Resolved – That scheme GBF1 Slough: Langley High Street Widening Phase 3 be given conditional financial approval in the sum of £1,643,000 in 2021/22 from the Getting Building Fund on the terms of the funding agreement set out at paragraph 14 step 5 of the report, subject to meeting the following conditions: 1. SBC to demonstrate positive discussions with the landowners that result in documented outline agreement for the acquisition of the land required to develop the scheme. 2. Production of a revised, and more robust, assessment of scheme costs, post-preliminary scheme design. 3. Formal confirmation (e.g. S151 Officer letter) to cover SBC funding allocation, along with confirmation that SBC would cover any potential cost overruns; and 4. The scheme retain an initial Benefit Cost Ratio of at least 1.5:1. These conditions should be met at the earliest feasible date, but no later than 1 st March 2021.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To consider giving financial approval to scheme GBF1 Slough Langley High Widening – Phase 3.
2. This scheme is an extension to the junction and rail station accessibility improvement scheme delivered at Station Road/ Waterside Drive in 2018, and the junction improvement scheme delivered at High Street/ Station Road/ Langley Road in March 2020. It is also an extension to the adjoining proposed junction improvements at Meadfield Road/ High Street (referred to throughout this report as ‘Section 2’) and High Street widening between Elmhurst Road and Langley Road (referred to throughout this report as ‘Section 1’) which have conditional LEP funding approval.
3. Phase 1 of the scheme 2.45 Langley High Street Improvements was given financial approval at the June 2020 BLTB meeting and Phase 2 was given financial approval at the July 2020 BLTB meeting.
4. As a combined package of measures, Sections 1, 2 and 3 are promoted by Slough Borough Council to deliver a step-change in provision along the Langley High Street / Station Road corridor, supporting the planned closure of the parallel Hollow Hill Lane as part of the Western Rail Link to Heathrow (WRLtH), as well as enabling development growth across the corridor.
Recommendation
5. You are recommended to give scheme GBF1 Slough Langley High Widening Phase 3 conditional financial approval in the sum of £1,643,000 in 2021/22 from the getting Building Fund on the terms of the funding agreement set out at paragraph 14 step 5 below, subject to meeting the following conditions:
1) SBC to demonstration positive discussions with the landowners that result in documented outline agreement for the acquisition of the land required to develop the scheme;
2) Production of a revised, and more robust, assessment of scheme costs, post-preliminary scheme design;
3) Formal confirmation (e.g. S151 Officer letter) to cover SBC funding allocation, along with confirmation that SBC will cover any potential cost overruns; and
4) The scheme retains an initial Benefit Cost Ratio of at least 1.5 to 1.
These conditions should be met at the earliest feasible date, but no later than 1st March 2021.
Other Implications
Financial
Item 8 BLTB 12 November 2020 Financial Approval GBF1 Slough: Langley High Street Widening – Phase 3 6. A call for bids process was undertaken in January 2020 and a list of prioritised projects were agreed at the BLTB meeting March 2020. Scheme GBF1 Slough Langley High Street Widening phase 3 is funded from this reallocation. See Appendix 1.
7. This report recommends that Slough Borough Council be authorised to draw down the capital sum £1,643,000 from the recent Ministry of Housing, Communities and Local Government (MHCLG)/ Getting Building Fund (GBF) monies for this scheme.
8. The funding agreement set out at paragraph 14 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Risk management
9. The risk management arrangements already put in place by the Local Transport Body are as follows: • The Assurance Frameworki has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes • Hatch Regeneris have been appointed as Independent Assessors and have provided a full written report (see Appendix 2) on the full business case for the scheme • The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.