Audit Committee, Thursday 13 September 2018 at 1.30pm

Second line assurance: Strategic Risks Update

Noted Finance 1 paper

Audit Committee noted this item on Thursday 13 September 2018. Below is the council's own wording, with the papers it was decided on.

Item40

Resolved

To note the position as set out in the report.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit Committee, 5 pages

Committee and Date Item Paper

Audit Committee – 13th September 2018

STRATEGIC RISK REPORT SEPTEMBER 2018

Responsible Officer Angela Beechey e-mail: [email protected] Tel: (01743) Fax (01743) 252073 252858

1. Summary 1.1 This report sets out the current strategic risk exposure following completion of a strategic risk workshop with Directors and the July 2018 quarterly review.

2. Recommendations 2.1 Members are asked to accept the position as set out in the report.

REPORT

3. Current Strategic Risk Exposure 3.1 The management of strategic risk is a key process which underpins the successful achievement of our priorities and outcomes. Strategic risks are linked, where appropriate, with the Annual Governance Statement Targeted Outcomes.

3.2Our strategic risks are reviewed on a quarterly basis ensuring that the level of risk exposure is monitored regularly in our rapidly changing environment.

3.3The review was achieved through scheduled meetings with key officers, Directors, Chief Executive and Portfolio Holder. The outcome of each review is then reported to Directors and Informal Cabinet.

3.4The Risk Profile & Action Plans for managing our strategic risks are completed and fully embedded. These detail the direction of travel for each strategic risk over the year and clearly articulate the current controls in place and the additional controls required to mitigate and manage our strategic risk exposure effectively. Any slippage on outstanding actions is also identified and challenged.

3.5The Risk Profile & Action Plan also includes target scores for each strategic risk to be achieved by the end of the current financial year.

3.6As at the July 2018 review there were 16 strategic risks on the strategic risk register and these are each managed by specific Directors. These are detailed as follows:-

Contact: Angela Beechey (01743 252073) 1 Audit Committee: 1st March 2018

Risk Risk Owner L I Status Sustainable Budget James Walton 3 5 15 Staffing Michele Leith 5 4 20 Work Related Stress Michele Leith 5 4 20 Future Funding Levels James Walton 3 5 15 Failure to Safeguard Vulnerable Adults Andy Begley 2 3 6 Digital Transformation Programme Michele Leith 3 5 15 Contract Management James Walton 2 3 6 Failure to Safeguard Vulnerable Children Karen Bradshaw 3 4 12 Commercial Strategy Tim Smith 4 5 20 Economic Growth Strategy Gemma Davies 2 3 6 Governance Claire Porter 3 2 6 Health & Social Care Andy Begley 5 2 10 ICT Provision Michele Leith 3 3 9 Strategic Vision and Strategy Clive Wright 3 4 12 Reputation Michele Leith 5 4 20 Economic Impact of Brexit Clive Wright 4 3 12

High Risks Medium Risks Low Risks

3.7This review saw changes to the scoring of six of the risks as follows –

3.7.1 Failure to safeguard vulnerable children - Score increased due to the increased demand and complexity of children coming into the system and stretched qualified resources. Inability to recruit qualified and experienced social workers is also a problem. Increased from a 2x4=8 to a 3x4=12 – remaining as a medium risk.

3.7.2 Strategic vision and strategy for the Council– Score increased in recognition of the work to be done on strategic vision in line with actions from the recent Peer Review. Increased from 2x4=8 to 3x4=12 – remaining as a medium risk.

3.7.3 Reputation – The score was changed to reflect the reputational impact around current high profile areas. Increased from 4x4=16 to 5x4=20 – moving to a high risk.

3.7.4 Failure to safeguard vulnerable adults - The score was reduced as a result of the work which has been undertaken to reduce the risk in relation to DoLs and resources are being managed proactively. Reduced from a 3x3=9 to a 2x3=6 which is a low risk.

3.7.5 Contract management - The score was reduced as it was felt by Directors that contracts are now being managed more effectively within the Council. Reduced from a 3x4=12 to a 2x3=6 which reduces this to a low risk. Contact: Angela Beechey (01743 252073) 2 Audit Committee: 1st March 2018

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Second line assurance: Strategic Risks UpdateReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Shropshire

Search all
  1. Second line assurance: Strategic Risks UpdateThis decision
  2. Second line assurance: Annual Treasury ReportApproved
  3. Second line assurance: Approval of the Council's Draft Statement of Accounts 2025/26Approved
  4. Second line assurance: Annual Whistleblowing reportApproved
  5. Second line assurance: Treasury Strategy 2026/27Approved
  6. Second line assurance: Treasury Strategy Mid-Year Report 2025/26Agreed

More from Shropshire Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. Approved Open
16 Jul 2025 Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... Approved Open
16 Jul 2025 Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. Noted Open
16 Jul 2025 Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... Agreed Open
16 Jul 2025 Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies