Internal Audit Update - Quarter 2 2016/17

Agreed Finance 2 papers

Audit and Corporate Governance Committee agreed this item on Wednesday 11 January 2017. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

It was agreed that the report format would be reviewed in future to provide members with a clearer overview of current and outstanding issues rather than historic information. Concern was raised about the overall strength of the governance and management issues given the fact that five of eight most recently finalised reports were not fully assured and in view of the weaknesses in some of the Council’s policies and procedures highlighted by recent governance issues. Members made a number of suggestions about how to review the relevant policies and strengthen the governance arrangements. A cross-party task group was suggested comprising members of the Committee, Member Panel on the Constitution and the Employment & Appeals Committee and it was agreed to explore the feasibility and scope of this proposal noting that work was already underway to review the Constitution. At the conclusion of the discussion, the Internal Audit Progress Report was noted. Resolved – (a) That the report be noted. (b) That the possibility of establishing a Working Group to review the Council’s Policies and Procedures, including Governance Arrangements, be explored further.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

Purpose of report

The purpose of this report is to report to members on the progress against the 2016/17 Internal Audit Plan up to Quarter 2.

2. Recommendation(s)/Proposed Action

That the Audit & Corporate Governance Committee comment on and note the report.

3. The Slough Joint Wellbeing Strategy, the JSNA and the Five Year Plan

The Slough Joint Wellbeing Strategy (SJWS) is the document that details the priorities agreed for Slough with partner organisations. The SJWS has been developed using a comprehensive evidence base that includes the Joint Strategic Needs Assessment (JSNA). Both are clearly linked and must be used in conjunction when preparing your report. They have been combined in the Slough Wellbeing Board report template to enable you to provide supporting information highlighting the link between the SJWS and JSNA priorities.

3a. Slough Joint Wellbeing Strategy Priorities

The report indirectly supports all of the strategic priorities and cross cutting themes.

The maintenance of excellent governance within the Council to ensure that it is efficient, effective and economic in everything it does is achieve through the improvement of corporate governance and democracy by ensuring effective management practice is in place.

The report helps achieve the corporate objectives by detailing how the Council is delivering the Council’s budget in line with the approved budget. 4. Other Implications

(a) Financial

There are no direct financial implications of this report, however failure to implement actions raised could have an impact on the Council’s ability to achieve it financial objectives.

(b) Risk Management

This report is concerned with the risk management and other governance arrangements of the Council

(c) Human Rights Act and Other Legal Implications

There are no human rights issues arising from this report

(d) Equalities Impact Assessment

There are no equality issues arising from this report

5. Supporting Information

5.1The Council have finalised the following ten reports relating to the 2015/16 plan since the previous Audit and Corporate Governance Committee meeting.

5.2The IT Business Continuity and Disaster Recovery, Income and Debtors, Asset Register and Treasury Management audits resulted in only ‘Partial Assurance’ and the Follow Up report demonstrated that only ‘Little’ progress had been made in implementing previous recommendations.

5.3The opinions and numbers of recommendations have been reported previously for these reports as part of RSM’s Internal Audit Annual Report.

 Treasury Management – Partial Assurance  Income and Debtors – Partial Assurance  IT Business Continuity and Disaster Recovery - Partial Assurance  Asset Register – Partial Assurance  Follow Up – Little Progress  Five Year Plan Outcomes – Reasonable Assurance  Rent Accounts – Reasonable Assurance  Governance – Reasonable Assurance  IT Strategy – Reasonable Assurance  Khalsa Primary School - Reasonable Assurance

5.42016/17 Internal Audit Plan The Council have finalised eight reports relating to the 2016/17 plan since the previous Audit and Corporate Governance Committee meeting. These are in the following areas:

 Business Continuity – No Assurance  Budgetary Control and Financial Reporting – Partial Assurance  Budget Setting – Reasonable Assurance  School Financial Value Standard – Reasonable Assurance  Agresso: Transfer of Balances – Partial Assurance  Voids – No Assurance  Information Governance – No Assurance  Cippenham Nursery School – Substantial Assurance

5.5Five of these reports; Information Governance, Voids, Budgetary Control, Agresso: Transfer of Balances and Business Continuity resulted in negative assurance opinions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Progress AppendixAppendix 646 KB Download
PDF
Internal Audit Update: Quarter 2 2016/17Report 80 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
SS
Councillor Shabnum SadiqChair, present
MB
Councillor Madhuri BediVice-Chair, present
AS
Councillor Amarpreet S. DhaliwalCommittee Member, present
MK
Councillor Mandeep K. RanaCommittee Member, present
SS
Councillor Sunyia SarfrazCommittee Member, present
JC
Councillor James C SwindlehurstCommittee Member, present
RR
Ronald RobertsCo-Optee, present
AS
Alan SunderlandCo-Optee, apologies
LL
Dr Louis LeeObserver, present
PC
Parish Councillor Raymond JacksonParish Council Representative, present
PC
Parish Councillor Raja Muhammad FayyazParish Council Representative, apologies
SK
Shabana KauserDemocratic Services Officer, expected

On this subject at Slough

Search all
  1. Internal Audit Update - Quarter 2 2016/17This decision
  2. Internal Audit Plan and Charter 2026/27Approved
  3. Internal Audit Mid-Year Progress ReportNoted
  4. Internal Audit Mid-Year Progress ReportNoted
  5. Finance and Commercial Internal Audit Recommendations UpdateNoted
  6. Digital, Data and Technology Internal Audit Recommendations UpdateNoted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open