A45 SOUTH BRIDGE – CONFIRMATION OF PREFERRED BIDDER AND FINAL SUBMISSION TO DEPARTMENT FOR TRANSPORT.
AgreedCommittee1 paper
CPH Transport & Highways Decision Session agreed this item on Thursday 19 June 2014. Below is the council's own wording, with the papers it was decided on.
The Cabinet Member agreed that the Preferred Bidder is approved and then (subject to confirmation from DfT of final funding) a design and build contract is entered into with the preferred bidder for the delivery of the bridge replacement works.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
Report to CPH Transport & Highways Decision Session
Purpose of report
1.1To outline the process leading to the recommendation of a Preferred Bidder contractor for delivering the replacement bridge works for the A45 South Bridge Major Project taking into account the scheme budget, programme and risk allocation.
1.2To obtain approval from the Cabinet Member to a) the appointment of the Preferred Bidder contractor and to b) submit our final approval application to the Department for Transport ( DfT) for Final Approval of funding for the scheme and if approved, to enter into a design and build contract with the preferred bidder for delivery of the Major Project. 2. Decision(s) Recommended
2.1It is recommended that the Preferred Bidder is approved and then (subject to confirmation from DfT of final funding) a design and build contract is entered into with the preferred bidder for the delivery of the bridge replacement works.
Background
3.1The A45 South Bridge Replacement Major Scheme has four main objectives:
Replacing the old Bridge to deal with all safety issues associated with the existing bridge,
Improving Highway Safety by the provision of an additional carriageway lane and in this additional lane segregating traffic travelling from M42 Northbound into the Airport from other traffic. The proposed scheme will also provide a safe pedestrian access along the A45 towards the Airport and improve the slip road into the Airport,
Improving traffic capacity by the provision of an additional traffic lane and by increasing the widths of the current sub-standard width lanes.
Supporting the local economy - The proposed scheme will ensure ongoing and un-interrupted accessibility to an economically important national location,
3.2Construction Stages – The Works consist of the following four key stages:
Detailed design completion by December 2014, to enable a start on site in January 2015;
Between January 2015 and December 2015, the Contractor will construct an accommodation bridge alongside the existing A45 South Bridge structure and relocate the utilities from within the existing bridge either into the new accommodation bridge or into the existing A45 North bridge;
Demolition of the old structure (Christmas Day & Boxing Day 2015); and
Carrying out of the remaining works required to complete the new bridge structure to enable the new bridge to open in August 2016.
3.3Current Status – the scheme is presently at Programme Entry stage in the Department for Transport (DfT) national major projects programme.
Land has been secured for the works through a Compulsory Purchase Order process. Network Rail has been engaged to relocate a railway signal at an early stage. These two aspects have substantially reduced the risk to the scheme.
4. Tendering
4.1Process
The tendering process has followed the European Legislation with a notice submitted and published in the Official Journal of the European Union (OJEU). This is the publication in which all tenders from the public sector which are valued above a certain financial threshold according to EU legislation must be published.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CPH Transport & Highways Decision Session at Solihull and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.