That Cabinet: 1. Approved the recommended amendments to the conditions of the contract and the commercial arrangements as set out in Section 7.5 of this report. 2. Authorised the implementation of the amendments via a deed of variation to the current contract between the Council and the Contractor for a period of 12 months from 1st April 2025. 3. Give delegated authority for the Executive Director of Place to explore and agreed further contract amendments, in consultation with the Portfolio Holder for Highways and Transport. That Cabinet: 1. Approved the recommended amendments to the conditions of the contract and the commercial arrangements as set out in Section 7.5 of this report. 2. Authorised the implementation of the amendments via a deed of variation to the current contract between the Council and the Contractor for a period of 12 months from 1st April 2025. 3. Give delegated authority for the Executive Director of Place to explore and agreed further contract amendments, in consultation with the Portfolio Holder for Highways and Transport.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
2.1The Highways and Environment Term Services Contract (TMC18) (“HETSC”) was awarded to Kier Transportation (the Contractor) in 2017 and commenced service delivery on 1st April 2018.
2.2The initial Service Period is 7 years; accordingly, the contract will end on 31st March 2025.
2.3The conditions of contract allow the Council to offer a maximum of three extensions to the Service Period, each of a one-year duration. The Council’s offer of an extension requires the Contractor’s acceptance to become effective.
2.4Council Officers and contractor representatives have been working together to discuss the basis for extending the contract. Both parties have proposed amendments to the current contract. 20/11/24 CABINET: Highways Term Maintenance Contract – Proposed Extension to Support Future Highways Model
2.5Significant change and service transformation have occurred across the highway service following a difficult start to the Kier Contract 2018. The contract and its management and delivery has evolved and now focuses on key areas of strength. The “mixed economy model” is now embedded, significantly benefiting Shropshire and our residents. Shropshire Council now has far greater control and influence over services, with Kier focused on areas of strength and value for money.
2.6As a result of the value the contract brings, it is recommended that a single-year extension to the Service Period be agreed upon, which will include certain amendments to the current agreement that will ensure that the contract aligns with the objectives of the Council and supports the plan and vision for the future service. The proposed extension period will ensure service continuity and give the Council sufficient time to shape and develop options for an optimal future operating model that aligns with the Council's vision. This acknowledges the current financial uncertainties within the Council and nationally.
2.7This report sets out the proposed amendments to the contract terms and seeks approval to implement them via a Deed of Variation to the contract.
3. Recommendations That Cabinet:
3.1Approve the recommended amendments to the conditions of the contract and the commercial arrangements as set out in Section 7.5 of this report.
3.2Authorise the implementation of the amendments via a deed of variation to the current contract between the Council and the Contractor for a period of 12 months from 1st April 2025.
3.3Give delegated authority for the Executive Director of Place to explore and agree further contract amendments, in consultation with the Portfolio Holder for Highways and Transport.
Report 4. Risk Assessment and Opportunities Appraisal
4.1[Financial Risk] Should the recommendations not be approved; the Council will not have a contract or a full suite of alternatives in place to deliver vital services across the highway network. This would leave the council at risk and may well lead to higher cost of highways services and materials from April 2025. Additionally, the cost of procurement will need to commence immediately, estimated at a minimum of £300,000. Therefore mitigation to preserve the current cost structure and avoid reputational risk and the cost of procurement is to undertake the extension.
Contact: [email protected] 2 20/11/24 CABINET: Highways Term Maintenance Contract – Proposed Extension to Support Future Highways Model
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.