That C ouncil : · Agree t he business case for the project , as set out in this paper, with a recommendation that the development of the be included in the capital programme with a n initial budget of £1 3 .1 00 m and fund ing source assumed to be prudential borrowing from Public Works Loan Board (PWLB) . · Acknowledge the significant average annual revenue pressure of £0. 5 0 9m m arising f rom approval of this scheme , reaching a maximum of £0.530m in 2028-29, and recommend t hat Council delegate resolution of this pressure to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism . · R ecommend that Council delegates authority to the Executive Director of Place , in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism, to procure, negotiate and agree the terms of any a greements/contracts necessary for the delivery of the project includin g , but not limited to : o Agree ing the procurement strategy o Design Team procurement and appointment o Site Surveys and Investigations and relevant reports o Planning permissions o Tendering activities o Main contractor procurement and contract sign-off o Construction o Hand over
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
2.1At its meeting on 27th April 2022 Cabinet agreed the following recommendations:
Note and acknowledge progress and actions undertaken to meet the recommendations of the Cabinet report in June 2021 Agree that the proposed plans be the subject of a formal public consultation exercise and that a further report be brought to Cabinet following completion of the consultation. Agree that subject to the outcome of the public consultation exercise and Cabinet’s consideration of that report, the business case for the project, as set out in this paper, be presented to Council with a recommendation that the development of the Whitchurch Swimming and Fitness Centre be included in the capital programme.
2.2The public consultation has now been completed and added to subsequent engagement with key stakeholders, it demonstrated overwhelming support for a proposed new Swimming and Fitness Centre at Whitchurch. There were 286 respondents to the public consultation, with 89% agreeing with the location, and 73% agreeing that the proposed facility mix was adequate. 44% of respondents had previously used the swimming pool weekly, with 77% arriving by car, 59% by foot and 30% by cycle. A concern was raised about the potential loss of water vole habitat, which will be investigated. The full consultation and 7th September 2022- Whitchurch Swimming and Fitness Centre
engagement report is available at Appendix 1 and an updated Equalities, Social Inclusion and Health Impact Assessment is attached at Appendix 2.
2.3The total cost of the facility is now estimated at £13.100m. The Feasibility Study for the new Centre is attached at Appendix 3. The report asks for Cabinet to make certain recommendations to Council to enable the rebuild to proceed as quickly as possible, bearing in mind inflationary pressures. If there are major issues or the capital budget is exceeded and there is a need for increased capital spend, a further paper will be taken to Council for consideration.
2.4Providing development to the next stages goes as planned, building should start in 2024, with the new Centre completed in 2025.
2.5On 7th Sept 2022, Cabinet agreed the following recommendations:
Agree the business case for the project, as set out in this paper, be presented to Council with a recommendation that the development of the Whitchurch Swimming and Fitness Centre be included in the capital programme with an initial budget of £13.100m, funded from Public Works Loan Board (PWLB). Acknowledge the significant average annual revenue pressure of £0.509mm arising from approval of this scheme, reaching a maximum of £0.530m in 2028-29, and recommend that Council delegate resolution of this pressure to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism. Recommend that Council delegates authority to the Executive Director of Place, in consultation with the Portfolio Holder for Communities, Culture, Leisure & Tourism, to procure, negotiate and agree the terms of any agreements/contracts necessary for the delivery of the project including, but not limited to:
o Agreeing the procurement strategy o Design Team procurement and appointment o Site Surveys and Investigations and relevant reports o Planning permissions o Tendering activities o Main contractor procurement and contract sign-off o Construction o Hand over
Recommendations
That Council:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies