CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Shropshire Council
Cabinet, Wednesday 7 September 2022 at 10.30am

Whitchurch Swimming and Fitness Centre

Agreed Executive 4 papers

Cabinet agreed this item on Wednesday 7 September 2022. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

That Cabinet: · Agreed that the business case for the project, as set out in the paper, be presented to Council with a recommendation that the development of the Whitchurch Swimming and Fitness Centre be included in the capital programme with an initial budget of £13.100m, funded from Public Works Loan Board (PWLB). · Acknowledged the significant average annual revenue pressure of £0.509m arising from approval of this scheme, reaching a maximum of £0.530m in 2028-29, and recommend that Council delegate resolution of this pressure to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism. · Recommend that Council delegates authority to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism, to procure, negotiate and agree the terms of any agreements/contracts necessary for the delivery of the project including, but not limited to: o Agreeing the procurement strategy o Design Team procurement and appointment o Site Surveys and Investigations and relevant reports o Planning permissions o Tendering activities o Main contractor procurement and contract sign-off o Construction o Hand over That Cabinet: · Agreed that the business case for the project, as set out in the paper, be presented to Council with a recommendation that the development of the Whitchurch Swimming and Fitness Centre be included in the capital programme with an initial budget of £13.100m, funded from Public Works Loan Board (PWLB). · Acknowledged the significant average annual revenue pressure of £0.509m arising from approval of this scheme, reaching a maximum of £0.530m in 2028-29, and recommend that Council delegate resolution of this pressure to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism. · Recommend that Council delegates authority to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism, to procure, negotiate and agree the terms of any agreements/contracts necessary for the delivery of the project including, but not limited to: o Agreeing the procurement strategy o Design Team procurement and appointment o Site Surveys and Investigations and relevant reports o Planning permissions o Tendering activities o Main contractor procurement and contract sign-off o Construction o Hand over
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Cabinet, 20 pages

Executive summary

2.1At its meeting on 27th April 2022 Cabinet agreed the following recommendations:

 Note and acknowledge progress and actions undertaken to meet the recommendations of the Cabinet report in June 2021  Agree that the proposed plans be the subject of a formal public consultation exercise and that a further report be brought to Cabinet following completion of the consultation.  Agree that subject to the outcome of the public consultation exercise and Cabinet’s consideration of that report, the business case for the project, as set out in this paper, be presented to Council with a recommendation that the development of the Whitchurch Swimming and Fitness Centre be included in the capital programme.

2.2The public consultation has now been completed and added to subsequent engagement with key stakeholders, it demonstrated overwhelming support for a proposed new Swimming and Fitness Centre at Whitchurch. There were 286 respondents to the public consultation, with 89% agreeing with the location, and 73% agreeing that the proposed facility mix was adequate. 44% of respondents had previously used the swimming pool weekly, with 77% arriving by car, 59% by foot and 30% by cycle. A concern was raised about the potential loss of water vole habitat, which will be investigated. The full consultation and 7th September 2022- Whitchurch Swimming and Fitness Centre

engagement report is available at Appendix 1 and an updated Equalities, Social Inclusion and Health Impact Assessment is attached at Appendix 2.

2.3The total cost of the facility is now estimated at £13.100m. The Feasibility Study for the new Centre is attached at Appendix 3. The report asks for Cabinet to make certain recommendations to Council to enable the rebuild to proceed as quickly as possible, bearing in mind inflationary pressures. If there are major issues or the capital budget is exceeded and there is a need for increased capital spend, a further paper will be taken to Council for consideration.

2.4Providing development to the next stages goes as planned, building should start in 2024, with the new Centre completed in 2025.

Recommendations

That Cabinet:

 Agree the business case for the project, as set out in this paper, be presented to Council with a recommendation that the development of the Whitchurch Swimming and Fitness Centre be included in the capital programme with an initial budget of £13.100m, funded from Public Works Loan Board (PWLB).  Acknowledge the significant average annual revenue pressure of £0.509mm arising from approval of this scheme, reaching a maximum of £0.530m in 2028-29, and recommend that Council delegate resolution of this pressure to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism.  Recommend that Council delegates authority to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism, to procure, negotiate and agree the terms of any agreements/contracts necessary for the delivery of the project including, but not limited to:

o Agreeing the procurement strategy o Design Team procurement and appointment o Site Surveys and Investigations and relevant reports o Planning permissions o Tendering activities o Main contractor procurement and contract sign-off o Construction o Hand over

Contact: Clare Featherstone 01743 255067 2 7th September 2022- Whitchurch Swimming and Fitness Centre

REPORT

4. Risk Assessment and Opportunities Appraisal

4.1Opportunities Appraisal - the need for a new facility in Whitchurch

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Whitchurch Swimming Leisure Centre Feedback Report August 2022 vfiiAppendix 1 20 pages Download
PDF
Whitchurch Swimming and Fitness Centre Feasiblity StudyAppendix 2 64 pages Download
PDF
ESHIA, Whitchurch Swimming and Fitness CentreAppendix 3 25 pages Download
PDF
Whitchurch Swimming and Fitness CentreReport 20 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Shropshire

Search all
  1. Whitchurch Swimming and Fitness CentreThis decision
  2. Whitchurch Swimming Pool - Agreement for CIL FundingApproved
  3. Whitchurch Swimming and Fitness CentreAgreed
  4. Whitchurch Swimming Centre Feasibility StudyNoted
  5. Whitchurch Swimming Centre Options ReportApproved

More from Shropshire Cabinet

All decisions
MeetingDecisionOutcome
18 Nov 2026 MinutesThat the minutes of the meeting held on 14 October 2026 be confirmed as an accurate record. Decided Open
18 Nov 2026 Crisis & Resilience Fund – 6-month Progress UpdateThat Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open
18 Nov 2026 Council Tax Support - Proposed Changes 2027-28 Consultation ResponsesThat Cabinet: 1. Considered the responses received to the statutory consultation. 2. Agreed the following changes to ... Agreed Open
18 Nov 2026 Financial Monitoring Report Quarter 2 2026/27That Cabinet: A. Supported the Q2 favourable revenue outturn forecast of £0.051m. B. Supported the significant advers... Noted Open
18 Nov 2026 Treasury Management Update Quarter 2 2026/27That Cabinet: 1. Endorsed the summary of the wider economic environment and the Council’s borrowings and investments ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies