Resolved
RESOLVED That the Project Plan be endorsed noting the need to consider the implications of "Lives not Services" approach, and that a further report be presented including the observations of Zürich.
Audit Committee decided this item on Monday 30 September 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Project Plan be endorsed noting the need to consider the implications of "Lives not Services" approach, and that a further report be presented including the observations of Zürich.
SOLIHULL METROPOLITAN BOROUGH COUNCIL
Report to: Audit Committee
Meeting date: 30th September 2013
Subject/Report Title: Annual Risk Management Report
Report from: Director of Governance
Report Author/Lead Jane Tattam Governance & Risk Management Advisor Contact Officer: 0121 704 8312, [email protected]
Wards affected: All Wards Bickenhill Blythe Castle Bromwich Chelmsley Wood Dorridge/Hockley Heath Elmdon Kingshurst/Fordbridge Knowle Lyndon Meriden Olton Shirley East Shirley South Shirley West Silhill Smith's Wood St Alphege
Public/Private Public report:
Exempt by virtue of N/A Paragraph:
1. Purpose of Report The purpose of this report is to inform Audit Committee about the review of the Council’s Risk Management Policy.
2. Decision(s) Recommended Audit Committee are asked to endorse the attached Project Plan and consider whether:
a) the Council’s current risk management approach continues to meet their needs? b) they are provided with all the information they need to fulfil their role? If not, what else do we need to provide? c) there is anything we could be doing differently or more efficiently? 3. Background 3.1 The Audit Committee has responsibility (set out in its Terms of Reference) to monitor the effective development and operation of the Council’s risk management arrangements.
3.2Whilst public resources are dwindling the challenge continues for the council to make the right decisions with less resources. This inevitably increases the exposure to various risks, with nationally several challenges made about the way local authorities have been making decisions in the light of more scarce resources.
3.3It is now some ten years since the Council first introduced a corporate approach to risk management. In that time, the Council has worked to develop a comprehensive and integrated approach to risk management and is now in a position where risk management is not an “add on” or a separate activity that happens once a year, but rather, it forms an integral part of the overall management approach of the Council. As a result: - staff are much clearer about what risk management is intended to achieve; - significant risks are continually being identified including those that have an impact on the Council’s long term future, like climate change; - staff can easily access training and guidance on risk management; - a common “risk language” has developed; and - risk management is seen as integral part of good corporate governance.
3.4Although the approach has been subject to regular review, it is now coming up for three years since our approach was last reviewed. As such, this review will seek to: - identify, through internal consultation and external challenge, whether our existing risk management arrangements continue to be proportionate and the most appropriate for the Council; - take account of changes in Adult Social Care and Public Health that have occurred since the last policy review; - re-consider communication/engagement with Members (as previously requested by Overview and Scrutiny Management Board; - look outside the organisation to consider other ways of working; - minimise the business cost of operating a risk management regime whilst maximising the use of the business intelligence it offers at an operational and corporate level.
3.5The review will include consultation with members, senior management, Internal Audit and other key stakeholders, culminating in a revised Policy from April 2014.
3.6For information a copy of the high level Project Plan is attached at Appendix A.
4. Evaluation of Alternative Option(s)
4.1Not applicable for this report.
5. Reasons for Recommending Preferred Option
5.1Not applicable for this report. 6. Scrutiny
6.1The project plan includes consultation with Overview and Scrutiny Management Board.
7. Implications
7.1Policy/Strategy Implications No direct implications for this particular report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Risk Management ReportReport | 37 KB | DownloadRead as text |
PDF |
Monitoring Report: Internal Audit AppendixAppendix | 48 KB | Download |
Follow Audit Committee at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2026 | Council’s Performance Management Framework - Annual UpdateRESOLVED Audit Committee reviewed and noted the report and asked for a more detailed presentation of the planning and... | Noted | Open |
| 20 Jul 2026 | Annual Report on Internal AuditRESOLVED Audit Committee: Noted the work of Internal Audit for 2025/26, detailed within the report, including the Hea... | Noted | Open |
| 20 Jul 2026 | Draft Annual Governance Statement for 2025-26RESOLVED Audit Committee endorsed the Council’s Annual Governance Statement. | Decided | Open |
| 20 Jul 2026 | Work ProgrammeRESOLVED Audit Committee approved the updated Work Programme, and noted the suggestions made in discussion. | Approved | Open |
| 17 Mar 2026 | 2025/26 Accounting PoliciesRESOLVED Audit Committee noted and considered the proposed Accounting Policies, accounting estimates and significant ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.