Overview and Scrutiny Management Board decided this item on Wednesday 4 December 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED i) That Officers report back to the Board’s meeting in February 2014 with a quantitative risk analysis of the various options, supported by the consultant’s report and, if possible, attendance by the consultant, and ii) Such report also to include detail on the systems in place with Network Rail to provide notification of any incidents.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1To provide an overview of the risk in relation to the structural integrity of the A45 South Bridge.
1.2To review the risk associated with the replacement of the A45 South Bridge, in relation to failing to deliver the project within the funding available.
2. Decision(s) Recommended
2.1OSMB are asked to consider the information provided. 3. Background
3.1The major A45 South Bridge Replacement Scheme has four main objectives:
Replacement of an old Bridge – to rectify all safety issues associated with the existing bridge, comprising inadequate width, the weak parapets and other structural defects.
Improve Safety - Provision of additional carriageway to reduce need for traffic from Junction 6 to the Clock Island to merge with through traffic on A45 and to increase overall traffic flow capacity at the junction. The proposed scheme will also provide safe pedestrian access along the A45 towards the Airport and improve the slip road into the Airport.
Support the economy – The strategically important economic assets served directly by the bridge are estimated to generate in excess of £2.5bn of GDP, supporting over 80,000 jobs. The proposed scheme will ensure ongoing and un-interrupted accessibility to an economically important location, resolve structural defects and minimise the impact of construction /works at this highly sensitive, and nationally important economic location. It will result in the economy will be supported and high productivity maintained.
Improving traffic movements – By providing a modern structure, the capacity constraints of the current bridge are removed. This is important in the light of its location at the heart of an area of economic and employment growth, with the key developments over the medium term.
The route is heavily trafficked at present with westbound counts showing average daily flows of 28-30,000 vehicles, with significant peaks in excess of this when major events are held at the NEC.
3.2Funding – the scheme is presently at Programme Entry stage in the Department for Transport (DfT) national major projects programme. We are due to make a submission to DfT in 2014 for final approval and confirmation of funding. The other contributions are detailed below :-
DfT Contribution £8,334,000
Birmingham Airport £1,600,000
Centro £2,000,000
Network Rail £200,000
TOTAL £12,134,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview & Scrutiny Work Plan 2015/16RESOLVED i ) That the list of potential topics for inclusion in Boards’ work plans be received, ii) That the subject ...
Adult Social Care Fees & Charges 2015/16RESOLVED i ) That the report, including the comments from the HWSB, be received, ii) That the fees and charges to be ...
Income Generation Task & Finish GroupRESOLVED i ) That the recommendations made by the TFG as printed below be supported: - a) That given the Council’s cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.