Cabinet, Wednesday 30 July 2014 at 12.30pm

Capital Monitor 2014/15 Period 3

Approved Executive 2 papers

Cabinet approved this item on Wednesday 30 July 2014. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

(a) That approval be given to the net budget variations of £0.5m to the 2014/15 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2014/15 capital budget of £70.9m. (b) That approval be given to the re-profiled capital budgets of £18.3m for 2015/16 and £5,4m for 2016/17 as detailed in Appendix 1/Table 4. (c) That Council be recommended to approve the budget increases for new external funding of £2.24m in additional Highways Maintenance funding from the Department of Transport for expenditure in 2014/15 and an additional £1.5m grant for BDUK for the current Broadband Project. (d) That the expenditure to date of £5.7m, representing 8.1% of the revised capital budget for 2014/15, with 25% of the year having elapsed, be accepted.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Summary

1.1The purpose of this report is to inform Members of the current position for the Council’s 2014/15 to 2017/18 capital programme taking into account the latest monitoring information on the progress of the schemes, any necessary budget increases and decreases and the re-profiling of budgets between 2014/15 and future years. The report reflects:

 The re-profiled 2014/15 budget of £70.9m and the future years capital programme budget;  Expenditure to date of 8.1% of the revised budget;  A projected outturn in line with the re-profiled budget of £70.9m; and  The current funding of the programme and its future affordability.

Recommendations

Members are asked to:

A. Approve net budget variations of £0.5m to the 2014/15 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2014/15 capital budget of £70.9m.

B. Approve the re-profiled capital budgets of £18.3m for 2015/16 and £5.4m for 2016/17 as detailed in Appendix 1/Table 4.

C. Recommend to Full Council the approval of the budget increases for new external funding of £2.24m in additional Highways Maintenance funding from the Department of Transport for expenditure in 2014/15 and an additional £1.5m grant from BDUK for the current Broadband Project.

D. Accept the expenditure to date of £5.7m, representing 8.1% of the revised capital budget for 2014/15, with 25% of the year having elapsed.

1 Cabinet 30 July 2014: Capital Monitoring – Quarter 1 2014/15

REPORT

3. Risk Assessment and Opportunities Appraisal

3.1Risk assessments are undertaken as part of the evaluation of all capital bids.

3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.

3.3Environmental appraisals are carried out for individual schemes as appropriate.

3.4Community consultations are carried out for individual schemes as appropriate.

Financial implications

4.1This report considers the capital spend within the capital programme for 2014/15 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.

Background

5.1The capital programme for 2014/15 and future years, was updated as part of the Capital Strategy 2014/15 to 2017/18 report, approved by Council 27 February 2014. This included updated allocations of capital grants and a review of and delivery schedule for schemes.

6. Original and latest proposed capital programme for 2014/15

6.1The capital budget for 2014/15 is subject to change, the largest element being slippage from 2013/14 and re-profiling into future years. In Quarter 1 there has been a net budget decrease of £0.5m, compared to the position reported at Outturn 2013/14. Table 1 summarises the overall movement, between that already approved, and changes for Period 11 that require approval.

Table 1: Revised Capital Programme Quarter 1 2014/15 Service Area Agreed Capital Slippage and Quarter 1 Revised Programme - budget changes budget 2014/15 Capital Council approved to changes to Programme 28/02/13 Outturn 13/14 be approved Quarter 1 General Fund

Commissioning 33,394,659 6,509,613 256,434 40,160,706 Adult Services 1,419,791 337,728 - 1,757,519 Children’s Services 13,173,406 3,230,846 (859,370) 15,544,882 Resources & Support 268,000 2,293,733 (138,642) 2,423,091

Total General Fund 48,255,856 12,371,920 (741,578) 59,886,198

Housing Revenue Account 10,090,890 720,212 230,380 11,041,482

Total Approved Budget 58,346,746 13,092,132 (511,198) 70,927,680 2 Cabinet 30 July 2014: Capital Monitoring – Quarter 1 2014/15

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
11A Appendix 1 Capital Monitoring Period 3Appendix 189 KB Download
PDF
Capital Monitor 2014/15 Period 3Report 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
KB
Keith BarrowLeader, present
AH
Ann HartleyDeputy Leader, present
TB
Tim BarkerCommittee Member, present
GB
Gwilym ButlerCommittee Member, present
KC
Karen CalderCommittee Member, present
LC
Lee ChapmanCommittee Member, present
SC
Steve CharmleyCommittee Member, present
MO
Mike OwenCommittee Member, present
MP
Malcolm PriceCommittee Member, present
CW
Claire WildCommittee Member, present

On this subject at Shropshire

Search all
  1. Capital Monitor 2014/15 Period 3This decision
  2. Capital Monitoring Report Quarter 2 2016/17Approved
  3. Capital Monitor 2016/17 Quarter 1Approved
  4. Capital Monitoring 2015/2016 Quarter 3Approved
  5. Capital Monitoring Report Quarter 2 2015/2016Noted
  6. Capital Monitoring Report Quarter 2 2015/2016Approved

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies