Solihull Metropolitan Borough Council
Cabinet, Thursday 15 June 2023 at 6.00pm

Kingshurst Village Centre Regeneration

Approved Executive 2 papers

Cabinet approved this item on Thursday 15 June 2023. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

(i) That it be approved to proceed with the refined phasing strategy to contribute to the local need for affordable housing and to respond positively to the challenges of rising inflation and market volatility, as set out in section 3 of the report; (ii) That it be agreed to delegate approval to the Director of Economy and Infrastructure, in consultation with the Leader of the Council, to enter into contract with Willmott Dixon for the construction of 25 social rented properties on the former Mountfort Pub site and associated highway section agreement works. This would be subject to completion of the value for money appraisal. Prior to entering into a contract, it be approved that the Director of Economy and Infrastructure provide a letter of intent to Willmott Dixon to allow instructions to be placed with utility providers; (iii) That the costs associated with the award of contract to Willmott Dixon and associated project costs be funded as set out at paragraph 6.3 of the report and in the private appendix be approved; (iv) That it be approved that authority is granted to the Director of Economy and Infrastructure and the Director of Resources ... view the full minutes text for item 9.
Word for word from the decision Solihull published for this meeting. Source: democracy.solihull.gov.uk

Follow this further

Built from Solihull's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1The purpose of this report is to provide an update on progress and to seek approval for the use of Council reserves and borrowing to progress Phase 1 construction works on the former Mountfort Pub site. This will deliver 25 social rented dwellings and associated highway section agreement works.

2. Decision(s) Recommended

2.1That Cabinet approves the following:

2.1.1 To proceed with the refined phasing strategy to contribute to the local need for affordable housing and to respond positively to the challenges of rising inflation and market volatility, as set out in section 3 of this report.

2.1.2 To delegate approval to the Director of Economy and Infrastructure, in consultation with the Leader of the Council, to enter into contract with Willmott Dixon for the construction of 25 social rented properties on the former Mountfort Pub site and associated highway section agreement works. This is subject to completion of the value for money appraisal. Prior to entering into contract approve that the Director of Economy and Infrastructure provide a letter of intent to Willmott Dixon to allow instructions to be placed with utility providers. 2.1.3 That the costs associated with the award of contract to Willmott Dixon and associated project costs are funded as set out at paragraph 6.3 of this report and in the private appendix.

2.1.4 That authority is granted to the Director of Economy and Infrastructure and the Director of Resources and Deputy Chief Executive, in consultation with the Leader of the Council, to agree and sign any contractual arrangements associated with the award of grants from the Brownfield Land Release Fund, WMCA and Homes England, should any of these bids be successful.

2.2To delegate authority to the Director of Economy and Infrastructure, in consultation with the Cabinet member for Environment and Infrastructure to progress the Kingshurst Park and active travel improvements.

3. Matters for Consideration

Background

3.1The aim of the Kingshurst project is to transform the Village Centre through the delivery of a thriving community and health-led regeneration scheme.

3.2Full planning permission was granted on 27 April 2022 (Planning reference: PL/2021/03072/MAJFDW).

3.3Cabinet has previously received progress updates, most recently on 6 October 2022, where approval was granted for the part demolition of the existing parade and the commencement of associated enabling works. Significant progress has been made since the last report which is summarised in this report.

Acquisitions

3.4The Compulsory Purchase Order was confirmed on the 17 April 2023, with notices being posted on site and in the necessary media on the 11 May.

3.5All site acquisition in Kingshurst town centre is complete, except for the Diocese of Birmingham land, including the vicarage, which is expected to complete imminently. The vicarage is currently leased and is providing site accommodation to the Willmott Dixon site team.

Development Management

3.6Onsite demolition and enabling works are progressing well and projected to complete on time and to budget by the end of July 2023.

3.7The UK construction industry is experiencing an unprecedented amount of volatility causing significant price increases and, in some cases, an unwillingness for contractors to quote for works that have a long lead time. This challenge, together with an unsuccessful Levelling Up Fund (Round 2) bid last year, has led to a refined phasing strategy, as set out in Appendix 1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet: Appendix 1: Indicative Phasing Plan FINALAppendix 18 MB Download
PDF
Kingshurst Village Centre RegenerationReport 205 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 16 attended
IC
Councillor Ian Courts Leader of the Council and Lead Member for Business and the EconomyCommittee Member, present
KG
Councillor Karen Grinsell Deputy Leader, Lead Member for Wellbeing, Skills & InclusionCommittee Member, present
TD
Councillor Tony Dicicco Adult Social Care and Health PortfolioCommittee Member, present
MG
Councillor Michael Gough Children & Education PortfolioCommittee Member, present
KH
Councillor Ken Hawkins Environment & Infrastructure PortfolioCommittee Member, present
AM
Councillor Andy Mackiewicz Climate Change, Planning & Housing PortfolioCommittee Member, present
MP
Councillor Mark Parker Housing PortfolioCommittee Member, present
WQ
Councillor Wazma Qais Communities & Leisure PortfolioCommittee Member, present
BS
Councillor Bob Sleigh OBE Resources Portfolio HolderCommittee Member, present
LM
Councillor Laura McCarthy Liberal Democrat Group Leader (Non-Voting Member)Committee Member, present
MM
Councillor Max McLoughlin Green Group Leader (Non-Voting Member)Committee Member, present
RB
Rebecca BoswellOfficer, expected

All 16 on the meeting page

On this subject at Solihull

Search all
  1. Kingshurst Village Centre RegenerationThis decision
  2. Kingshurst Village Centre Regeneration - Phase 2Agreed
  3. Kingshurst Village Centre RegenerationApproved
  4. Kingshurst Village Centre RegenerationApproved
  5. Kingshurst Village Centre RegenerationApproved
  6. Kingshurst Village CentreNoted

More from Solihull Cabinet

All decisions
MeetingDecisionOutcome
17 Sep 2026 Medium Term Financial Strategy (MTFS) update as at P4 (July 2026)RESOLVED that 1. the current financial position and actions being taken to address budget variances and determine whe... Approved Open
17 Sep 2026 Kingshurst Village Centre Regeneration - Phase 2It was agreed that a breakdown of the consultation sessions with residents would be shared with Members. RESOLVED tha... Agreed Open
17 Sep 2026 Exclusion of the Public and PressRESOLVED : That, pursuant to Section 100A (4) of the Local Government Act 1972, the press and public be now excluded ... Decided Open
23 Jul 2026 Medium term financial strategy and budget process 2027/28RESOLVED that the process outlined in the report for setting the 2027/28 budget and developing the Medium Term Financ... Approved Open
23 Jul 2026 Use of Strategic Community Infrastructure Levy FundsRESOLVED that: 1. the use of SCIL funding to fund the projects listed at paragraph 3.14 of the report be agreed; 2. i... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies