Resolved – That the minutes of the meeting held on 29 th September 2016 be approved as a correct record.
Audit and Corporate Governance Committee approved this item on Wednesday 11 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the minutes of the meeting held on 29 th September 2016 be approved as a correct record.
Audit and Corporate Governance Committee – Meeting held on Thursday, 29th September, 2016.
Present:- Councillors Sadiq (Chair), Bedi (Vice-Chair), Hussain, Rana, Sarfraz and Swindlehurst.
Co-Opted Independent Members: [name removed] and [name removed] Member:- Councillor Jackson (Colnbrook with Poyle)
Apologies for Absence:- Councillor Amarpreet Dhaliwal, Davies and [name removed] 1
10. Declarations of Interest
None were received.
11. Minutes of the Last Meeting held on 12th July, 2016
Resolved – That the minutes of the meeting held on 12th July 2016 be approved as a correct record.
12. Presentation: arvato Contract Progress Update
The Interim Chief Executive, Roger Parkin, reminded the Committee that the arvato contract had entered the fifth year of the partnership and introduced John Wybrant, Key Account Director and Kevin Hales, Slough Site Director to present an overview of contractual performance for the Thames Valley Transactional Services Partnership for the year ending March 2016.
[name removed] advised that arvato had succeeded in transferring its headquarter operations to Slough and the arvato Farnham Road site now employed in excess of 600 staff. New business had been created, including the recent addition of BMW to its contact centre and it was expected that the premises would be full at the end of the year.
In terms of performance, there was a 1.2% improvement in the council tax collection rate for the financial year 2015/16 compared to previous years and this had equated to collecting more than £7m revenue for the council.
The Committee noted that arvato continued to engage in the local community and was a member of Slough Aspire and Slough Business Community Partnership. Members were informed that the end of Year 5 target of employing 36 apprenticeships had been exceeded with 46 currently in post. The Partnership had also been nominated for the 2016 National Outsourcing Awards.
A Member asked what challenges arvato faced in terms of delivery of service. [name removed] stated although significant improvements had been made in ICT Audit and Corporate Governance Committee - 29.09.16
infrastructure, keeping abreast of technological developments was vital in terms of delivery of service. arvato would also assist in supporting the Council on its digital transformation framework. It was highlighted that a Robotic Process Automation Programme would be piloted in early October. The scheme would initially be used within the Revenue and Benefits Section following which it would be applied to a number of other areas.
Resolved – That arvato Officers be thanked for their presentation and details of the presentation be noted.
13. Financial Statements 2015/16
The Head of Financial Reporting, [name removed], outlined details of the report. Over the summer period the Council’s external auditors, BDO (independently appointed by the Audit Commission for the 2015-16 financial year), conducted a review of the Council and the financial statements produced.
BDO were required to provide an opinion on the Financial Statements and a Value for Money opinion to the Council by the 30th September.
The report from BDO covers the two opinions that they provide and detail how the Council complies, or otherwise, with these opinions. BDO also include recommendations for the Council going forward.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Last Meeting held on 29 September 2016Minutes | 78 KB | DownloadRead as text |
Follow Audit and Corporate Governance Committee at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... | Approved | Open |
| 11 Mar 2026 | Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... | Agreed | Open |
| 11 Mar 2026 | Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... | Agreed | Open |
| 11 Mar 2026 | Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. | Noted | Open |
| 11 Mar 2026 | Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.