Decision That Cabinet: 1. Approves the contract award to D Brown Building Contractors Ltd to undertake works to facilitate and deliver the development of a 4-unit new build housing scheme at Elizabeth Road, Stamford for the sum of £665,952.28. 2. Agrees to delegate price variations to the contract of no greater than 10% to the Chief Finance Officer, in consultation with the Cabinet Member for Housing and Planning, due to the complexity of the new build and the associated price volatility. 3. Delegates the Chief Finance Officer in consultation with the Cabinet Member for Housing and Planning to enter into the contract with D. Brown Building Contractors Ltd. Alternative options considered and rejected The Council could have waited to commence the scheme or not build the apartments. Reasons for decision There was a housing need for the Council to develop the site, therefore the resolution was for the contract be awarded so that works could commence in Autumn 2023. The demand for one-bedroomed properties in Stamford was high, with around 250 people on the housing register requesting this type of property. Thanks were placed on record to the Housing team for identifying an appropriate development site, and for bringing the plans to Cabinet.
Word for word from the decision South Kesteven published for this meeting.Source: moderngov.southkesteven.gov.uk
This report sets out the proposals for a 4-unit new build social housing development at Elizabeth Rd, Stamford and to recommend that the new build contract be awarded to D.Brown Building Contractors Ltd.
Recommendations
That Cabinet: 1. Approves the contract award to D Brown Building Contractors Ltd to undertake works to facilitate and deliver the development of a 4-unit new build housing scheme at Elizabeth Rd, Stamford for the sum of £665,952.28. 2. Agrees to delegate price variations to the contract of no greater than 10% to the Chief Finance Officer, in consultation with the Cabinet Member for Housing and Planning, due to the complexity of the new build and the associated price volatility. 3. Delegates the Chief Finance Officer in consultation with the Cabinet member for Housing and Planning to enter into the contract with D Brown Building Contractors Ltd.
Decision Information
Does the report contain any No exempt or confidential information not for publication?
What are the relevant corporate Supported Housing for all priorities? Which wards are impacted? Stamford
1. Implications
Taking into consideration implications relating to finance and procurement, legal and governance, risk and mitigation, health and safety, diversity and inclusion, safeguarding, staffing, community safety, mental health and wellbeing and the impact on the Council’s declaration of a climate change emergency, the following implications have been identified:
Finance and Procurement
1.1The delivery of this scheme is a key element of the new build programme or the Housing Revenue Account (HRA). The budget for this proposal is included in the 2022-2023 and 2023-2024 capital programme and is funded from the Capital Receipts Reserve. The delivery of 4 units will provide a rental income stream to the HRA and will be built in the HRA financial business plan. Based on a comparable affordable rental figure of £83.46 per week, this will generate an annual rental of £16,024 per annum (based on 48 rent week). This is a return on investment of 2.41% and this is broadly in line with social housing returns.
Completed by: Richard Wyles, Chief Finance Officer
Legal and Governance
1.2The necessary processes have been followed in accordance with the Council’s Contract Procedure Rules. There are no further significant legal, or governance implications not already highlighted within the body of the report. Completed by: Graham Watts, Assistant Director of Governance and Monitoring Officer
Risk and Mitigation
1.3A project risk register will be created in partnership between the contractor and the Council, which will be subject to robust review as the project progresses. As part of the process there will be a mutual agreement of the identified risks and enable confirmation of ownership to be confirmed by the contractor of the Council.
1.4The contractor will be responsible for insuring the build until the development is handed over to the Council.
Completed by: Tracey Elliott, Governance and Risk Officer
2. Background to the Report
2.1The proposed site, outlined in red in Appendix 1, is situated on Elizabeth Road in Stamford, Lincolnshire. The total area of the site is 586m² (0.059 hectares).
2.2This site is owned by South Kesteven District Council and is accessed off Elizabeth Road. The site comprises of a large area of hardstanding which is currently used by surrounding residents for parking and also provides vehicular access to the adjacent property to the south.
2.3The development looks to introduce four one- bed, two-person apartments along with associated landscaping, parking and refuse provision. The access to the adjacent property will be retained. Appendix 2 and 2B show the proposed development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Small Unmanned Aircraft (Drone) PolicyDecision That Cabinet: a) Approves the policy and the use of Drones for specified works. b) Delegates authority to th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.