Resolved – That scheme 2.36 Wokingham: Coppid Beech Park and Ride be given full financial approval in the sum of £2,400,000 in 2020/21 on the terms of the funding agreement set out in paragraph 11 step 5 of the report. (Malcolm Kempton and Stuart Atkinson left the meeting)
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme 2.36 Wokingham: Coppid Beech Park and Ride.
2. The purpose of this scheme, supported by Wokingham Council and Bracknell Forest Council in their work to deliver cross-boundary solutions to transport issues, is to relieve congestion along key road corridors. The scheme comprises:
- 250 parking spaces (including six disabled spaces) - Two Park and Ride bus stops - Bus shelter facilities and - Spaces for motorcycle and cycle parking.
The scheme lies on a development site named Keephatch Beech, which will provide 300 new homes on previously undeveloped land, south of the A329(M). The proposed Park and Ride provision would be predominately used by employment trips during weekdays, and leisure trips during weekends, into Wokingham and Bracknell Town Centre.
Recommendation
3. You are recommended to give scheme 2.36 Wokingham: Coppid Beech Park and Ride full financial approval in the sum of £2,400,000 in 2020/21 on the terms of the funding agreement set out at paragraph 11 step 5 below.
Other Implications
Financial
4. In January 2019 a re-prioritisation exercise was undertaken regarding previously allocated Growth Deal Funds which were returned to the Growth Deal “pot” for re-allocation. Scheme 2.36 Wokingham: Coppid Beech Park and Ride is funded from this reallocation and was given Programme Entry status by the BLTB on 31 January 2019 (minute 34b refers).
5. This report recommends that Wokingham: Coppid Beech Park and Ride be authorised to draw down the capital sum £2,400,000 from the Local Transport Body funding for this scheme, subject to usual capital grant letter conditions.
6. The funding agreement set out at paragraph 11 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
7. The risk management arrangements already put in place by the Local Transport Body are as follows:
The Assurance Framework1 has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme The funding agreement set out at paragraph 11, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
8. Slough Borough Council will provide legal support for the BLTB should any questions arise.
Supporting Information
9. The scheme will be carried out by Wokingham Borough Council.
10. The full details of the scheme are available from the Wokingham Borough Council website2.
A summary of the key points is given below:
Task Timescale Planning application Submitted 30 April 2020 Construction November 2020 to October 2021 Open to public November 2021
Activity Funder Cost (approx) Scheme development Wokingham Borough Council £0.0m Major scheme funding Berkshire Local Transport Body £2.4m Section 106 agreements Developers etc £0.652m Total £3.052m
1 http://www.thamesvalleyberkshire.co.uk/berkshire-strategic-transport-forum 2 https://www.myjourneywokingham.com/sustainable-travel/bus-travel/park-and-ride/ 11. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of Assurance Framework.
Assurance Framework 2.36 Wokingham: Coppid Beech Park & Ride Check list
Wokingham Coppid Beech Park & Ride will relieve congestion along key road corridors and deliver
- 250 parking spaces (including six disabled spaces)
- Two Park and Ride bus stops
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.