Resolved
That the Digital Transformation Programme – Business Case Review/Benefits Realisation report be noted.
Performance Management Scrutiny Committee noted this item on Wednesday 13 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Digital Transformation Programme – Business Case Review/Benefits Realisation report be noted.
1.1This report reflects on the original goals of the 2016 Digital Transformation Programme (DTP) and details what solutions have been delivered and what benefits have been achieved to date.
1.2Section 5.4 of the report outlines how the outstanding savings targets might be achieved, by utilising the technology that the organisation now has at hand.
2.1Members are asked to consider the progress made with DTP and the aspirations for the future digital transformation of the organisation.
3.0Opportunities and risks
3.1The management of risks and opportunities associated with Digital Transformation is done via the individual programme workstreams (as outlined in 5.1.4 below).
Where necessary risks and opportunities are escalated to the Transformation Programme Board for consideration and decisions.
4.0Financial assessment
4.1The 2016 business case for Digital Transformation included targets for both cashable and non cashable savings, as outlined in 5.1.6 and 5.1.7 below.
4.2Due to financial pressures in the intervening years, the cashable savings target associated with Digital Transformation rose to £9.5m.
Section 5.3 of this report details the savings that have subsequently been Meeting, date: Report heading
4.3realised as well as those that have been reinvested into improvement in service delivery.
Description Reference Budget Delivered Delivered Target (£’000) Elsewhere (£’000) (£’000) Total DTP Cashable Savings 2016 1663.00 268.82 748.00 Business Case Total DTP Non Cashable 2016 11,008.00 0.00 Business 1,790.00 Case Additional Transformation Financial 1,696.88 718.14 410.00 Savings (2018/19 & 2019/20) Strategy 2019/20 Single Front Door Financial 500.00 0.00 0.00 Strategy 2019/20 Total Potential Savings 14,867.88 986.96 2,948.00 Less ‘contingency’ (5,367.88) Total Savings Target built into 9,500.00 Financial Strategy
Total Delivered to Date 3,934.96
Total Still to be Delivered 5,565.04
4.4In addition to the £3.9m identified savings to date, there is also a £3m one-off saving from implementation (due to the project being delivered with a £3m underspend compared to the approved budget). In addition, savings from staffing rationalisation since 2016 (a 23% reduction in the FTE overall workforce) have not been attributed directly to DTP so are not included in these figures.
4.5Section 5.4 of this report explores how the remaining savings target for Digital Transformation could be achieved by the Council.
5.0Report
5.1Introduction – The Original Basis of the Programme
5.1.1 Shropshire’s ICT Digital Transformation Programme was approved by Council in July 2016. This programme had the stated desire to deliver services at the highest quality and lowest cost compared to other authorities in everything that it does. This included transforming IT systems, reshaping services and ‘back- office’ functions, reducing costs, removing duplication, improving efficiency, reducing business continuity risk and enabling more effective service delivery across a rural geography.
Council approved the recommended hybrid option (Option 4) as the preferred
2 Meeting, date: Report heading
5.1.2 solution for delivering a digital state to meet the business and IT needs of the Council and to support front-line services. In so doing, it would meet the requirements to:
Deliver the greatest level of financial benefits of all the options; Ensure business continuity in key services; Achieve the greatest benefit to the Council for a reasonable level of risk.
The hybrid approach allowed the Council to maximise the potential of its current 5.1.3 internal ICT provision coupled with ‘best of breed’ solutions for Social Care and back-office processing.
Four project boards, were put in place to deliver the Digital Transformation 5.1.4 Programme, covering the following areas:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Digital Transformation Programme UpdateReport | 13 pages | DownloadRead as text |
Follow Performance Management Scrutiny Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jul 2020 | Financial StrategyThat the Medium Term – July 2020 – 2020/21 to 2025/26, be noted. | Noted | Open |
| 8 Jul 2020 | Financial Monitoring Report, Quarter 4 2019/20That the report be noted. | Noted | Open |
| 8 Jul 2020 | Future Work Programmei) That Climate Change and SEND be considered by the Committee at its meeting in July; and ii) That the Financial Str... | Decided | Open |
| 10 Jun 2020 | Minutes of the meeting held on 20th May 2020that the minutes of the Performance Management Scrutiny Committee meeting held on 20 th May 2020 be approved as a cor... | Approved | Open |
| 10 Jun 2020 | Quarter 4, 2019/20 Corporate Performance ReportThat the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.