Minutes of the previous meeting held on the 29 October 2020

Approved Finance 1 paper

Audit Committee approved this item on Thursday 10 December 2020. Below is the council's own wording, with the papers it was decided on.

Item130

Resolved

That the minutes of the meeting of the Audit Committee held on 29 October 2020 be approved and signed by the Chairman as a correct record.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit Committee, 6 pages

Committee and Date

Audit Committee

10 December 2020

MINUTES OF THE AUDIT COMMITTEE MEETING HELD ON 29 OCTOBER 2020 1.30 - 2.45 PM

Responsible Officer: Michelle Dulson Email: [email protected] Tel: 01743 257719

Present Councillors Ioan Jones, Chris Mellings, Brian Williams (Vice Chairman), Michael Wood and Gerald Dakin (Substitute) (substitute for Peter Adams)

In the absence of the Chairman, the Vice-Chairman, Councillor Brian Williams took the Chair.

119 Apologies for Absence / Notification of Substitutes

119.1 An apology was received from Councillor Peter Adams. Councillor Gerald Dakin substituted for Councillor Adams.

120 Disclosable Pecuniary Interests

120.1 The Chairman reminded Members that they must not participate in the discussion or voting on any matter in which they have a Disclosable Pecuniary Interest and should leave the meeting prior to the commencement of the debate.

121 Minutes of the previous meeting held on the 17 September 2020

121.1 RESOLVED:

That the minutes of the meeting of the Audit Committee held on 17 September 2020 be approved and signed by the Chairman as a correct record.

122 Public Questions

122.1 No public questions had been received.

123 Member Questions

123.1 No Member questions had been received.

124 Third line assurance: External Audit: Redmond Review Briefing

124.1 The Committee received the report of the External Auditor (copy attached to the signed minutes) which updated the Committee in relation to the Redmond Review. The Engagement Lead introduced this item and explained that the Redmond Minutes of Audit Committee held on 29 October 2020

Review, which had been published in early September, was likely to have a fundamental impact on both the accounts process in the future and on the Audit and how the audit worked. 124.2 The Engagement Lead explained the reasons for the review and drew Members’ attention to two key issues that had come out of the review, one was that the accounts were too complex and the other was around the Audit process and the audit fees and the need to ensure that the audit market was sustainable and that audit suppliers could deliver the level of audit that the public would expect of them at a fee that would enable them to do that on a sustainable basis.

124.3 He then took the Committee through some of the key findings of the review (set out on pages 7 to 12 of the report) along with the recommendations which included the setting up of the Office of Local Audit and Regulation and a removal of PSAA and the FRC from the field, a revised fee structure to ensure that adequate resources could be deployed to all audits in future, and reverting back to the September deadline. Redmond was recommending not only the simplification of the accounts but also the production of an audited accounting summary, that would be more of a public document that would enable a lay person to easily understand the key financial dynamics of the local authority.

124.4 The Engagement Lead explained that Grant Thornton’s view as a firm very much supported the outcome of the review and very much wanted to help with its implementation. They wanted sustainable arrangements to be put in place so that they could continue with their presence in the public audit market.

124.5 In response to a query, the Engagement Lead explained that the first point on page 11 of the report referred to the ability of Audit Committees to effectively consider audit reports. The Director of Finance, Governance and Assurance (Section 151 Officer) was then asked to comment on the last paragraph on page 11 of the report about the need for a greater role for Full Council who had delegated the Audit function to the Audit Committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Minutes of the previous meeting held on the 29 October 2020Minutes 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Shropshire

Search all
  1. Minutes of the previous meeting held on the 29 October 2020This decision
  2. Minutes of the previous meetingApproved
  3. Minutes of the previous meeting held on the 25 June 2026Approved
  4. Minutes of the previous meetingApproved
  5. Minutes of the previous meetings held on the 5 February 2026 and 14 May 2026Approved
  6. Minutes of the previous meetingApproved

More from Shropshire Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. Approved Open
16 Jul 2025 Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... Approved Open
16 Jul 2025 Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. Noted Open
16 Jul 2025 Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... Agreed Open
16 Jul 2025 Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies