B. Approve the re-profiled capital budgets of £71.4m for 2014/15, including slippage of £6.6m from 2013/14, £13.7m for 2015/16 and £5.3m for 2016/17 as detailed in Appendix 1/Table 4.

C. Accept the outturn expenditure set out in appendix 1 of £40.7m, representing 85.9% of the revised capital budget for 2013/14.

1 Cabinet 4 June 2014, Audit Committee 26 June 2014, Council 17 July 2014: Capital Outturn – 2013/14 D. Approve the Highways & Transport programme of schemes for delivery in 2014/15 and delegate authority to the Area Commissioner South in consultation with the Portfolio Holder to approve any changes to the implementation plan of schemes for delivery in 2014/15, within the parameters of the outline capital programme.

E. Approve the setting aside of capital receipt of £1.35m to replace the self- financed prudential borrowing previously applied to finance the Solar PV schemes. This will generate an ongoing revenue saving from 2014/15.

F. Approve retaining a balance of capital receipts set aside of £13.25m as at 31st March 2014 to generate a Minimum Revenue Provision saving of £530,000 in 2014/15.

REPORT

3. Risk Assessment and Opportunities Appraisal

3.1Risk assessments are undertaken as part of the evaluation of all capital bids.

3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.

3.3Environmental appraisals are carried out for individual schemes as appropriate.

3.4Community consultations are carried out for individual schemes as appropriate.

Financial implications

4.1This report considers the capital spend within the capital programme for 2013/14 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.

Background

5.1The capital programme for 2013/14 and future years, was updated as part of the Capital Strategy 2013/14 to 2016/17 report, approved by Council 28 February 2013. This included updated allocations of capital grants and followed a review of internally financed schemes to re-prioritise schemes based on current priorities and to ensure the programme is affordable based on the projected level of capital resources available to the Council. The Council’s capital programme is subject to regular review and an updated Capital Strategy 2014/15 to 2016/17 was approved by Council on 27 February 2014.

6. Original and latest proposed capital programme for 2013/14

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Monitoring Period 12Appendix 1 1.1 MB Download
PDF
Highways ProgrammeAppendix 2 302 KB Download
PDF
Capital Outturn Report 2013/2014Report 197 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 5 attended
BW
Brian WilliamsChairman, present
MW
Michael WoodVice Chairman, present
JC
John CadwalladerCommittee Member, present
CM
Chris MellingsCommittee Member, present
MW
Mansel WilliamsCommittee Member, present

On this subject at Shropshire

Search all
  1. Capital Outturn Report 2013/2014This decision
  2. Revenue and Capital Outturn 2016/2017Noted
  3. Capital outturn 2015/16Approved
  4. Capital Outturn 2015 - 2016Approved
  5. Capital Outturn Report 2015/16Approved
  6. Capital Outturn Report - 2015/16Approved

More from Shropshire Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. Approved Open
16 Jul 2025 Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... Approved Open
16 Jul 2025 Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. Noted Open
16 Jul 2025 Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... Agreed Open
16 Jul 2025 Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies