The Cabinet Member for Resources: (i) Noted and approved the current status of the Capital ICT Projects Programme; (ii) Approved the balance of £27,472 from completed projects and £30,350 grant funding from Improvement and Efficiency West Midlands to be transferred to the ICT Projects fund; and (iii) Noted that the future improvement requirements of the Council will require an ICT capital budget for 2015/16 and beyond, for which there is currently no provision.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1The purpose of this report is to update the Cabinet Member for Resources on the current status of the Capital ICT Projects Programme. 2. Decision(s) Recommended
2.1To note the current status of the Capital ICT Projects Programme for approval and comment. 2.2 To approve the balance of £27,472 from completed projects and £30,350 grant funding from Improvement and Efficiency West Midlands to be transferred to the ICT Projects fund. 2.3 To note that the future improvement requirements of the Council will require an ICT capital budget for 2015/16 and beyond, for which there is currently no provision.
Background
3.1The Capital ICT Projects Programme for 2014-15 has a budget of £1,025,200. This includes provisions from the Oracle R12 upgrade programme of 2011, and some new capital provision approved by members at the start of the 2013/14 and 2014/15 financial years. Of this amount £373,000 is currently available for new projects. 3.2 The current project list which forms part of the Capital Programme, together with the funds allocated to the projects, the spend to date, and the status of the projects is shown in Appendix 1. 3.3 Two projects, the ‘case management system for Legal Services’, and the ‘Website Rebuild’ have now been successfully completed. These projects were completed within the allocated budget. 3.4 Other projects are progressing well. In particular, the Oracle exploitation programme has gathered pace following the recruitment of staff on temporary fixed term contracts to support this work. Work is now progressing on the specification for a corporate reporting solution to improve the availability of good quality management information across the Council, on extending the use of iExpenses across the Council to reduce the manual processing of expense claims, on replacing the corporate Purchase Card management system with a supported and more process efficient solution, and to grow the use of integrated web forms following the success of the web site pilot. New technology weblogic software is now available for the integrated web forms and this is described below. 3.5 Officers advise that there is a requirement to replace the Council’s Oracle reporting solution which is obsolete and will soon be unsupported by the supplier Oracle. Officers recommend that the procurement be funded from the ICT Projects Fund cost centre within the Capital ICT Projects Programme. The costs for such reporting solutions can vary however and it is not possible to state at this time how much such a solution will cost. Officers propose to seek approval from the Cabinet Member to procure the solution at a later date once costs are known. 3.6 Further funding has been received from Improvement and Efficiency West Midlands, following the completion of the pilot to roll out integrated web forms to the Council’s web site. This funding was provided on completion of the pilot to implement fully integrated forms for ‘missed bin collections’ and ‘bulky waste’.
4. Recent Investment Decisions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.