A. To note the progress that has been made to address the recommendations in the 9 th November Audit Report and that wherever possible improvements are being effectively implemented; B. To note that the change required under recommendation 1 in regards uprating of financial contributions required Cabinet approval and public consultation and that in July 2018 the Cabinet agreed to the recommendation that the Council set the Minimum Income Guarantee for people of pensionable age in line with the Governments Statutory Minimum Income Guarantee level in order for the Council to be seen as consistent in its approach to charging for care; C. To note that the main improvements and implementation of the Action Plan associated with the audit which are outstanding are contingent on the Digital Transformation Project which is underway for Adult Social Care and that the recommendations of the audit in regards systems improvement have been fed into the workflow processes to ensure future systems will meet these requirements and will go live on 10 th December 2018 as a part of wider system change.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
1.1This report is an update for the Audit Committee which sets out the actions taken by the Financial Assessment Team and management following the 2017/18 final internal audit report regarding adult social care financial assessments which was issued on the 9th November 2017.
1.2A total of 23 recommendations were set out for the service in the final audit report. No recommendations were categorised as fundamental, 14 recommendations were categorised as significant and 9 were categorised as requiring attention.
1.4The managers of the service have addressed all of the recommendation where possible. Of the twenty three improvements required for the service 14 recommendations have now been completed. 7 remain outstanding due to them being contingent on the new ControCC (financial management system) and LAS (Case management system) which are currently being implemented and will go live on the 10th December 2018. 2 recommendations are in progress, these are both regarding time taken to turn assessments around and have been impacted by team changes and resource issues.
1.5The staff team has been recently changed with the replacement of the Senior Assessment Officer and a redesign of the role to include more oversight responsibility of the team’s performance.
Recommendations
2.1It is requested that Audit Committee members note the progress that has been made to address the recommendations in the 9th November Audit Report and that wherever possible improvements are being effectively implemented.
2.2It is requested that Committee members note that the change required under recommendation 1 in regards uprating of financial contributions required cabinet approval and public consultation and that in July 2018 the cabinet agreed to the recommendation that the Council set the Minimum Income Guarantee for people of pensionable age in line with the Governments statutory Minimum Income Guarantee level in order for the Council to be seen as consistent in its approach to charging for care.
2.3It is requested that Committee members note that the main improvements and implementation of the action plan associated with the audit which are outstanding are contingent on the Digital Transformation Project which is underway for Adult Social Care and that the recommendations of the Audit in regards systems improvement have been fed into the workflow processes to ensure future systems will meet these requirements and will go live of 10th December 2018 as a part of wider system change.
REPORT
3. Risk Assessment and opportunities appraisal.
3.1It has been accepted by the Financial Assessment Team and management that a number of system issues were identified though the audit that, when improved, would ensure more effective and efficient service is received by individuals being assessed. A complete system redesign for Adult Social Care is underway and all of the system improvement recommendations for financial assessment have been included in the design of the financial management system (ControCC). New systems will go live on 10th December 2018.
3.2Current staff resources have been directed to system testing and data migration for the new ControCC system to ensure that the redesign has achieved the required system improvements, effective controls and processes and is taking full advantage of the opportunity to make these even more efficient and effective by ensuring the data is accurate and robust.
3.2Some delays still exist due to significant time required from the team for data testing and migration to new systems and also for MIG uprating prompted by July cabinet decision. Following the go live date for the new system it is anticipated that both systems and time taken to process assessments will significantly improve.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.