First line assurance: Adult Social Care Outturn Management Update
AgreedFinance2 papers
AI summaryAudit & Governance Committee agreed current Adult Social Care outturn assurance is first-line only and asked Internal Audit to revisit in early March 2026 to validate savings documentation and controls. Councillor Lumby abstained.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedInternal Audit to revisit for independent validation
Money£16.1m to £31.2mPeople Directorate overspend variance in 2024/25
What happens nextInternal Audit review in early March 2026Of actions taken on the six recommendations
Who it affectsNot stated
What was decided
The committee agreed that the current assurance was first-line only, rather than independently validated, and proposed that Internal Audit revisit the area.
The committee noted the update on progress with implementing the recommendations arising from the Internal Audit review. Report 3.1
Councillor Lumby abstained from voting on the recommendation.
Why
Year-end financial monitoring for 2024/25 showed a significant variance in the People Directorate, with the forecast overspend changing from £16.1m at period 11 to £31.2m at outturn. Report 7.1
The former Chief Executive commissioned an Internal Audit review to find the causes and identify mitigations against recurrence. Report 7.1
A financial emergency was declared by Cabinet on 10 September 2025, and the council is operating in an environment of unprecedented financial demands.
What happens next
Internal Audit will undertake a review of the actions taken in response to the recommendations in early March 2026. Report 2.2, 7.4
Officers will continue to implement the six recommendations, of which three were complete and three remained in progress at the time of the report. Report P16
Continued collaboration between Adult Social Care budget holders and the Finance team is planned to clarify roles and improve in-year monitoring. Report 4.1, P7
The money
£16.1m People Directorate forecast overspend at period 11 in 2024/25 Report 7.1
£31.2m People Directorate outturn overspend for 2024/25 Report 7.1
Options considered
Rejected: Treat management update as sufficient first-line assurance. Committee judged assurance to be first-line only and wanted independent Internal Audit validation
Chosen: Ask Internal Audit to revisit to provide independent validation of controls, savings documentation and prevention of recurrence. To strengthen the assurance on savings and reduce the risk of a repeat outturn variance
Implications
Financial: Cabinet declared a financial emergency on 10 September 2025, with all non-essential spend to be stopped and essential spend challenged.
Financial: Better monitoring should reduce the need for unbudgeted use of reserves to cover overspends. Report P7
Risk: Weakness in monitoring and budget-holder and Finance team coordination is being addressed through the six recommendations, with Internal Audit revisiting in early March 2026. Report 4.1, 7.4
Climate: The report notes it does not directly make decisions on energy, carbon or climate change adaptation, but the committee will consider these within the governance and control environment. Report P12
Who and where
Adult Social Care budget holders within the People Directorate Report 4.1, P7
Members and officers who rely on public financial reporting Report P7
Council reserves, which may face unbudgeted use if overspends are not addressed in year Report P7
Timeline
17th July 2025: Financial Outturn 2024/25 reported to Council Report P20
Summer 2025: Internal Audit review of the People Directorate outturn variance took place Report 7.2
September 2025: Internal Audit findings discussed Report 7.2
10 September 2025: Cabinet declared a financial emergency
27th November 2025: Audit & Governance Committee received initial update on the audit and recommendations Report 7.3, P20
31st December 2025: Implementation deadline for three of the six recommendations, all reported as complete Report P16
2026: Implementation deadline for the remaining two recommendations, both still in progress Report P16
Last month (before 5 February 2026): Final Internal Audit report issued Report 7.2
5th February 2026: This committee meeting Report P4
Early March 2026: Internal Audit planned to review actions taken on the recommendations Report 2.2, 7.4
Plain English for the jargon
Period 11 / Period 12 / Period 13: Monthly stages in the council's financial monitoring cycle, with period 13 being the year-end outturn stage.
Outturn: The actual final spending and income position at the end of the financial year.
First-line assurance: Initial checks and controls carried out within the service itself, rather than by an independent reviewer.
People Directorate: The council directorate covering Adult Social Care and other people services, which recorded the £16.1m to £31.2m overspend variance.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item90
Resolved
To agreed that the current assurance was first-line only and to proposed that Internal Audit revisit the area to provide independent validation of controls, especially regarding savings documentation and prevention of recurrence. Councillor Lumby abstained from voting for this recommendation.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
2.1This report provides an update to the Committee on progress made to date with addressing the issues that contributed to the significant change in financial monitoring positions between period 11 and period 12 during 2024/25.
2.2Internal Audit are planning to undertake a review of the actions undertaken in response to the recommendations in early March 2026.
Recommendations
3.1Note with appropriate comment the update provided in this report.
[email protected] 1 Audit & Governance Committee 5th February 2026- Adult Social Care Outturn Management Update
Report 4. Risk Assessment and Opportunities Appraisal
4.1Continued collaboration to develop the preparation and monitoring of Adult Social Care budgets is necessary to improve understanding of the roles and responsibilities between budget holders and the Finance team. This clarity will;
a) enhance the reliability and accuracy of in year financial monitoring and enable corrective and timely action to be taken, which at outturn (as in 2024/25) is too late to undertake for that financial year. b) Strengthen the understanding of the information between the two teams, including simplification and improvement of the reporting to enable the service to respond to risks and mitigations accordingly. c) Ensure public reporting of the council’s financial position is accurate and enables Members and Officers to take any necessary decisions to improve the Council’s financial position. d) Prevent the need for unbudgeted use of reserves to mitigate overspends against budgets.
4.2Implementation of the recommendations as set out in Appendix 1 and a continuous review throughout the year will mitigate against a reoccurrence of the 2024/25 outturn issue.
5. Financial Implications 5.1. Shropshire Council continues to manage unprecedented financial demands and a financial emergency was declared by Cabinet on 10 September 2025. The overall financial position of the Council is set out in the monitoring position presented to Cabinet on a monthly basis. Significant management action has been instigated at all levels of the Council reducing spend to ensure the Council's financial survival. While all reports to Members provide the financial implications of decisions being taken, this may change as officers and/or Portfolio Holders review the overall financial situation and make decisions aligned to financial survivability. All non-essential spend will be stopped and all essential spend challenged. These actions may involve (this is not exhaustive): • scaling down initiatives, • changing the scope of activities, • delaying implementation of agreed plans, or • extending delivery timescales.
5.2Current Financial Monitoring reports to Cabinet set out the challenging position of the Council and the pressures on budgets and reserves. Ensuring robust financial monitoring is essential to operating within agreed budgets and taking corrective action where necessary. The implementation of the recommendations arising from the review will support the strengthening of the current financial monitoring process.
[email protected] 2 Audit & Governance Committee 5th February 2026- Adult Social Care Outturn Management Update
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.