AI summarySlough's Audit and Corporate Governance Committee noted the Finance Improvement Programme update: 34 projects, only 1 rated red by September 2025, funded partly by a £1.373m reserve.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee resolved to note programme progress
Money£1.373mSet aside in budget smoothing reserve for 2025/26
What happens nextIntervention until 30 November 2026Council remains under government intervention
Who it affectsCouncil financial recoveryProgramme is integral to financial recovery
What was decided
The committee noted the progress made on the Financial Improvement Programme. Report P1
Members asked questions about specific projects, including the Grants Register, and reviewed the appendix showing detailed progress on each project.
The committee noted the RAG and direction of travel status of all 34 projects as at September 2025. Report 2.6, P13
Why
The programme is essential to the council's improvement journey, addressing requirements set by government Directions to improve financial resilience and sustainability. Report P19
The council remains under statutory intervention until 30 November 2026, with Commissioners recommending the programme be reprofiled and prioritised into deliverable goals over a longer timeframe. Report P3, P18
Implementing project governance has reduced the number of red-rated projects, with only one project, addressing the level of reserves, remaining at red status. Report 2.6
What happens next
Further condense the 34 projects into appropriate themes, a review currently being undertaken by the Corporate Resources management team. Report 2.5
Continue monthly reporting with the external auditor and ongoing audit of 2024/25 accounts, with auditors on site from November 2025. Report P29
Finalise the Revenue and Welfare services restructure for consultation launch on 1 December 2025. Report P29
The money
£1.373m Set aside in budget smoothing reserve for the Finance Improvement Plan 2025/26 Report P17
Options considered
Chosen: Note the progress made on the Financial Improvement Programme. Recommendation to note progress; direction of travel generally positive with only 1 of 34 projects rated red Report P1
Implications
Financial: No direct financial implications from this report; the plan is funded through the £1.373m budget smoothing reserve and the transformation reserve. Report P17
Legal: The council is required by government Directions under the Local Government Act 1999 to improve financial resilience and sustainability; the programme is essential to meeting these Directions. Report P19
Risk: Corporate risk register includes CR09, Failure to achieve financial sustainability and a balanced MTFS, with the Finance Improvement Programme reported as a sub-risk on a quarterly basis. Report 3.3, P21, P22
Other: No environmental or equality implications identified. Report 3.4, P24
Who and where
Slough Borough Council as a whole, as part of its statutory financial improvement journey Report P19
Finance Improvement Board and Corporate Leadership Team, who receive quarterly assurance reports Report 2.1
External auditors, with whom monthly reporting has commenced Report P29
Budget holders, who are receiving new monthly system-generated reports and training Report P32
Council companies including JEH, GRE 5 and DISH, which are subject to 2024/25 audits Report P32
Timeline
18 September 2023: Finance Improvement Programme reset and refresh last formally reviewed by Cabinet Report 2.1
May 2024: Programme manager joined the council Report 2.3
Q4 2024/25: Finance Improvement Programme formally paused for two months for budget and MTFS activity Report 2.4
September 2024: 37 discrete projects within the programme themes Report 2.3
By September 2025: Programme reduced to 34 projects, with 1 red, 19 amber and 14 green RAG status Report 2.6, P13
15 September 2025: Last Cabinet update on the overall Recovery and Improvement plan Report 2.1
November 2025: Auditors on site for 2024/25 accounts Report P29
1 December 2025: Launch of consultation on Revenue and Welfare services restructure Report P29
January 2026: Target to include fraud awareness as an e-learning module in corporate induction Report P41
30 November 2026: Council's intervention under Statutory Directions currently confirmed to run until this date Report P18
Plain English for the jargon
RAG status: Red, Amber, Green rating used to indicate project progress and risk
MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document
CIPFA FM code: Chartered Institute of Public Finance and Accountancy Financial Management code, a standard for local authority finance
Directions: Statutory directions issued by the Minister of State for Local Government under the Local Government Act 1999
BAU: Business as Usual, meaning an activity is operating as a standard ongoing service rather than a project
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item45
Resolved
Decision Making Support (c) Financial Culture and Awareness (d) Medium Term Planning (e) Transformation and Automation (f) Deep dive projects A review reduced the number of projects to 34 and these may be further condensed in future. The direction of travel on the projects was generally positive and by September 2025 only 1 of the 34 projects were rated as red with 19 amber and 14 green. The appendix to the report set out the detailed progress against each of the projects and Members asked questions about the progress of specific projects including the Grants Register. The update was noted. Resolved – That the progress made on the Financial Improvement Programme be noted.
Word for word from the decision Slough published for this meeting.Source: democracy.slough.gov.uk
Report to Audit and Corporate Governance Committee
Recommendation
Committee is recommended to note the progress made on the Financial Improvement Programme.
Commissioner Review
The Councils financial improvement programme, which is integral to the Council’s financial recovery has evolved and expanded over time. The overall picture from the Councils self- assessment of its progress in delivering the programme, highlights a commitment to improvement despite a reduced pace and significant challenges remaining, in getting the basics right, achieving long-term financial stability and fulfilling its best value duty. Commissioners would recommend that the programme is reprofiled and prioritised into deliverable goals over a longer timeframe, focusing on strategic realignment with core business goals, maximising value and impact and resource availability for practical execution.
2. Report
Background
2.1A reset and refresh of the council’s Finance Improvement Programme was last reviewed formally by Cabinet on 18 September 2023 with updates since then forming part of the update on the overall Recovery and Improvement plan. The last update to Cabinet was on 15 September 2025. Internally, more frequent updates have continued to be provided though the Finance Improvement Board (previously Finance Board). On a quarterly basis, the corporate leadership team and Finance Improvement Board are provided with an assurance report measuring evidence led progress on the financial improvement journey including internal and external audit recommendations and against current finance related Directions. 2.2 The refresh led to a number of actions that were centred around the following themes:
a) Getting the basics right b) Governance and Decision Making Support c) Financial Culture and Awareness d) Medium Term Planning e) Transformation and Automation f) Deep dive projects
2.3By September 2024, there were 37 discrete projects within these themes. A programme manager joined in May 2024, a consultant in August 2024, a project manager in October 2024 and a further finance specialist in April 2025 forming the core project team. Additional resources for clearing the backlog accounts worked alongside operational teams and additional projects resources are in place for systems development.
2.4The Finance Improvement Programme was formally paused for two months during Q4 2024/25 to enable all resources to concentrate on budget and MTFS activity. Whilst the overall programme was paused, other significant projects that continued, included:
• Completion of the backlog of the accounts • Implementation of the Procurement Act • Scoping the internal controls activity for Unit 4 – the council’s HR and finance system
2.5Following this pause, the project team reviewed governance and implemented appropriate project governance. The governance sets out the scope, objectives, deliverables and benefits of each project, cross referencing to the CIPFA FM self-assessment completed in May 2025, the outstanding internal and external audit recommendations and Directions. To date, there are now 34 projects, 17 with formal project management in place, 10 in final drafting and the remaining still to be completed. There is a further opportunity to condense these projects into appropriate themes and is currently under review by the Corporate Resources management team.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.