Audit and Corporate Governance Committee agreed this item on Thursday 24 September 2015. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

It was agreed that the Assistant Director, Finance and Audit, would liaise with the Chair to determine which meeting the next report would be brought to. Resolved – (a) That the Internal Audit update for Quarter 1 2015/16, Counter Fraud Activity and Council’s Risk Register be noted. (b) That the report on Contract Management be noted, and that a further update be brought to a future meeting of the Committee.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

Purpose of report

The purpose of this report is to:

 Report to Members on the progress against the 2015/16 Internal Audit Plan up to Quarter 1  Report to Members on the progress of the implementation of Internal Audit recommendations  Report to Members the Council’s latest counter-fraud activity  Report to Members the Council’s Risk Register

Recommendation

That Audit & Corporate Governance Committee Members comment on and note the reports.

3 Sustainable Community Strategy Priorities

The actions contained within the attached reports are designed to improve the governance of the organisation and will contribute to all of the emerging Community Strategy Priorities

Priorities:  Economy and Skills  Health and Wellbeing  Regeneration and Environment  Housing  Safer Communities

4 Other Implications

4.1Financial

None other than those detailed in the internal audit reports

Risk management

This report concerns risk management across the Council 4.3 Human Rights Act and Other Legal Implications

n/a

4.4Equalities Impact Assessment

There is no identified need for an EIA

5 Supporting Information

5.1Overview

5.1.1 Baker Tilley have completed a number of audits from their work during the first quarter of 2015-16.

5.1.2 The overall Internal audit reports have continued to be finalised at a more appropriate rate than in the previous financial year. Of the 2014-15 internal audits, four remain outstanding for the Council:

 Procurement  arvato performance management  Educational Services – Contract Management Arrangements

5.1.3 No reports in respect of schools remain outstanding.

5.1.4 The Committee saw many of the reports summary in draft at the previous meeting. In the Annual Governance Statement that was approved at the previous meeting, many of these reports were highlighted as red and were included in the Statement as key issues, for example contract management. The Council is working to improve contract management arrangements and there is a separate appendix on contract management audits summarised the key issues found over the past 12 months.

5.1.5 The corporate risk register has been updated to reflect the latest risks.

5.2Internal Audit Q1 2015-16 progress report

5.2.1 The full report is attached at appendix A.

5.2.2 The internal audit plan for 2015-16 was set very much with a focus on addressing identified risks in the Corporate Risk Register, External audit’s risk focus and in light of the 5YP.

5.2.3 It is pleasing to note that in respect of the budget setting audit for 2015-16 that this has again been assessed as green and can provide some strong assurance for the second year in a row to members and senior management around the processes governing how the budget was set for 2015-16 in a time of increasingly scarce resources.

5.3Finalising Internal Audit Reports

5.3.1 The table below shows those Internal Audits that remain in draft and are yet to be finalised as at 1st September 2015. This list of Audit Title Draft Issued Responses due Client sponsor Rating Education Services Contract Management 37 14 15 07 May 2015 21 May 2015 Jane Wood Red Procurement 40 14 15 21 May 2015 4 June 2015 Roger Parkin Amber Red Avarto Performance management 45 14 15 19 June 2015 3 July 2015 Roger Parkin Red

5.3.2 The Risk and Insurance Officer regularly monitors the progress of the implementation of “high” or “medium” recommendations made following Internal Audit reports. Below is a graph that shows the percentage of recommendations that have either been implemented, are in progress, no action has been taken, or the recommendation has been superseded.

5.3.3 Bakertilly has received assurance that the Council’s Internal Audit recommendation tracking tool implemented by the Council is a useful tool for the Committee.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit and Risk Management Update: Quarter 1 2015/16Report 115 KB DownloadRead as text
PDF
Governance Update Appx C Contract Mgt SummaryReport 303 KB Download
PDF
Governance Update Corporate Risk Register Appx BReport 149 KB Download
PDF
Governance Update Progress Report Appx AReport 182 KB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
NC
Councillor Nimrit ChohanChair, present
FA
Councillor Fiza A MatloobVice-Chair, present
ZA
Councillor Zaffar AjaibCommittee Member, apologies
AS
Councillor Amarpreet S. DhaliwalCommittee Member, present
FM
Councillor Fatima MansoorCommittee Member, present
MN
Councillor Mohammed NazirCommittee Member, apologies
RS
Councillor Rajinder S SandhuCommittee Member, present
GD
Graham DaviesCo-Optee, apologies
AK
Ajay KwatraCo-Optee, apologies
RR
Ronald RobertsCo-Optee, present
AS
Alan SunderlandCo-Optee, present
PC
Parish Councillor Scott BryantParish Council Representative, absent

All 15 on the meeting page

On this subject at Slough

Search all
  1. Audit and Risk Management Update: Quarter 1 2015/16This decision
  2. 2018/19 Updated Audit Plan and Revised Risk AssessmentNoted
  3. Audit & Risk Management Update - Quarter 4 2019/20Noted
  4. Audit and Risk Management Update Quarter 3 2019/20Agreed
  5. Audit and Risk Management Update - Quarter 2 2019/20Agreed
  6. Audit and Risk Management Update - Quarter 1 2019/20Noted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open