Resolved
Resolved – That the progress made on the schemes previously given programme entry system, as set out in Appendix 1 to the report, be noted.
Berkshire Local Transport Body noted this item on Thursday 17 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the progress made on the schemes previously given programme entry system, as set out in Appendix 1 to the report, be noted.
1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planii.
2. The government subsequently announced further support to Thames Valley Berkshireiii. Growth Deal 2 included four new transport schemes worth a total of £7.5m, taking the headline figure for transport schemes to £102.1m. This report provides progress reports on all schemes, whether announced in GD1 or GD2.
3. £14.7m was approved for spending in 2015/16 and, following a successful review of year 1, £17.0m is approved for spending in 2016/17, of which £16.35m is currently programmed. The remainder has an indicative approval over four future years 2017/18 to 2020/21 with a provisional profile.
4. That you note the progress made on the schemes previously given programme entry status, as set out in Appendix 1
Other Implications
Financial
5. Thames Valley Berkshire LEP has been granted freedoms and flexibilities in managing the Growth Deal Capital Programme. This means that we will receive an annual allocation of capital within which it will be our responsibility to manage the allocation to individual schemes. This is a positive development for TVB LEP and recognises the confidence that government has in our governance arrangements.
6. The government has confirmed the allocation of funding for 2016/17 and there is a provisional profile for payments in the financial years 2017/18 - 2020/21.
Item 5 BLTB 17 November 2016 Thames Valley Berkshire Local Growth Deal 2015/16-2020/21 Table 1: Available Finance for Transport Schemes in TVB Growth Deal
£m 2015/16 – 2020/21 LTB previously approved 14.5 Growth Deal 1 56.1 Growth Deal 1 “DfT Major 24.0 Schemes” Growth Deal 2 7.5 Total 102.1
7. The profile and status of the available money in each year is as follows:
Table 2: Growth Deal Financial Allocation for 2015/16
£m 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Carried forward from previous year Combined Growth Deal 1 and 2 and 14.7 16.4 - - - - 31.1 LTB Allocation Approved To carry forward to following year Growth Deal 1 (DfT Major - - 24.0 24.0 Schemes) indicative) Combined Growth Deal 1 and 2 and - - 16.8 18.8 10.7 0.7 47.0 LTB Allocation indicative profile Total 14.7 16.4 71.0 102.1
8. Table 3 sets out the final allocation of scheme finance for 2015/16 and 2016/17 and the provisional allocation for future financial years, which are subject to alteration following the government’s confirmation of the Growth Deal funding profile.
Table 3 – Growth Deal 1 and 2: Confirmed and provisional allocations to schemes
SEP Scheme Name Status 15/16 16/17 17/18 18/19 19/20 20/21 £m Ref Newbury: King’s GD 2.01 On site - 1.340 1.000 - - - 2.340 Road Link Road 1 Bracknell: Warfield GD 2.02 On site 3.500 - - - - - 3.500 Link Road 1 Newbury: London GD 2.03 On site 0.500 1.400 - - - - 1.900 Rd Ind Estate 1 Wokingham: DfT Programme 2.04 - - - - 15.900 8.100 24.000 Distributor Roads major entry 2.05 Newbury: GD Full - - 1.000 1.400 0.500 - 2.900
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 460 KB | Download |
PDF |
Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21Report | 133 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.