(i) That it be approved to proceed with the refined phasing strategy to contribute to the local need for affordable housing and to respond positively to the challenges of rising inflation and market volatility, as set out in section 3 of the report; (ii) That it be agreed to delegate approval to the Director of Economy and Infrastructure, in consultation with the Leader of the Council, to enter into contract with Willmott Dixon for the construction of 25 social rented properties on the former Mountfort Pub site and associated highway section agreement works. This would be subject to completion of the value for money appraisal. Prior to entering into a contract, it be approved that the Director of Economy and Infrastructure provide a letter of intent to Willmott Dixon to allow instructions to be placed with utility providers; (iii) That the costs associated with the award of contract to Willmott Dixon and associated project costs be funded as set out at paragraph 6.3 of the report and in the private appendix be approved; (iv) That it be approved that authority is granted to the Director of Economy and Infrastructure and the Director of Resources ... view the full minutes text for item 9.
Word for word from the decision Solihull published for this meeting.Source: democracy.solihull.gov.uk
1.1The purpose of this report is to provide an update on progress and to seek approval for the use of Council reserves and borrowing to progress Phase 1 construction works on the former Mountfort Pub site. This will deliver 25 social rented dwellings and associated highway section agreement works.
2. Decision(s) Recommended
2.1That Cabinet approves the following:
2.1.1 To proceed with the refined phasing strategy to contribute to the local need for affordable housing and to respond positively to the challenges of rising inflation and market volatility, as set out in section 3 of this report.
2.1.2 To delegate approval to the Director of Economy and Infrastructure, in consultation with the Leader of the Council, to enter into contract with Willmott Dixon for the construction of 25 social rented properties on the former Mountfort Pub site and associated highway section agreement works. This is subject to completion of the value for money appraisal. Prior to entering into contract approve that the Director of Economy and Infrastructure provide a letter of intent to Willmott Dixon to allow instructions to be placed with utility providers. 2.1.3 That the costs associated with the award of contract to Willmott Dixon and associated project costs are funded as set out at paragraph 6.3 of this report and in the private appendix.
2.1.4 That authority is granted to the Director of Economy and Infrastructure and the Director of Resources and Deputy Chief Executive, in consultation with the Leader of the Council, to agree and sign any contractual arrangements associated with the award of grants from the Brownfield Land Release Fund, WMCA and Homes England, should any of these bids be successful.
2.2To delegate authority to the Director of Economy and Infrastructure, in consultation with the Cabinet member for Environment and Infrastructure to progress the Kingshurst Park and active travel improvements.
3. Matters for Consideration
Background
3.1The aim of the Kingshurst project is to transform the Village Centre through the delivery of a thriving community and health-led regeneration scheme.
3.2Full planning permission was granted on 27 April 2022 (Planning reference: PL/2021/03072/MAJFDW).
3.3Cabinet has previously received progress updates, most recently on 6 October 2022, where approval was granted for the part demolition of the existing parade and the commencement of associated enabling works. Significant progress has been made since the last report which is summarised in this report.
Acquisitions
3.4The Compulsory Purchase Order was confirmed on the 17 April 2023, with notices being posted on site and in the necessary media on the 11 May.
3.5All site acquisition in Kingshurst town centre is complete, except for the Diocese of Birmingham land, including the vicarage, which is expected to complete imminently. The vicarage is currently leased and is providing site accommodation to the Willmott Dixon site team.
Development Management
3.6Onsite demolition and enabling works are progressing well and projected to complete on time and to budget by the end of July 2023.
3.7The UK construction industry is experiencing an unprecedented amount of volatility causing significant price increases and, in some cases, an unwillingness for contractors to quote for works that have a long lead time. This challenge, together with an unsuccessful Levelling Up Fund (Round 2) bid last year, has led to a refined phasing strategy, as set out in Appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.