Resolved
To note the progress that each of the projects within the programme are making and the mitigations that are being put in place to address the issues within each work stream.
Audit Committee noted this item on Monday 25 February 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the progress that each of the projects within the programme are making and the mitigations that are being put in place to address the issues within each work stream.
This report will provide updates on the following:
1.1Digital Transformation Programme 1.2 Social Care Project 1.5 Customer Experience Project 1.3 Infrastructure and Architecture Project 1.4 Business Transformation Project
2.1The recommendations are that:
2.2The Committee notes the progress that each of the projects within the programme is making and the mitigations that are being put in place to address the issues within each work stream.
REPORT
3.0Social Care Project
3.1The adults modules in Liquidlogic went live as planned on 10th Dec and system is working well, staff are getting to grips with a different system. Additional resource is being directed to developing the suite of reports from the system, which hasn’t been straight forward but progress is being made.
Please contact Michele Leith on 01743 254402 1 Audit Committee: Digital Transformation Programme Update
3.2Children’s modules are still scheduled to go live 18th Feb, Social Care Project Board gave go live approval, there will be a final check on Sunday evening and launch on Monday.
4.0Customer Experience Project
4.1Telephony and Contact Centre Software has been rolled out across the council CRM modules are working well, the first iteration of My Shropshire will be launched at the end of this month. Cabinet saw a demonstration on 28th January 2019. A portal for Members is being built, we will be asking members to come along and comment on the build and requirements with a view to having the portal live from October.
4.2Customer Services Centre have gone live with Web Chat and we are seeing positive impact from its use.
4.3Work with the DEG and STP is progressing well, this will helpful to facilitate the work on an enhanced single patient record.
4.4Broseley Project on assisted digital health progressing well.
5.0Infrastructure and Architecture Project
5.1The team has started to procure a provider to implement the Gov- Roam wifi solution which will allow staff from NHS and Local Authority access their respective systems from the same/shared locations.
5.2Master Data Management Proof of Concept is progressing well and the servers to support MDA have been built.
5.3Dashboard for reporting data sets are being developed – Highways, Food Hygiene, Housing, communications, comments complements and complaints.
5.4Print Solution and 365 fax rollout phase one is complete.
6.0Business Transformation
6.1Go live remains scheduled for 1st April 2019, level of defects has been high throughout this project and whilst reducing there still some to fix. The team are working hard resolve them.
6.2Staff training has been developed and will begin mid Feb, and initially last for 6 weeks, this is an estimate as all Council staff are likely to need some training on the new system.
Please contact Michele Leith on 01743 254402 2 Audit Committee: Digital Transformation Programme Update
6.3System security and multi factor identification a solution to this has now been found.
7.0Budget
7.1The programme is still projected to underspend.
7.2We continue to scope the post implementation phase including the decommissioning of legacy systems & new ways of working, productivity on front line as the mechanism to realise the savings.
8.0Governance
8.1The Assurance team are still engaged with each project board and report to overarching programme board. We have introduced a feedback/completion loop to ensure items raised by Assurance team are resolved.
Please contact Michele Leith on 01743 254402 3
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
First Line Assurance: Digital Transformation Programme updateReport | 89 KB | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.