Audit and Risk Management Update Quarter 4 2017/18

Noted Finance 5 papers

Audit and Corporate Governance Committee noted this item on Thursday 8 March 2018. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

Resolved - That details of the Internal Audit Reports and implementation of recommendations and the Corporate Risk Register be noted.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

List of Outstanding audit actions APPENDIX 1 New Chart

Location Action Required Management Actions Recommendation Rating Implementation Status Target Date Person Responsible Completion Notes

Title: Schools Financial Value Standard Finance and Resources We identified instances where the SFVS Each of the schools identified as not Medium No Action Taken 31/12/16 Follow up audit finding that this action was return had been submitted without an submitting a signed SFVS return (Chalvey not complete appropriate signature from the Chair of the Early Years Centre; Lea Nursery; Slough Governing body. Centre Nursery; St Anthony’s Catholic Primary School; St Joseph’s Catholic High School; and St Mary’s CE Primary School) will be contacted and requested to re- submit their return, duly signed by the Chair of the Governing Body / Management Committee of the school.

Finance and Resources 5 We noted not all schools produced action Refer to management action regarding the Medium Partially Completed 31/12/16 George Grant Neil advised that he would raise this with plans to address areas of non-compliance. review of SFVS returns by the Council’s George Grant and Coral Miller in February Where action plans were produced, we Schools Finance team. 2017 identified these either did not cover all Advised by George Grant 17th Aug 2017 areas of non-compliance or actions were not time-bound and/or assigned

Finance and Resources A reminder will be issued to the Chair of the A reminder will be issued to the Head Medium No Action Taken 28/02/17 George Grant Completed as per George Grant 17/08 Governing Body of Khalsa Primary School Teachers of the schools identified with Amended as per q2 follow up highlighting the importance of ensuring exceptions regarding the narrative provided SFVS responses accurately reflect the within their SFVS returns (Arbour Vale arrangements within the school. School; Chalvey Early Years Centre; Lea The Council will also ensure that any other Nursery; Slough Centre Nursery; St schools found to have a lack of accuracy Anthony’s Catholic Primary School; St with their SFVSs will be sent a reminder as Ethelbert’s Catholic Primary School) of the actioned in the point above. need to provide sufficient narrative to evidence the basis for their responses to each standard. Finance and Resources We noted that the main reason for the The Council will create a tailored best Medium Partially Completed 30/09/17 Nic Barani There are plans in progress and will be above actions not being completed properly practice guide that will be provided to all the completed shortly was because no action plan template had maintained schools annually. This will been used. Where Cippenham Nursery had include:  The minimum amount of used an action template, we confirmed all narrative expected to satisfy each of the 25 actions were appropriately SMART standards  A breakdown of key SFVS (Specific, Measurable, Attainable, Realistic criteria expected of the school  A link to and Time-bound). the detailed SFVS ‘Support Notes’ and ‘Additional Resources’ guidance provided by the Education Funding Agency.

Title: Contract Management Change Finance and Resources To ensure contracts are managed in a This recommendation will be addressed as Medium 31/12/17 Neil Wilcox consistent and robust manner, a Council part of the contract management guidance wide contract management framework which is currently being developed. should be applied to manage contracts across the Council. Finance and Resources The Council should establish a Corporate This will be taken forward as part of the Medium 31/12/17 Neil Wilcox Contract Management function regardless overall Council restructure. The Head of of the decision around the contract Contract Management will report to the management model i.e. centralised, de- Service Lead Governance. centralised and hybrid; and A Head of Contracts post should be created to implement and manage the CCM.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A&R Mgt Appx 1Report 127 KB DownloadRead as text
PDF
A&R Mgt Appx 2Report 46 KB Download
PDF
A&R Mgt Appx 3Report 56 KB Download
PDF
A&R Mgt Appx 4Report 126 KB Download
PDF
Audit and Risk Management Update Quarter 4 2017/18Report 113 KB Download

At this meeting

Whole meeting

Who was there

12 of 14 attended
NC
Councillor Nimrit ChohanVice-Chair, present
PB
Councillor Preston BrookerCommittee Member, present
DC
Councillor Diana CoadCommittee Member, present
AS
Councillor Amarpreet S. DhaliwalCommittee Member, present
AD
Councillor Arvind DhaliwalCommittee Member, present
MN
Councillor Mohammed NazirCommittee Member, present
KU
Councillor Khaula UsmaniCommittee Member, present
RR
Ronald RobertsCo-Optee, present
AS
Alan SunderlandCo-Optee, present
IZ
Iqbal ZafarCo-Optee, present
LL
Dr Louis LeeObserver, present
PC
Parish Councillor Raymond Jackson Colnbrook with Poyle Parish CouncilParish Council Representative, present

All 14 on the meeting page

On this subject at Slough

Search all
  1. Audit and Risk Management Update Quarter 4 2017/18This decision
  2. 2018/19 Updated Audit Plan and Revised Risk AssessmentNoted
  3. Audit & Risk Management Update - Quarter 4 2019/20Noted
  4. Audit and Risk Management Update Quarter 3 2019/20Agreed
  5. Audit and Risk Management Update - Quarter 2 2019/20Agreed
  6. Audit and Risk Management Update - Quarter 1 2019/20Noted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies