Resolved
That the Cornovii Developments Limited – Developments Update Report be noted.
Housing Supervisory Board noted this item on Thursday 21 November 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Cornovii Developments Limited – Developments Update Report be noted.
1.1The following report provides the Housing Supervisory Board with an update from Cornovii Developments Limited on the progress of the two development sites at Overton Road, Ifton Heath and Frith Close, Monkmoor, Shrewsbury; since the previous meeting of the Board on 31st October 2019.
2.1That the Housing Supervisory Board notes the Cornovii Developments Limited Sites Update Report.
3. Risk Assessment and Opportunities Appraisal
3.1N/A.
4.1N/A.
Page 1 of 5 REPORT
5.1Cornovii Developments Limited, Shropshire Council’s wholly-owned Local Housing Company, has been progressing the development of its first two sites at Overton Road, Ifton Heath and Frith Close, Monkmoor, Shrewsbury.
5.2The report in Appendix A, provides an update on the development progress since the last meeting of the Housing Supervisory Board on 31st October 2019.
6. Additional Information
6.1None.
Background Papers (This MUST be completed for all reports, but does not include items containing exempt or confidential information) None
Cabinet Member (Portfolio Holder) Cllr. Robert Macey
Local Member Cllr. Steve Davenport & Cllr. Pam Moseley
Appendix A Cornovii Developments Limited - Developments Update Report
Page 2 of 5 Appendix A
Cornovii Developments Limited Developments Update Report 21st November 2019
1 Purpose
1.1To update the Housing Supervisory Board with the progress of the first two development sites.
2 Introduction
2.1The Company has been progressing the development of its first two sites at Overton Road, Ifton Heath and Frith Close, Monkmoor, Shrewsbury. Since our last update to the Housing Supervisory Board, several key actions and key activities have taken place as outlined in this report.
3.1That the Housing Supervisory Board notes the Cornovii Developments Limited Sites Update Report.
4 Surveys
4.1Survey at both sites (with the exception of the Geo-Environmental which is having additional ground gas measures) have now been completed. Reports have been issued to Willmott Dixon. A preliminary Geo-Environmental report has been produced, also issued to Willmott Dixon.
4.2The completed surveys are as follows: Topographical Survey Utility Survey CCTV Survey Acoustic Arboricultural Survey Geotechnical Investigation (additional ground measures on-going) Ecology Surveys.
Page 3 of 5 4.3 The DNA analysis of bat droppings at Overton Road has now been completed. The findings show that the droppings in the central part of the roof are from ‘Lesser Horseshoe Bats’. They are considered to be from occasional, or episodic, use, so do not present a significant issue.
4.4However, given the nature of the buildings and the species present, we will not be able to start works that will impact on the older buildings until mid-March. We are now in the process of consulting with individuals with particular expertise on Lesser Horseshoe’s and will develop a bat strategy accordingly.
5 Appointments
5.1Martin Kelly has been appointed as interim Director of Development. Martin is to replace Claire Nangle as lead and most senior officer working on behalf of Cornovii Developments.
5.2The formal appointment of legal services is anticipated imminently. With the formal appointment of sales and marketing services to take place by the end of November 2019.
5.3Upon the formal appointment of legal services, contract negotiations with Willmott Dixon will commence. We expect to have Willmott Dixon in contract by the end of November 2019. When in contract, Willmott Dixon will move forward with the detailed design of both sites.
5.4Confirmation of the appointment of Contract Management, Quantity Surveying and Clerk of Works Services is expected shortly.
6 Design Workshop
6.1Design workshops took place on Tuesday 29th September 2019, the focus of which was the further development of a “One Scheme”.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Cornovii Developments Ltd: Developments Update ReportReport | 5 pages | DownloadRead as text |
Follow Housing Supervisory Board at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2026 | Exclusion of the Press and PublicThat in accordance with the provisions of Schedule 12A of the Local Government Act 1972, and paragraph 10.4(3) of the... | Decided | Open |
| 19 Mar 2026 | MinutesThat the minutes of the meeting held on 27 th November 2025 be approved as a true record. | Approved | Open |
| 19 Mar 2026 | Cornovii Developments Limited - Quarter Three Monitoring ReportThat the progress made by Cornovii Development Ltd to the end of December 2025 against the approved business plan and... | Approved | Open |
| 19 Mar 2026 | Cornovii Developments Limited - Business PlanThat the update be noted. | Noted | Open |
| 19 Mar 2026 | Exclusion of the Press and PublicThat in accordance with the provisions of Schedule 12A of the Local Government Act 1972, and paragraph 10.4(3) of the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.