Resolved
Resolved - That the progress report be noted.
Berkshire Local Transport Body noted this item on Thursday 24 July 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved - That the progress report be noted.
1. To provide a progress report for the 17 schemes identified in the Strategic Economic Plan, and to give detailed reports on the eight schemes given Programme Entry status by the decision of the LTB on 18 July 2013.
2. To give the LTB an opportunity to review each of these schemes and to ask questions of the council promoting the schemes.
3. You are requested to: • Urge scheme promoters to seek out and secure further contributions from non-LTB sources in order to maximise the number of schemes that can be supported • Note the progress of each of the schemes • Confirm your continued support for each of the schemes
Other Implications
Financial
4. The DfT has previously confirmed the allocation of Local Majors Capital Funding for Berkshire LTB as £14.5m over four years, commencing April 2015. The Local Growth Deal includes this sum, and in addition approves £11.1m for spending in 2015/16 and indicative approval for £69.05m over the five years 2016/17- 2020/21.
Table 1 – Available Finance
£m 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Growth Deal 11.10 - - - - - 11.10 “Tail” of scheme above - 2.00 - - - - 2.00 Indicative approval - 67.05 67.05 LTB 3.625 3.625 3.625 3.625 - - 14.50 Total 94.65
5. Table 2 below sets out the seventeen SEP schemes in four sections: • LTB priorities 1 and 2 to be funded from the devolved LTB guaranteed funding • LTB Programme Entry schemes approved in the Local Growth Deal • Local Growth Deal approved schemes without Programme Entry Status
Item 9 BLTB 24 July 2014 - Progress on the Other Prioritised Schemes – Page 1 • Other SEP schemes without either Programme Entry status or Local Growth Deal approval
6. The numerical reference given to each scheme is the scheme number in the SEP Implementation Plan Annexe where you can find a full description of each scheme.
7. The allocation of funding to financial years reflects the detail set out in the SEP Implementation Plan Annexe, except where Local Growth Deal approval has not been given for a 2015/16 start. In these cases the finance requested has been deferred by one year to reflect the amounts in the Local Growth Deal. These amounts are indicated with *.
Table 2 – Scheduling of Schemes
SEP 2015 2016 2017 2018 2019 2020 Bal- refer- £m Total /16 /17 /18 /19 /20 /21 ance ence LTB Funding – LTB Programme Entry Schemes Newbury: Kings Road 2.01 1.335 1.000 0 0 0 0 0 2.335 Link Road Reading: Green Park 2.06 2.290 2.625 1.485 0 0 0 0 6.400 Railway Station U Unallocated 0 0 2.175 3.625 0 0 0 5.800 Total LTB 3.625 3.625 3.625 3.625 0 0 0 14.500 Local Growth Deal Funding – LTB Programme Entry Schemes
Wokingham Distributor 2.04 a 0 4.800 4.800 4.800 4.800 4.800 0 24.000 Roads
Bracknell: Coral Reef 2.07 2.100 0 0 0 0 0 0 2.100 Roundabout Slough: Rapid Transit 2.08 3.600 2.000 0 0 0 0 0 5.560 Phase 1 Reading: East Reading 2.14 0 6.800 8.800 0 0 0 0 15.600 Mass Rapid Transit Local Growth Deal Funding – Schemes without Programme Entry Status Bracknell: Warfield Link 2.02 3.500 0 0 0 0 0 0 3.500 Road Newbury: London Road 2.03 1.900 0 0 0 0 0 0 1.900 Industrial Estate 2.09 Sustainable Transport: 0 1.900* 1.500* 0.800* 0 0 0 4.200 (part) NCN 422 2.09 Sustainable Transport: 0 0.545* 0 0 0 0 0 0.545 (part) A4 Cycle (with Bucks) Slough: A332 2.10 0 2.700* 0 0 0 0 0 2.700 Improvements Reading: South 2.11 0 2.960* 0 0 0 0 0 2.960 Reading MRT phase 1 Reading: South 2.12 0 0 1.520* 0 0 0 0 1.520 Reading MRT phase 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress on the Other Prioritised SchemesReport | 190 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.