Audit Progress Report and Sector Update
Shropshire Council Year ending 31 March 2020 December 2020 Contents Section Page Introduction 3 Progress at November 2020 4 Audit Findings Report Update 6 Audit Deliverables 7 Sector Update 8
© 2020 Grant Thornton UK LLP. Audit Progress Report and Sector Update | December 2020 2 Introduction
Richard Percival Engagement Lead T 0121 232 5434 This paper provides the Audit Committee with a report on progress in E [email removed] delivering our responsibilities as your external auditors. The paper also includes a summary of emerging national issues and developments that may be relevant to you as a local authority. Members of the Audit Committee can find further useful material on our website, where we have a section dedicated to our work in the public sector. Here you can download copies of our publications www.grantthornton.co.uk Mary Wren If you would like further information on any items in this briefing, or would like to register with Grant Thornton to Engagement Manager receive regular email updates on issues that are of interest to you, please contact either your Engagement Lead or T 0121 232 5254 Engagement Manager./ E [email removed]
© 2020 Grant Thornton UK LLP. Audit Progress Report and Sector Update | December 2020 3 Progress at November 2020
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Third line assurance: External Audit, Audit progress report and sector updateReport | 15 pages | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.