Audit and Corporate Governance Committee, Wednesday 19 July 2023 at 6.30pm

Internal Audit Annual Report 2022/23

Noted Finance 2 papers

Audit and Corporate Governance Committee noted this item on Wednesday 19 July 2023. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Resolved – (a) That the Internal Audit Annual Report 2022/23 be noted. (b) That the Committee expected management to ensure that the issues and weaknesses identified were being addressed in line with the timescales agreed.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

Recommendations

Committee is recommended to:

a) Note the contents of this report b) Seek assurance that all of the issues and weaknesses identified are being addressed in line with the timescales agreed.

Commissioner Review

Commissioners are content with the recommendations.

2. Report

Introductory paragraph

2.1The Council has outsourced the internal audit provision up to 31st March 2023 and the annual report provides an opinion on the overall adequacy and effectiveness of Slough Borough Council’s risk management, control and governance processes. All of the 2022/23 work has been completed, with 21 reports issued in final and six reports still in draft awaiting management responses. Background

2.2The Internal Audit Plan for 2022/23 was approved by the Audit and Corporate Governance Committee in March 2022 and this report provides the annual opinion on the risk management, governance and internal control processes.

In 2022/23 the internal audit team carried out a total of 27 internal audit reviews. The conclusion on the internal control framework at the Council, is that it was not adequate or effective. 27 audits were completed in 2022/23 and the following assurance levels were provided: • Minimal Assurance (negative) – nine audits • Partial Assurance (negative) – seven audits • Advisory (significant issues) – four reviews, one where the full scope could not be completed • Little Progress (negative) – three full follow up audits

• Reasonable Assurance (positive) – one audit • Advisory (no significant issues) – one review • Good Progress (positive) – one follow up audit • Reasonable Assurance (positive) – one full follow up audit.

The key findings from the negative opinions (minimal and partial assurances) and the negative outcomes from the follow up and advisory reviews with significant issues are summarised in the paper, but there are a range of significant issues that need to be addressed as a matter of urgency in some areas.

3. Implications of the Recommendation

Financial implications

There are potential some direct financial implications relating to the findings and weaknesses in the internal audit reports issued in 2022/23. The successful and timely implementation of management actions agreed will improve the council’s processes including those that underpin sound financial management, governance, risk management and internal control.

Failure to address those risks associated with the Directions from the Department for Levelling Up, Housing and Communities will impact the ability to secure the Authority’s compliance with the requirements of Part I of Local Government Act 1999. The Council has specific legal duties in relation to certain areas, such as managing health and safety risks and civil contingency. Effective internal audit is a key part of providing assurance on the adequacy of governance, risk management and internal control.

3.3Risk management implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IA Annual Report 2022.23 AppendixAppendix 365 KB Download
PDF
Internal Audit Annual Report 2022/23Report 97 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
FO
Councillor Frank O’KellyChair, present
EA
Councillor Ejaz AhmedVice-Chair, present
SA
Councillor Sabia AkramCommittee Member, present
RA
Councillor Robert AndersonCommittee Member, apologies
NR
Councillor Neel RanaCommittee Member, present
WS
Councillor Waqas SabahCommittee Member, present
MS
Councillor Mabu ShaikCommittee Member, present
RZ
Councillor Rifaqat ZaraitCommittee Member, apologies
NB
Naira Bukhari (Co-Optee Member)Co-Optee, apologies
SK
Shabana KauserClerk, expected
PK
Councillor Pavitar Kaur MannGuest, in attendance

On this subject at Slough

Search all
  1. Internal Audit Annual Report 2022/23This decision
  2. Internal Audit Plan and Charter 2026/27Approved
  3. Internal Audit Mid-Year Progress ReportNoted
  4. Internal Audit Mid-Year Progress ReportNoted
  5. Finance and Commercial Internal Audit Recommendations UpdateNoted
  6. Digital, Data and Technology Internal Audit Recommendations UpdateNoted

More from Slough Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
11 Mar 2026 Minutes of the Meetings held on 21st January and 12th February 2026.Resolved – That the minutes of the meetings held on 21 st January and 12 th February 2026 be approved as a correct re... Approved Open
11 Mar 2026 Action Progress ReportIt was agreed that the Chair, on behalf of the Committee, would write to the Lead Members responsible for regeneratio... Agreed Open
11 Mar 2026 Annual Governance Statement 2024/25 – End of Year Progress UpdateIt was agreed that the Committee would receive at a future meeting, data relating to late reports. A Member asked wha... Agreed Open
11 Mar 2026 Closing of Accounts debrief 2024/25Resolved - That the findings of the Grant Thornton audit work review and Council’s response to this be noted. Noted Open
11 Mar 2026 Closing of Accounts Plan and Timetable 2025/26Resolved - That the closing plan and timetable for the production of the 2025/26 Statement of Accounts be noted. Noted Open