Resolved
Resolved – That the progress made on schemes previously given programme entry status be noted.
Berkshire Local Transport Body noted this item on Thursday 20 July 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the progress made on schemes previously given programme entry status be noted.
1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, as amended by Growth Deal 2 (£10.2 million further support to Thames Valley Berkshireii) with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planiii.
2. In April 2017, the government announced Growth Deal 3iv, including six new transport schemes for Thames Valley Berkshire worth a total of £33.826m, taking the headline figure for transport scheme grants to £135.926m. This report provides progress reports on all 25 approved schemes.
3. £14.742m was spent on transport schemes in 2015/16 and £16.546m in 2016/17. We are planning to spend £16.716m this year. The remainder has an indicative approval over three future years 2018/19 to 2020/21.
4. That you note the progress made on the schemes previously given programme entry status, as set out in Appendix 1.
Other Implications
Financial
5. Thames Valley Berkshire LEP has been granted freedoms and flexibilities in managing the Growth Deal Capital Programme. This means that we will receive an annual allocation of capital within which it will be our responsibility to manage the allocation to individual schemes. This is a positive development for TVB LEP and recognises the confidence that government has in our governance arrangements.
6. The government has confirmed the allocation of funding for 2017/18 and there is a provisional profile for payments in the financial years 2018/19 - 2020/21.
Item 6 BLTB 20 July 2017 - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Table 1: Available Finance for Transport Schemes in TVB Growth Deal
£m 2015/16 – 2020/21 LTB previously approved 14.5 Growth Deal 1 56.1 Less unallocated - 0.7 55.4 Growth Deal 1 “DfT Major Schemes” 24.0 Growth Deal 2 7.5 Growth Deal 3 33.8 Plus unallocated 0.7 34.5 Total 135.9
7. The profile and status of the available money in each year is as follows:
Table 2: Growth Deal Financial Allocation for 2015/16
£m 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total Combined Growth Deal 1, 2, 3 14.7 16.5 16.7 - - - 47.9 and LTB Allocation approved Growth Deal 1 (DfT Major - - - 24.0 24.0 Schemes) indicative Combined Growth Deal 1, 2 and 3 - - - 32.1 21.5 10.4 64.0 LTB Allocation indicative profile Total 14.7 16.5 16.7 88.0 135.9
8. Table 3 sets out the final allocation of scheme finance for 2015/16, 2016/17 and 2017/18 and the provisional allocation for future financial years, which are subject to alteration following the government’s confirmation of the Growth Deal funding profile.
Table 3 – Growth Deal 1, 2 and 3 Scheme Funding Profiles
SEP Scheme Name Status 15/16 16/17 17/18 18/19 19/20 20/21 £m Ref Newbury: King’s Rd 2.01 GD 1 On site - 1.335 1.000 - - - 2.335 Link Road Bracknell: Warfield 2.02 GD 1 On site 3.500 - - - - - 3.500 Link Road Newbury: London Rd 2.03 GD 1 Complete 0.500 1.400 - - - - 1.900 Industrial Estate Wokingham: DfT Programme 2.04 - - - - - - - Distributor Roads major entry Newbury: Sandleford 2.05 GD 2 Full approval - - 1.000 1.400 0.500 - 2.900 Park
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
to Item 6 BLTB 20 July 2017 Thames Valley Berkshire Local Growth Deal 2015-16 to 2020-21Appendix 1 | 1.2 MB | Download |
PDF |
Thames Valley Berkshire Local Growth Deal 2015-16 to 2020-21Report | 134 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.