Resolved
Resolved – That the minutes of the Berkshire Local Transport Body (BLTB) held on 21 st July 2016 be approved as a correct record.
Berkshire Local Transport Body approved this item on Thursday 17 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the minutes of the Berkshire Local Transport Body (BLTB) held on 21 st July 2016 be approved as a correct record.
Berkshire Local Transport Body – Meeting held on Thursday, 21st July, 2016.
Present:- Members Authority Councillor Page Reading Borough Council Councillor Bryant (deputising for West Berkshire Council Councillor Simpson. Arrived 4.26pm) Ingrid Fernandes Thames Valley Berkshire LEP Peter Howe Thames Valley Berkshire LEP Councillor Matloob Slough Borough Council Councillor Richards Wokingham Borough Council Graeme Steer Thames Valley Berkshire LEP Matthew Taylor Thames Valley Berkshire LEP Councillor Turrell (deputising for Bracknell Forest Council Councillor Brunel-Walker)
Apologies Councillor Brunel-Walker Bracknell Forest Council for Councillor Bicknell The Royal Borough of Windsor & Maidenhead Absence:- Councillor Simpson West Berkshire Council
Also present:- Councillor Sleight (deputy member for Wokingham Borough Council)
Apologies for Absence:- Councillor Bicknell, Charles Eales and Ian Frost
PART 1
1. Declarations of Interest
Matthew Taylor declared that his company had a minor commercial interest in scheme 2.08 Slough: Rapid Transit Phase 1.
2. Election of Chair 2016/17
Resolved – That Councillor Page be elected Chair of the Berkshire Local Transport Body (BLTB) for the ensuing municipal year.
(Councillor Page in the Chair for the remainder of the meeting)
3. Election of Deputy Chair 2016/17
Resolved – That Charles Eales be elected Deputy Chair of the Berkshire Local Transport Body (BLTB) for the ensuing municipal year. Berkshire Local Transport Body - 21.07.16
4. Minutes of the meeting held on 17th March 2016
Resolved – That the minutes of the Berkshire Local Transport Body (BLTB) held on 17th March 2016 be approved as a correct record.
5. Request for additional funding for 2.05 Newbury Sandleford Park
A report was considered on the case for increasing the funding allocated to scheme 2.05 Newbury Sandleford Park. The scheme had an existing allocation of £2,000,000, however, detailed modelling had resulted in a request for a further £900,000 from the unallocated capital sum. A separate report elsewhere on the agenda sought full financial approval for the revised sum of £2,900,000. The BLTB noted that the unallocated capital sum was £5,827,000 and there were two other schemes seeking additional funding later on the agenda.
The scheme would help deliver the Sandleford Park strategic housing site to the south of Newbury by providing supporting infrastructure to access the development area. The total estimated cost of the scheme had risen significantly and the additional LEP funding sought would cover 17% of this increase in costs. After due consideration, the BLTB agreed the additional funding as requested.
Resolved – That the financial allocation for 2.05 Newbury Sandleford Park be increased from £2,000,000 to £2,900,000.
6. Financial approval 2.05 Newbury Sandleford Park
A report was considered that sought financial approval for scheme 2.05 Newbury Sandleford Park. The scheme would deliver additional accesses to Sandleford Park, a strategic development site of up to 2,000 dwellings, and unlock land for a new primary school and enterprises. The scheme had been assessed on the basis of the increased LEP allocation of £2.9m as agreed in Minute 5.
The Independent Assessment, as attached at Appendix 1 to the report, recommended giving full financial approval to the scheme, acknowledging that the scheme was primarily being progressed on its development rather than transport benefits. After due consideration, it was agreed to give the scheme full financial approval on the terms set out in the report.
Resolved – That scheme 2.05 Newbury Sandleford Park be given full financial approval in the sum of £2,900,00 over three financial years (2017/18, 2018/19, 2019/20) on the terms of the funding agreement set out at paragraph 14 step 5 of the report. Berkshire Local Transport Body - 21.07.16
7. Request for additional funding for 2.06 Reading: Green Park Railway Station
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the meeting held on 21st July 2016Minutes | 86 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.