It was agreed that the Assistant Director, Finance and Audit, would liaise with the Chair to determine which meeting the next report would be brought to. Resolved – (a) That the Internal Audit update for Quarter 1 2015/16, Counter Fraud Activity and Council’s Risk Register be noted. (b) That the report on Contract Management be noted, and that a further update be brought to a future meeting of the Committee.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
Report to Audit and Corporate Governance Committee
Purpose of report
The purpose of this report is to:
Report to Members on the progress against the 2015/16 Internal Audit Plan up to Quarter 1 Report to Members on the progress of the implementation of Internal Audit recommendations Report to Members the Council’s latest counter-fraud activity Report to Members the Council’s Risk Register
Recommendation
That Audit & Corporate Governance Committee Members comment on and note the reports.
3 Sustainable Community Strategy Priorities
The actions contained within the attached reports are designed to improve the governance of the organisation and will contribute to all of the emerging Community Strategy Priorities
Priorities: Economy and Skills Health and Wellbeing Regeneration and Environment Housing Safer Communities
4 Other Implications
4.1Financial
None other than those detailed in the internal audit reports
Risk management
This report concerns risk management across the Council 4.3 Human Rights Act and Other Legal Implications
n/a
4.4Equalities Impact Assessment
There is no identified need for an EIA
5 Supporting Information
5.1Overview
5.1.1 Baker Tilley have completed a number of audits from their work during the first quarter of 2015-16.
5.1.2 The overall Internal audit reports have continued to be finalised at a more appropriate rate than in the previous financial year. Of the 2014-15 internal audits, four remain outstanding for the Council:
5.1.3 No reports in respect of schools remain outstanding.
5.1.4 The Committee saw many of the reports summary in draft at the previous meeting. In the Annual Governance Statement that was approved at the previous meeting, many of these reports were highlighted as red and were included in the Statement as key issues, for example contract management. The Council is working to improve contract management arrangements and there is a separate appendix on contract management audits summarised the key issues found over the past 12 months.
5.1.5 The corporate risk register has been updated to reflect the latest risks.
5.2Internal Audit Q1 2015-16 progress report
5.2.1 The full report is attached at appendix A.
5.2.2 The internal audit plan for 2015-16 was set very much with a focus on addressing identified risks in the Corporate Risk Register, External audit’s risk focus and in light of the 5YP.
5.2.3 It is pleasing to note that in respect of the budget setting audit for 2015-16 that this has again been assessed as green and can provide some strong assurance for the second year in a row to members and senior management around the processes governing how the budget was set for 2015-16 in a time of increasingly scarce resources.
5.3Finalising Internal Audit Reports
5.3.1 The table below shows those Internal Audits that remain in draft and are yet to be finalised as at 1st September 2015. This list of Audit Title Draft Issued Responses due Client sponsor Rating Education Services Contract Management 37 14 15 07 May 2015 21 May 2015 Jane Wood Red Procurement 40 14 15 21 May 2015 4 June 2015 Roger Parkin Amber Red Avarto Performance management 45 14 15 19 June 2015 3 July 2015 Roger Parkin Red
5.3.2 The Risk and Insurance Officer regularly monitors the progress of the implementation of “high” or “medium” recommendations made following Internal Audit reports. Below is a graph that shows the percentage of recommendations that have either been implemented, are in progress, no action has been taken, or the recommendation has been superseded.
5.3.3 Bakertilly has received assurance that the Council’s Internal Audit recommendation tracking tool implemented by the Council is a useful tool for the Committee.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.