Turnpike Close Site Remediation works

Approved Executive 2 papers

Cabinet approved this item on Tuesday 12 July 2022. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Decision That Cabinet: 1. Approves an additional budget allocation of £150,000 for the remediation of the Council asset at Turnpike Close, Grantham and this allocation be funded from the Local Priorities Reserve. 2. Approves the remediation of the site and delegates authority to the Chief Executive and Section 151 Officer, in consultation with the Cabinet Member for Housing and Property, to confirm the appointment of a contractor to undertake the works within the budget envelope of £245,000. Alternative options considered and rejected Cabinet could have agreed to leave the site in its existing condition or undertake the works as part of a main contract at a later stage. Reason for decision In April 2021, the Council purchased land at Turnpike Close, Grantham, for the proposed relocation of its operational depot which was currently situated at Alexandra Road in Grantham. It had been identified through the lead consultant commissioned as part of procurement process associated with the acquisition of the land that the land required a significant amount of demolition and remediation works to prepare the site before any construction could commence. Two quotes for these remediation works had been received from contractors to date, however, it was proposed that the Council approached a framework to appoint a contractor so that site management and set up costs would be included as part of the contract and reduce costs, as opposed to including this in a main construction contract at a later stage. £95,000 was remaining in the budget originally allocated after deduction of legal fees, surveys and consultants’ fees. It was therefore proposed that the remaining balance was increased by a further £150,000 to provide a maximum budget envelope of £245,000 for the demolition and remedial works. The following comments were noted during discussion: · Clarification was sought as to whether this was the right time to commit to such expenditure when the total costs associated with the scheme were unknown. The demolition and remedial works needed to be undertaken before any further works could commence on the site. A point was made that, in the event that the proposed development of the site did not take place, the undertaking of these works would make the land more marketable to potential purchasers. It was considered more cost effective to procure these works now as opposed to paying potentially inflated rates at a later date as a result of the current economic climate and cost of living crisis · This represented a key project for the district, creating light industrial units and regeneration of a town centre site in Grantham
Word for word from the decision South Kesteven published for this meeting. Source: moderngov.southkesteven.gov.uk

Follow this further

Built from South Kesteven's papers

What the report saysPro

Report to Cabinet

Cabinet 12 July 2022

Report of: Councillor Robert Reid, Cabinet Member for Housing and Property

Remediation Costs for Turnpike Close, Grantham This report seeks approval for the budget required to remediate the Council owned site off Turnpike Close, Grantham.

Report Author

Debbie Roberts (Organisational Development Manager) 01476 406080 [email protected]

Corporate Priority: Decision type: Wards:

Clean and Sustainable Budget and Policy Grantham Earlesfield Environment Framework

Reviewed by: Alan Robinson (Deputy Chief Executive) 27 June 2022

Approved by: Karen Bradford (Chief Executive) 1 July 2022

Signed off by: Councillor Robert Reid, Cabinet Member for Housing 4 July 2022 and Property

Recommendation (s) to the decision maker (s)

1. The Cabinet approves an additional budget allocation of £150,000 for the remediation of the Council asset at Turnpike Close, Grantham. This allocation is to be funded from the Local Priorities Reserve.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
SITE PLANAppendix 1 347 KB Download
PDF
Turnpike Close Site Remediation worksReport 235 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at South Kesteven

Search all
  1. Turnpike Close Site Remediation worksThis decision
  2. Progress Update in respect of the construction of the Waste Depot, Turnpike Close GranthamAgreed
  3. Award of Contract for the Construction of the Waste Depot, Turnpike Close GranthamApproved
  4. Proposed Replacement Depot Turnpike Close GranthamRefused

More from South Kesteven Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 LGR - Response to Decision - Legal AdviceDecision Cabinet resolved to: A. Instruct the Director of Law and Governance to take all necessary and appropriate pr... Decided Open
21 Jul 2026 Warmer Homes GrantDecision That Cabinet: 1. Approve the acceptance of the additional £999k Warm Homes Social Housing Fund grant which h... Approved Open
21 Jul 2026 Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th... Approved Open
21 Jul 2026 2026/2027 Pay AwardDecision That Cabinet: Approved an additional budget of: · £214,000 from the Local Priorities Reserve to fund the Gen... Approved Open
21 Jul 2026 Refuse and Recycling Operational Policy UpdateDecision That Cabinet: Review and approve the updated Refuse and Recycling Operational Policy. Reasons for the decisi... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies