It was agreed that contact be made with the local Members of Parliament who had taken an interest in the scheme to make representations to seek to bring greater clarity to the delivery timescale. · 2.40 Windsor: Town Centre Package – the retendering exercise had been completed with a new contractor due to start work imminently. The scheme as due for completion in December 2023. The report was noted. Resolved – That the progress made on the schemes previously given programme entry status be noted.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, as amended by Growth Deal 2 (£10.2 million further support to Thames Valley Berkshireii) and Growth Deal 3 (Factsheet GD3iii) with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planiv; and on the progress of schemes funded by the Business Rates Retention Pilots (BRRP) of 2018/19 and 2019/20. This report also reports on the transport element of the Getting Building Fund (GBF) released in September 2020.
Recommendations
2. That you note the progress made on the schemes previously given programme entry status, as set out in the accompanying summary report.
Background
3. The headline figure for transport scheme grants under the three Local Growth Deals is £135.98m. This includes £24m of “DfT retained” allocation relating to the Wokingham Distributor Roads.
4. A further £25m has been released through BRRP1 (2018/19) and £11m from BRRP2 (2019/20).
5. Berkshire LEP has received £7.5m through the GBF, of which £2,093,000 has been allocated to two transport projects. GBF investment decisions were taken by the LEP through the Place Making Board (PMB) in consultation with senior officers from the six local authorities. The transport investments are reported to BLTB for information whilst the remaining GBF projects are reported to PMB. All projects are reported to the LEP Board.
6. £1.1m of BRRP has been allocated to two digital projects, including the TVB Smart City Cluster scheme, which was previously reported to BLTB. Digital projects are now governed by the Digital Infrastructure Group and not reported here.
Other Implications
Risk management
7. The delegation of programme management responsibilities to the LEP/BLTB brings risks. The well-established scrutiny of the transport projects given by both BST(O)F and BLTB meetings is designed to mitigate that risk.
8. There will be an element of risk for scheme promoters who invest in developing their schemes to full business case stage in accordance with the approved Assurance Frameworkv. However, there is also risk involved in not developing the schemes; that risk is that any reluctance to bring the schemes forward will result in any final approval being delayed or refused.
Item 4 BLTB 9 March 2023 - Thames Valley Berkshire Capital Programme Update 9. The risks associated with each scheme are monitored locally. Table 4 has been adapted to show the current risk rating of each of the live schemes.
10. There are currently no transport projects are currently rated with a red risk score however there is one transport project rated at an AR risk rating:
10.1Scheme 2.38 - Theale Station Upgrade – Currently has a RAG rating of AR. Work underway for Access for all footbridge, to complete late summer. Design & build contract for car park/ forecourt to be procured, delays likely.
Financial
11. Berkshire LEP has been granted freedoms and flexibilities by Government in managing Local Growth Funds. This means that RBWM, as the LEP’s Accountable Body, received an annual allocation and it was the LEP’s responsibility, via BLTB, to manage the award of LGF to individual schemes.
Table 1: Available Finance for Transport Schemes in TVB Local Growth Deal, BRRP and GBF
£m 2015/16 – 2022/23 Growth Deal 1 “DfT Major Schemes” 24.00 Local Growth Deal 111.98 BRRP 2018/19 and 2019/20* 34.88 Getting Building Fund 2.10 Grand Total 172.96
*Digital infrastructure projects have been removed from the totals above as these are governed by the Digital Infrastructure Group.
12. The profile and status of the available money in each year is as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.