Resolved
Resolved – That the One Year Evaluation Reports from the scheme promoter and independent assessor be noted.
Berkshire Local Transport Body noted this item on Thursday 12 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the One Year Evaluation Reports from the scheme promoter and independent assessor be noted.
1. At your meeting in March 2017, you approved guidance for the preparation of one- and five-year- on impact reports for BLTB funded local transport schemes.
2. This report introduces the impact report for scheme 2.08 Slough: Rapid Transit, Phase 1.
3. You are recommended to note the reports from the scheme promoter and the independent assessor.
Other Implications
Financial
4. There are no direct financial implications of this report.
5. The government requires all LEPs to have Assurance Frameworks which set out governance arrangements and financial procedures. One of the specific requirements for transport schemes is to require scheme promoters to submit impact reports one and five years post implementation.
Human Rights Act and Other Legal Implications
6. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the Assurance Framework.
Supporting Information
7. Slough Borough Council received £5.6m towards the £9.1m cost of this scheme.
8. The one-year on impact report is attached at Appendix 1; and the independent assessor’s report is attached at Appendix 2. Conclusion
9. The SMaRT 1YIR provides a good overview of the status of the project and some insight into the overall impact to date. Overall, it is not considered to meet all of the requirements for a 1YIR due to limitations in the availability of quantified metrics demonstrating the impact of the scheme.
10. The report provides a good overview of the infrastructure elements of the scheme. It highlights some of the challenges that have been met through the construction process and demonstrated that these did not unduly impact upon cost, albeit did significantly delay the delivery of the scheme.
11. The report also provides a good assessment of the operation of bus services along the western section of the infrastructure. The scheme has clearly facilitated a more effective approach to delivering bus services on behalf of major business employers along the corridor. It is estimated that there has been a 50% increase in patronage since the SMaRT service was launched primarily coming from business users (data from SMaRT Steering Group/Stewarts).
12. A number of developments have been granted planning permission with some starting on site but with no development complete and occupied.
13. The scheme was delivered on time and close to budget (+1.6%).
14. The Independent Assessors have found it hard to verify whether or not this project has currently delivered against its objectives. As such, TVB LEP has agreed with Slough Borough Council that they will undertake:
- with the SMaRT steering group to evaluate the increase in patronage since the start of the public service - to provide the journey time savings that have been achieved since the launch of SMaRT - to provide an assessment outputs on air quality in the area through the AQMA - to ensure that all relevant learnings from phase 1 are shared for subsequent phases of the SMaRT scheme development
15. There is no further action required.
Background Papers: None. Appendix 1
Slough: Mass Rapid Transit 1 (SMaRT)
Berkshire Local Transport Body (BLTB)
One Year On Evaluation report
February 2020
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.08 Slough: Rapid Transit, Phase 1: One Year Evaluation ReportReport | 2.2 MB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.