Resolved
(a) That the contents of the report by the Director of Commissioning be endorsed and accepted. (b) That a further update be submitted to the Audit Committee in September 2014.
Audit Committee decided this item on Thursday 26 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
(a) That the contents of the report by the Director of Commissioning be endorsed and accepted. (b) That a further update be submitted to the Audit Committee in September 2014.
This report provides an update on the existing and emerging assurance and management controls and risk management arrangements within the Council. The report gives assurance on the robustness of governance arrangements for all change related activity arising from the Council’s 2014/17 Business Plan and Financial Strategy including service redesign, commissioning and service transitions to new delivery vehicles as well as IT enablement.
Members are asked to consider and endorse with appropriate comment, the contents of this report.
REPORT
3. Risk Assessment and Opportunities Appraisal
A robust approach to risk management is in place in relation to the 2014/17 Business Plan and Financial Strategy as well as the associated Directorate business plans. All service improvements identified in the plans have been linked to the Council’s strategic risks, where relevant. This provides assurance that the improvements support the mitigation of strategic risks and prevents the Council from compromising or increasing risk exposure.
Furthermore, all strategic, project and business planning risks are linked to the 4+1 outcomes (Your Council, Your Life, Your Environment, Your Money, Your Health). This is a new requirement as part of measuring performance and is in the process of being implemented. At a time of significant change, it is important that the Council can provide assurance that controls and mitigation are strong, and therefore all strategic risks are linked to the annual governance statement action plan points. This integrated approach to managing risks across all risk areas of the Council ensures that we are managing risk cohesively and robustly.
At a project level, working closely with the Council’s Risk Management Team, Programme Management services (now part of ip&e Ltd) co-ordinates service managers to ensure that they fulfil their responsibility to complete detailed risk analyses and that all change activity takes correct account of all risks and opportunities, as per the Council’s agreed Opportunity Risk Management Strategy.
The recommendations contained in this report are compatible with the Human Rights Act 1998.
The delivery of redesign proposals, particularly aligned to the significant budget savings that need to be delivered over the next three years are monitored on a monthly basis and reported to the Council's Senior Management Team. To ensure consistency and robustness of the approach, any figures reported in relation to the achievement or non-achievement of savings will be directly reflected within the Council's revenue monitoring reports.
With the reduction in the number of Cabinet Meetings introduced in 2014/15, financial monitoring reports will be approved by Cabinet on a quarterly basis. However, monthly reports will continue to be produced and will be considered in a timely manner by the Council's Director's Team. Furthermore, to ensure Cabinet Members are able to fulfil their roles in their respective Portfolio areas, monthly informal Cabinet meetings have been diarised throughout the year specifically to review and monitor progress against the delivery of the Council's savings plans (over all three years of the current Medium Term Financial Plan) and the impact on Council's in-year revenue and capital position.
5. Management Controls
Management control arrangements at Shropshire Council are based on clear, consistent governance structures and reporting, ensuring that the right people make the right decisions based on the right information. This approach is based on national ‘Best Management Practice’ principles, and is applied elsewhere in both the public and private sector.
5.1Programme Management (including ‘Tracking Hub’) :
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on Programme Management Controls and RisksReport | 84 KB | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.