Resolved
Resolved – That the progress made on schemes previously given programme entry status as set out in the report and appendix be noted.
Berkshire Local Transport Body noted this item on Thursday 13 July 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That the progress made on schemes previously given programme entry status as set out in the report and appendix be noted.
1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, as amended by Growth Deal 2 (£10.2 million further support to Thames Valley Berkshireii) and Growth Deal 3 (Factsheet GD3iii) with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planiv; and on the progress of schemes funded by the Business Rates Retention Pilots (BRRP) of 2018/19 and 2019/20. This report also reports on the transport element of the Getting Building Fund (GBF) released in September 2020.
2. That you note the progress made on the schemes previously given programme entry status, as set out in the accompanying summary report.
3. The headline figure for transport scheme grants under the three Local Growth Deals is £135.98m. This includes £24m of “DfT retained” allocation relating to the Wokingham Distributor Roads.
4. A further £25m has been released through BRRP1 (2018/19) and £11m from BRRP2 (2019/20).
5. Berkshire LEP has received £7.5m through the GBF, of which £2,093,000 has been allocated to two transport projects. GBF investment decisions were taken by the LEP through the Place Making Board (PMB) in consultation with senior officers from the six local authorities. The transport investments are reported to BLTB for information whilst the remaining GBF projects are reported to PMB. All projects are reported to the LEP Board.
6. £1.1m of BRRP has been allocated to two digital projects, including the TVB Smart City Cluster scheme, which was previously reported to BLTB. Digital projects are now governed by the Digital Infrastructure Group and not reported here.
Other Implications
7. The delegation of programme management responsibilities to the LEP/BLTB brings risks. The well-established scrutiny of the transport projects given by both BST(O)F and BLTB meetings is designed to mitigate that risk.
8. There will be an element of risk for scheme promoters who invest in developing their schemes to full business case stage in accordance with the approved Assurance Frameworkv. However, there is also risk involved in not developing the schemes; that risk is that any reluctance to bring the schemes forward will result in any final approval being delayed or refused.
Item 6 BLTB 13 July 2023 - Thames Valley Berkshire Capital Programme Update 9. The risks associated with each scheme are monitored locally. Appendix A shows the current risk rating of each of the live schemes, along with a comment relating to the status.
10. There is currently one transport project rated with a red risk score:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Thames Valley Berkshire Capital Programme UpdateAppendix | 236 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.