Progress on the Prioritised Schemes

Agreed Committee 1 paper

Berkshire Local Transport Body agreed this item on Thursday 14 November 2013. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

It was agreed to add the approximate timescale from approval to delivery in future updates. Slough to Heathrow MRT – Western and Central Sections: progress report noted, including the status of local funding from Section 106 contributions and the Council. North Wokingham Distributor Road: progress report noted and agreed to add a more detailed programme timetable to future reports. South Wokingham Distributor Road: the risk of developers failing to reach agreement with Network Rail on the new bridge over the railway was noted. Discussions with Network Rail had started. It was noted the scheme was slightly behind schedule. Following discussion, the BLTB agreed to note the updates provided on the progress of the schemes and confirmed its support for the eight prioritised schemes. Resolved – (a) That the progress of each of the schemes be noted. (b) That the continued support of BLTB for each of the eight schemes be confirmed.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To provide a progress report for each of the eight schemes given Programme Entry status by the decision of the LTB on 18 July 2013. 2. To give the LTB an opportunity to review each of these schemes and to ask questions of the council promoting the schemes.

Recommendation

3. The BLTB are requested to resolve: (a) That the progress of each of the schemes be noted. (b) That its continued support for each of the eight schemes be confirmed.

Other Implications

Financial

4. The DfT has confirmed the allocation of Local Majors Capital Funding for Berkshire LTB as £14.5m over four years, commencing April 2015. This confirmation needs to be understood in the context of other Government announcements in relation to the preparation of Strategic Economic Plans, Growth Deals and the allocation of the Local Growth Fund.

5. The DfT have confirmed that the financial allocation of £14.5m to TVB LEP as part of the emerging Growth Deal is guaranteed, and that this element of the settlement will be exempt from the competition for Local Growth Fund allocations.

6. They have further confirmed that while the financial allocation is confirmed, there is local discretion available to the LEP to rescind the LTB prioritisation in favour of other priorities identified for the Strategic Economic Plan.

7. In Thames Valley Berkshire, there is no intention of using this discretion. The LEP has confirmed its support for the work of the LTB, and for the conclusions of the prioritisation process conducted earlier in 2013. Further, the LEP intends to promote not only the 8 schemes with programme entry status within the Strategic Economic Plan, but a range of other proposals, including transport schemes previously considered by the LTB.

8. Each scheme promoter is continuing to develop the scheme proposals at their own cost and their own risk. Recommendations for financial approval will only be brought to the LTB after the promoter has submitted a full business case proposal, and after that has been subjected to an independent assessment.

Item 3 - Progress on the Prioritised Schemes 9. In other developments, the DfT has announced financial support for a transport scheme in Thames Valley Berkshire from Tranche 3 of Local Pinch Point funding, and invited bids for a Tranche 4. The Reading London Road A4 Eastern Gateway scheme was approved in Tranche 3, and Bracknell Forest, Slough, West Berkshire and Wokingham have submitted one bid each in Tranche 4.

10. Slough Borough Council is the Accountable Body responsible for BLTB and has thus agreed to take on the responsibilities including legal advice, appropriate use of funds through Section 151 Officer, adherence to the Assurance Framework, maintaining official records of BLTB proceedings and overall responsibility for decisions taken in the case of legal challenge. Slough Borough Council will incur additional costs for some of these activities. Whilst the Council is able to accommodate some of the costs in kind, where there are significant cash costs, notably if there are costs to commission project bid evaluations, these costs will be shared.

Risk management

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress on the Prioritised SchemesReport 184 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 15 attended
PB
Councillor Pamela BaleCommittee Member, present
KB
Cllr Keith BakerCommittee Member, apologies, sent representative
MB
Cllr Marc Brunel-WalkerCommittee Member, present
GH
Cllr Geoffrey HillCommittee Member, apologies
SM
Councillor Sohail MunawarCommittee Member, present
TP
Councillor Tony PageCommittee Member, present
SC
Steve Capel-DaviesCommittee Member, present
MH
Melvyn HaleCommittee Member, present
IF
Ian FrostCommittee Member, apologies
RL
Robert LynchCommittee Member, present
KM
Kathy MatthewsCommittee Member, apologies
PV
Philip von HeydebreckCommittee Member, present

All 15 on the meeting page

On this subject at Slough

Search all
  1. Progress on the Prioritised SchemesThis decision
  2. Progress on the Prioritised SchemesNoted
  3. Progress on the Other Prioritised SchemesNoted
  4. Progress on the Prioritised SchemesNoted

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies