Item5
Resolved
RESOLVED i. That the rephasing of the Corporate Capital Programme into 2014/15 and future years as set out in the report and Appendix A be approved; ii. That the revised capital programme for 2013/14, after rephasing, as detailed in Appendix B to the report be approved; iii. That the passporting of Government capital allocations for 2014/15 to individual cabinet portfolios for project allocation be approved; and iv. That the remaining drawdown of £0.340m of Prudential Borrowing to enable the capital works at Blythe Valley Innovation Centre to proceed be approved.
Word for word from the decision Solihull published for this meeting.
Source: democracy.solihull.gov.uk