(a) That approval be given to the net budget variations of £3m to the 2014/15 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2014/15 capital budget of £66.6m. Including new allocations of capital receipt funding as follows: · Acquisition - Former Oswestry Health Centre £340,900. (b) That approval be given to the re-profiled capital budgets of £51.5m for 2015/16 and £31.2m for 2016/17 and £19.8m for 2017/18 as detailed in Appendix 1/Table 4. (c) That the expenditure to date of £34.4m, representing 51.6% of the revised capital budget for 2014/15, with 75% of the year having elapsed, be accepted.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1The purpose of this report is to inform Members of the current position for the Council’s 2014/15 to 2017/18 capital programme taking into account the latest monitoring information on the progress of the schemes, any necessary budget increases and decreases and the re-profiling of budgets between 2014/15 and future years. The report reflects:
The re-profiled 2014/15 budget of £66.6m and the future years capital programme budget; Expenditure to date of 51.6% of the revised budget; A projected outturn in line with the re-profiled budget of £66.6m; and The current funding of the programme and its future affordability.
Recommendations
Members are asked to:
A. Approve net budget variations of £3m to the 2014/15 capital programme, detailed in Appendix 1/Table 1 and the re-profiled 2014/15 capital budget of £66.6m. Including new allocations of capital receipt funding as follows: Acquisition - Former Oswestry Health Centre £340,900
B. Approve the re-profiled capital budgets of £51.5m for 2015/16 and £31.2m for 2016/17 and £19.8m for 2017/18 as detailed in Appendix 1/Table 4.
C. Accept the expenditure to date of £34.4m, representing 51.6% of the revised capital budget for 2014/15, with 75% of the year having elapsed.
1 Cabinet 11 February 2015: Capital Monitoring – Quarter 3 2014/15 REPORT
3. Risk Assessment and Opportunities Appraisal
3.1Risk assessments are undertaken as part of the evaluation of all capital bids.
3.2Capital receipt levels and the timing of receipts are dependant on planning approvals and prevailing market conditions.
3.3Environmental appraisals are carried out for individual schemes as appropriate.
3.4Community consultations are carried out for individual schemes as appropriate.
Financial implications
4.1This report considers the capital spend within the capital programme for 2014/15 and considers the impact that slippage within the programme will have on the financing of the capital programme in the future, including any future revenue implications.
Background
5.1The capital programme for 2014/15 and future years, was updated as part of the Capital Strategy 2014/15 to 2017/18 report, approved by Council 26 February 2014. This included updated allocations of capital grants and a review of the delivery schedule for schemes.
5.2A further update of the capital programme has been undertaken and an updated Capital Strategy for 2015/16 to 2017/18 is included on this Cabinet agenda as part of the Business Plan and Financial Strategy and will be presented to Council on 26 February 2015 for final approval.
6. Original and latest proposed capital programme for 2014/15
6.1The capital budget for 2014/15 is subject to change, the largest elements being slippage from 2013/14 and re-profiling of slippage into future years. In Quarter 3 there has been a net budget decrease of £3m when compared to the position reported at Quarter 2 2014/15. Table 1 summarises the overall movement between that already approved and changes for Quarter 3 that require approval.
2 Cabinet 11 February 2015: Capital Monitoring – Quarter 3 2014/15
Table 1: Revised Capital Programme Quarter 3 2014/15 Service Area Agreed Capital Slippage and Quarter 3 Revised Programme - budget changes budget 2014/15 Capital Council approved to changes to Programme 27/02/14 Quarter 2 14/15 be approved Quarter 3 General Fund
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.