Digital Transformation Roadmap

Approved Executive 4 papers

AI summaryShropshire Council Cabinet approves Digital Roadmap 2026 to 2030, a four-phase corporate programme covering customer access, automation, data, system modernisation and workforce productivity, with future spending subject to separate approvals.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhased corporate delivery plan endorsed
MoneyNo specific sum givenFuture investment to go through separate business cases
What happens nextPhase 1 begins 2026/27Mobilise, Prioritise and Decide
Who it affectsAll council services, residents and staffCounty-wide digital transformation

What was decided

Cabinet approved the Digital Roadmap 2026 to 2030 as the council's strategic delivery plan for digital transformation, supporting the Corporate Plan, Improvement Plan, Digital Strategy and Financial Sustainability Programme. Report 2.1, 1.6

Cabinet endorsed a four-phase delivery approach running to 2030, covering mobilisation, foundations, scaling and optimisation across each financial year from 2026/27 to 2029/30. Report 2.2, P10, 3.10

Cabinet delegated authority to the Service Director for Enabling Services and the Head of Service for Automation and Technology, in consultation with the Transformation and Economic Growth Portfolio Holder, to make amendments that do not materially alter the approved scope or direction. Report 2.4

Why

The council faces sustained financial pressure, rising service demand, ageing technology and growing cyber risks, with more transformation demand than delivery capacity can support. Report 3.1, 3.4, 3.7

More than 150 digital, automation and transformation initiatives were reviewed and prioritised through a framework assessing statutory risk, financial impact, demand reduction, deliverability, dependency and political sensitivity. Report 3.5, 3.6, 3.8

The Corporate Peer Challenge, Improvement Plan and Financial Sustainability Programme have called for clearer corporate prioritisation, modernised service delivery and stronger governance of digital investment. Report 3.1, 3.4, 7.3

What happens next

Phase 1 in 2026/27 will focus on mobilisation, prioritisation, governance, baselining and key platform decisions, including establishing the benefits realisation baselines. Report P10, 3.10, 4.4

Future major system replacements, platform licensing, implementation and procurement activity will require separate business cases, governance approvals and procurement processes. Report 2.3, 8.6

Further Equality, Social inclusion and Health impact Assessments will be carried out during implementation where warranted and proportionate. Report 12.1

Options considered

  • Rejected: Do nothing or continue with the current approach. Would not address rising demand, fragmented delivery, duplicated investment or long-term financial sustainability challenges Report 5.1, P33
  • Rejected: Individual service-led transformation activity without a single corporate roadmap. Likely to increase duplication, reduce value for money, create inconsistent customer experience and make benefits realisation harder Report 5.1, P34
  • Chosen: Adopt the Digital Roadmap 2026 to 2030 as a single corporately governed delivery plan. Aligns digital investment to organisational priorities, improves control and transparency, and links strategy to implementation Report 5.1, P35, 5.2

Implications

  • Financial: Roadmap supports the Financial Sustainability Programme through productivity, demand reduction, automation, service redesign and income optimisation, but approval does not itself authorise future capital or revenue spending. Report 8.1, 8.3, 8.5, 8.6
  • Equalities: Initial Equality, Social inclusion and Health impact Assessment rates impacts as neutral to low positive across all nine Protected Characteristics, with potential for low to medium positive for Age, Disability, Carers and Social Inclusion; commitment to a 'digital by choice, human when it matters' approach. Report 12.1, 12.2, 12.4, 12.5, 12.6, 1.5
  • Climate: No significant adverse climate or biodiversity impacts identified; indirect benefits expected from reduced paper use, automation, cloud adoption and reduced travel. Report 13.2, 13.3, 13.4, 13.7
  • Risk: Delivery contributes to strategic risks on financial sustainability, skills shortages, cyber resilience, governance compliance and service access, with mitigations including secure-by-design, governance oversight, phased delivery and inclusive design. Report 6.3, 6.4, P51
  • Staffing: Programme depends on workforce development, change management, digital skills, recruitment and new ways of working; HR support required throughout delivery. Report 9.4, 9.6
  • Legal: Individual initiatives will require legal review for procurement legislation, subsidy control, data protection, accessibility, cyber standards and service-specific statutory duties. Report 9.1, 9.2, 9.3

Who and where

  • Residents across all areas of Shropshire, including rural communities and those unable or unwilling to use digital channels Report 10.2, 10.3, 11.6, 11.7
  • Council staff, through new digital tools, automation and changed ways of working Report 4.6, 9.4
  • Adult Social Care and Children's Services, including care leavers, through earlier intervention, prevention and improved access Report 11.3, 11.4, 11.8, 11.9
  • Council-wide service areas delivering digital, transformation and service improvement initiatives Report 3.5, 3.9

Timeline

  • 2026/27: Phase 1: Mobilise, Prioritise and Decide, including governance, baselining and key platform decisions Report P10, 3.10
  • 2027/28: Phase 2: Foundations and Early Value, delivering customer, data and integration capabilities with early service improvements Report P10, 3.10
  • 2028/29: Phase 3: Scale and Transform, embedding redesigned operating models and broader automation adoption Report P10, 3.10
  • 2029/30: Phase 4: Optimise and Sustain, focusing on continuous improvement, prevention and benefits realisation Report P10, 3.10

Plain English for the jargon

  • CRM: Customer Relationship Management, a system for managing the council's interactions with residents
  • CCaaS: Contact Centre as a Service, a cloud-based contact centre platform
  • ESHIA: Equality, Social inclusion and Health impact Assessment, used to assess effects on protected and local groups
  • CAF: Cyber Assessment Framework, the government framework for assessing cyber resilience
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item228

Resolved

RESOLVED 2.1 To approve the Digital Roadmap 2026–2030, attached at Appendix A. Appendix B (plan on a page) provides details for each workstream the key activities during each phase of the roadmap and benefits over the life of the programme. This supports delivery of the Corporate Plan, Improvement Plan, Digital Strategy and Financial Sustainability Programme. 2.2. Endorse the phased delivery approach set out within the roadmap, comprising: Phase 1 – Mobilise , Prioritise and Decide (2026/27) Phase 2 – Foundations and Early Value (2027/28) Phase 3 – Scale and Transform (2028/29) Phase 4 – Optimise and Sustain (2029/30) 2.3. Note that the roadmap establishes the strategic direction, delivery priorities and initial funding envelope for digital transformation and that future investment decisions relating to major system replacements, platform licensing, implementation activity and associated procurements will be subject to separate business cases, governance approvals and procurement processes where required. 2.4. Delegate authority to the Service Director for Enabling Services and the Head of Service – Automation and Technology, in consultation with the Portfolio Holder for Transformation and Economic Growth, to make amendments to the roadmap, delivery sequencing and associated delivery plans, provided such changes do not materially alter the strategic objectives, scope or overall direction approved by Cabinet.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet

Purpose of report

1.1Shropshire Council has approved a Digital Strategy which sets the strategic direction for how the Council will use digital, data, automation and technology to improve outcomes, redesign services and support long-term financial sustainability.

1.2The Digital Roadmap 2026–2030 translates that strategy into a practical programme of delivery, setting out the specific capabilities, priorities, sequencing and outcomes required to achieve transformation across the Council.

1.3The roadmap provides a single, prioritised programme for digital transformation, bringing together customer access, service redesign, data and insight, automation and artificial intelligence, workforce productivity, system modernisation and organisational improvement into a coherent delivery plan. It consolidates digital, transformation and service improvement activity into a corporately governed roadmap aligned to the Council’s priorities, delivery capacity and financial position.

1.4The roadmap establishes a phased delivery approach through to 2030, providing clarity on investment requirements, governance arrangements, dependencies, benefits realisation and the capacity required to deliver change. It demonstrates how transformation activity will be prioritised, governed and delivered through a single corporate programme focused on customer experience, demand reduction, workforce productivity, service improvement and financial sustainability.

1.5It also provides assurance that digital transformation will remain inclusive, maintaining the Council’s commitment to a ‘digital by choice, human when it matters’ approach, ensuring that residents who cannot or do not wish to use digital channels continue to receive appropriate support and access to services.

1.6The report seeks Cabinet approval of the Digital Roadmap 2026–2030 as the Council’s strategic programme for digital transformation and organisational improvement, supporting delivery of the Corporate Plan, Improvement Plan and Financial Sustainability Programme.

Recommendations

Cabinet is recommended to:

2.1Approve the Digital Roadmap 2026–2030, attached at Appendix A. Appendix B (plan on a page) provides details for each workstream the key activities during each phase of the roadmap and benefits over the life of the programme. This supports delivery of the Corporate Plan, Improvement Plan, Digital Strategy and Financial Sustainability Programme.

2.2Endorse the phased delivery approach set out within the roadmap, comprising:

Phase 1 – Mobilise, Prioritise and Decide (2026/27) Phase 2 – Foundations and Early Value (2027/28) Phase 3 – Scale and Transform (2028/29) Phase 4 – Optimise and Sustain (2029/30)

2.3Note that the roadmap establishes the strategic direction, delivery priorities and initial funding envelope for digital transformation and that future investment decisions relating to major system replacements, platform licensing, implementation activity and associated procurements will be subject to separate business cases, governance approvals and procurement processes where required.

2.4Delegate authority to the Service Director for Enabling Services and the Head of Service – Automation and Technology, in consultation with the Portfolio Holder for Transformation and Economic Growth, to make amendments to the roadmap, delivery sequencing and associated delivery plans, provided such changes do not materially alter the strategic objectives, scope or overall direction approved by Cabinet. 3. Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Digital RoadmapAppendix A 1.9 MB Download
PDF
Plan on a Page Digital RoadmapAppendix B 5.5 MB Download
PDF
From Demand To DeliveryAppendix C 4.3 MB Download
PDF
Digital Transformation RoadmapReport 293 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
HK
Heather KiddCommittee Member, present
AW
Alex WagnerCommittee Member, present
RE
Roger EvansCommittee Member, present
AH
Andy HallCommittee Member, present
RH
Ruth HoughtonCommittee Member, present
JO
James OwenCommittee Member, present
RW
Rob WilsonCommittee Member, present
DV
David VasmerCommittee Member, present
DW
David WalkerCommittee Member, present
SM
Sarah MarstonCommittee Member, present

On this subject at Shropshire

Search all
  1. Digital Transformation RoadmapThis decision
  2. First line assurance : Digital Transformation UpdateNoted
  3. Digital Transformation Programme UpdateNoted
  4. First Line Assurance: Digital Transformation Programme updateNoted
  5. Digital Transformation ProgrammeAgreed
  6. Digital Transformation Programme UpdateNoted

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open