Resolved
To endorse the Internal Audit Annual Plan for 2026/27.
AI summaryShropshire Council's Audit and Governance Committee has endorsed the Internal Audit Annual Plan for 2026/27, scheduling audits across social care, IT, finance, governance and procurement.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
To endorse the Internal Audit Annual Plan for 2026/27.
Audit and Governance Committee, 5th February 2026, Draft Internal Audit Plan 2026/27
Committee and Date Item 14
Audit and Governane Committee
5th February 2026 Public 10:00am
Draft Internal Audit Annual Plan 2026/27 Responsible Officer: Barry Hanson
email: [email protected] Tel: [phone removed]
Cabinet Member (Portfolio Holder): Heather Kidd, Leader of the Council Duncan Kerr, Chairman of the Audit and Governance Committee Roger Evans, Portfolio Holder – Finance
1. Synopsis The risk based Internal Audit Plan, 2026/27 is presented to the Audit and Governance Committee for approval. It will evaluate the effectiveness of the Council’s risk management, internal control and governance processes across all Directorates.
2. Executive Summary 2.1. This report provides Members with the proposed risk based Internal Audit Plan for 2026/27. The annual plan will provide coverage across the high-risk areas of the Council and delivers internal audit services to a range of external organisations. It takes account of issues identified by the clients’ risk management frameworks, including the risk appetite levels set by management for the different activities or parts of the organisations audited. The proposed plan considers the requirement to produce an annual internal audit opinion and assurance framework.
2.2Given the need to respond flexibly to both the Council’s demands and the available resources in the team at different times throughout the year, the plan is
Contact: [email protected] 1 Audit and Governance Committee, 5th February 2026, Draft Internal Audit Plan 2026/27
designed to ensure that all external contracts are completed and for Shropshire Council, must do areas of work are delivered alongside an element of high-risk audits. If there is further recruitment within the year allocations will be made on risk priority matched to auditor skill sets from high-risk areas within the Council not covered in the planned element. The draft 2026/27 Internal Audit plan is set out in Appendix A and the call off list of in Appendix B. Delivery outcomes will continue to be reported to Audit and Governance Committee through the standard performance reports presented throughout the financial year.
3. Recommendations 3.1. The Committee is asked to consider and endorse, with appropriate comment, the approach taken to create the proposed Internal Audit Plan for 2026/27 and approve its adoption.
Report 4. Risk Assessment and Opportunities Appraisal 4.1. Under the Audit and Governance Committee’s terms of reference, reviewing the risk-based audit plan, including internal audit resource requirements, the approach to using other sources of assurance and any other work upon which reliance is placed, is an important responsibility. In considering this plan Members should be assured that it is linked to the Council’s key risks and provides enough coverage to ensure a reasonable opportunity to identify any weaknesses in the internal control environment. Risks identified as being critical to the Council’s operations will be reported and rectified where possible and viable.
4.2Areas to be audited within the plan have been considered using risk register information both at an operational and strategic level in addition to liaison with key members and officers.
4.3The recommendations contained in this report are compatible with the provisions of the Human Rights Act 1998. There are no direct environmental, equalities, consultation or climate change consequences of this proposal.
4.4The Internal Audit Annual Plan satisfies the Global Internal Audit Standards (GIAS), CIPFA’s Application Note on the GIAS and the Accounts and Audit Regulations 2015 part 2. The latter sets out the requirements on all relevant authorities in relation to internal control, including requirements in respect of accounting records, internal audit and review of the system of internal control. Specifically:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Third line assurance: Internal Audit Plan 2026/27Report | 811 KB | DownloadRead as text |
Follow Audit & Governance Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Minutes of the previous meeting held on the 25 June 2026That the Minutes of the meeting of the Audit & Governance Committee held on the 25 June 2026 be approved as a true re... | Approved | Open |
| 15 Jul 2026 | Second line assurance: Annual Treasury ReportTo approve the actual 2025/26 prudential and treasury indicators in this report. 2. To note the annual treasury manag... | Approved | Open |
| 15 Jul 2026 | Overall assurance: Annual Governance Statement and Code of Corporate Governance 2025/26to note the Draft Annual Governance Statement 2025/26 and Code of Corporate Governance. to request that external audi... | Noted | Open |
| 15 Jul 2026 | Second line assurance: Approval of the Council's Draft Statement of Accounts 2025/26To approve the draft Statement of Accounts. | Approved | Open |
| 15 Jul 2026 | Exclusion of Press and PublicThat in accordance with the provision of Schedule 12A of the Local Government Act 1972, Section 5 of the Local Author... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.