Resolved
Resolved – That the reports from the scheme promoter and the independent assessor be noted.
Berkshire Local Transport Body noted this item on Thursday 11 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the reports from the scheme promoter and the independent assessor be noted.
1. At your meeting in March 2017, you approved guidance for the preparation of one- and five-year- on impact reports for BLTB funded local transport schemes.
2. Per reports received at the March and July 2021 BLTB meetings, it was agreed that due to the Covid pandemic, the pending one-year impact reports would be temporarily suspended until a sufficient resumption of normal, or near normal, traffic movements resumed. It has been agreed by the Berkshire Transport Officers that we are probably now at this point, enabling reports to be drawn up and submitted.
3. This report introduces the one-year impact report for scheme 2.21 Slough: Langley Station Access.
4. You are recommended to note the reports from the scheme promoter and the independent assessor.
Other Implications
Financial
5. There are no direct financial implications of this report.
6. The government requires all LEPs to have Assurance Frameworks which set out governance arrangements and financial procedures. One of the specific requirements for transport schemes is to require scheme promoters to submit impact reports one- and five-years post implementation.
Human Rights Act and Other Legal Implications
7. Slough Borough Council will provide legal support for the BLTB should any questions arise on the application of the Assurance Framework.
Supporting Information
8. Slough Borough Council received £1.5m in LGF towards the cost of this £5.26m scheme (including £3.5m from Network Rail).
9. The one-year on impact report is attached at Appendix 1; and the independent assessor’s report is attached at Appendix 2.
Item 8: BLTB 11 November 2021 - Scheme 2.21 Slough: Langley Station Access - One Year Evaluation Report Conclusion
10. The Independent Assessor concludes the SBC one-year impact report is a well-constructed and balanced document, making good use of the available evidence at this stage. Whilst the agreed delay in producing this report was agreed with TVB LEP and Berkshire Local Transport Body no quantitative evidence or survey data was provided at this stage.
11. The report also provides very helpful photographs of the before and after context for the scheme which brings to life the changes which have been implemented because of TVB LEP and SBC investment. While the report helpfully outlines how the scheme has addressed the multiple issues and challenges surrounding safety and access to Langley station, particularly for pedestrians and cyclists.
12. SBC recognises that undertaking a one-year impact report is too soon to provide a realistic assessment of the actual outcomes of the scheme. The Council expects to be able to provide a much more detailed review of the scheme at the five-year evaluation report milestone.
13. The key points for consideration, both to enhance the future outcomes of the project and to facilitate wider learning, include:
While the report provides a positive indication of the scheme improving the safety and accessibility to Langley Station, providing quantitative data for the five-year report will be important to evaluate the impact and outcomes of the scheme. Data includes measuring the uptake in public transport in the area, walking and cycling counts and usage numbers of the cycle docking station in Alderbury Road. This approach to future monitoring would provide greater assurance on project impacts and outcomes to TVLEP and SBC.
• The scheme focussed on addressing a number of challenges to do with accessibility and safety to Langley Station. Going beyond qualitative and inferred assessments of these types of observed changes, future monitoring and evaluation could also consider local survey data, air quality and road safety data along the corridor compared to pre-investment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.21 Slough: Langley Station Access: One Year Evaluation ReportReport | 2.9 MB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.