(i) That t he use of Council reserves as set out in the report to fund the detailed design; noting that these will be spent at risk until approval of the Full Business Case (FBC) be approved; and (ii) That delegated authority to the Director of Economy and Infrastructure, in consultation with the Leader, to enter into a Pre-Construction Services Agreement with Wilmott Dixon for the next stage of detailed design, subject to planning consent be approved.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1To provide an update on progress and to seek delegated approval, subject to planning consent, for the use of Council reserves to progress to detailed design.
2. Decision(s) recommended
2.1To approve:
(a) The use of Council reserves as set out in the report to fund the detailed design; noting that these will be spent at risk until approval of the Full Business Case (FBC).
(b) Delegate authority to the Director of Economy and Infrastructure, in consultation with the Leader, to enter into a Pre-Construction Services Agreement with Wilmott Dixon for the next stage of detailed design, subject to planning consent.
3. Matters for Consideration
Background 3.1 The aim of the Kingshurst project is to transform the Village Centre through the delivery of a thriving community and health-led regeneration scheme.
3.2Cabinet has previously received progress updates, most recently on July 15, 2021. Significant progress has been made since the last report which is summarised in the following sections.
Health and Community
3.2.1 CCL Solutions Ltd has been commissioned by the Clinical Commissioning Group and supported by the Council to proceed with the development of the Integrated Community, Health and Wellbeing Hub FBC. This FBC will robustly assess the community and health services to be delivered from the hub, including a suitable operating model, and this will feed into the wider project FBC.
3.2.2 Kingshurst library has been reconfigured to allow for community groups to make better use of it as a community building. Alongside this reconfiguration, as part of the cultural offer Parrabbola, the Council’s commissioned culture partner, is working with the community to develop a catalogue of stories and art that illustrates the depth of community cohesion and pride for the Kingshurst locality.
Acquisitions
3.2.3 In accordance with previous Cabinet approvals, a Compulsory Purchase Order (CPO) was made in March 2021 to facilitate the acquisition of all remaining land and property interests in the village centre. Two objections were initially received, however because of successful negotiations with the objectors, these have recently been withdrawn. The Planning Inspectorate has confirmed that the Council can confirm the Order as an unopposed Order.
3.2.4 As part of the Council’s commitment to retain key local services throughout the development period, IM Hadfield Opticians and Browns Pharmacy have been temporarily relocated to units that will not be required for redevelopment until the second phase of construction. In addition, the Post Office service which had closed as a result of Martins Newsagents’ decision to close their store, has now re-opened inside Browns Pharmacy with Council support.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.